New Gurgaon

Gurgaon

On the map

Overview

RERA projects
148
+95 not yet checked
Median ₹/sq ft
₹15,000
apartments, ₹11,000–18,000
Past RERA date
28 (19%)
neither ready to move nor cancelled
Since launch
+11%
median change, 17 projects
Due 2026–2028
2,196 homes
in 48 projects, by RERA date
Builders
64
Most active: DLF, Signature Global
Sectors
20
Projects by stage
  • 8 new launch
  • 55 under construction
  • 74 ready to move
  • 9 stalled or on hold

Projects

148 projects checked by our team

See all 74

Sort byNamePrice₹/sq ftRERA date

  • Ready to moveResidential

    County The Centre Court

    County Group, Sector 88A

    ₹14,500/sq ft3% below the area

    Homes
    3 BHK
    Price
    ₹2.27–3.15 Cr
    RERA date
    Sep 2025
    Size
    4 towers, 464 homes
  • Ready to movePlots/Floors/Villas

    ₹14,000/sq ft

    Homes
    3 BHK
    Price
    ₹2.24 Cr
    RERA date
    Oct 2028
  • Ready to moveResidential

    Godrej Air Phase 1

    Godrej, Sector 85

    ₹15,000/sq ftat the area median

    Homes
    2, 3, 4 BHK
    Price
    ₹2.11–3.9 Cr
    RERA date
    Jun 2025
    Size
    1 tower, 179 homes
  • Ready to moveResidential

    Godrej Air Phase 2

    Godrej, Sector 85

    ₹15,000/sq ftat the area median

    Homes
    2, 3, 4 BHK
    Price
    ₹2.11–3.9 Cr
    RERA date
    Sep 2027
    Size
    2 towers, 222 homes
  • Ready to moveResidential

    Godrej Air Phase 3

    Godrej, Sector 85

    ₹15,000/sq ftat the area median

    Homes
    2, 3, 4 BHK
    Price
    ₹2.11–3.9 Cr
    RERA date
    Sep 2023registration lapsed
    Size
    2 towers, 200 homes
  • Ready to moveCommercial

    Godrej Air Phase 4

    Godrej, Sector 85

    RERA date
    Dec 2022registration lapsed
    Size
    7 homes
  • No photo yet
    Ready to movePlots/Floors/Villas

    102 Eden Estate Ii

    COUNTRYWIDE PROMOTERS PRIVATE LIMITED, Sector 102

    RERA date
    Mar 2025registration lapsed
  • No photo yet
    Ready to moveCommercial

    83 Avenue

    REAL TOWN PROPERTIES PVT LTD, Sector 83

    RERA date
    Sep 2020
  • No photo yet
    Ready to moveCommercial

    83 Metro Street

    S.V HOUSING PVT. LTD., Sector 83

    RERA date
    Mar 2021registration lapsed
  • No photo yet
    Ready to moveResidential

    Aangan

    ALTON BUILDTECH INDIA PVT. LTD., Sector 88A

    RERA date
    Dec 2022registration lapsed
  • No photo yet
    Ready to movePlots/Floors/Villas

    Ace Palm Floors

    ACE Group, Sector 89

    RERA date
    Jun 2023registration lapsed
  • No photo yet
    Ready to moveResidential

    Adani Aangan

    ALTON BUILDTECH INDIA PVT. LTD., Sector 88A

    RERA date
    Dec 2022
  • See all 74 projects
All 74 projects by nameA to Z, each linked to its project page
95 more RERA projects here, not yet checked by our teamFound by their RERA address or map point. Not counted in the numbers on this page.
  • Ace Palm Floors
    ACE Group, SECTOR 89-90, GURUGRAM
    RERA completion 31 Dec 2021; registration lapsed; address names Sector 89
  • Amb Selfie Walk
    AMB INFRABUILD PRIVATE LIMITED, VILLAGE HAYATPUR, SECTOR 88
    RERA completion 30 Jun 2028; address names Sector 88
  • Aspiration
    VATIKA LIMITED, SECTOR - 88B
    RERA completion 29 Jun 2025; address names Sector 88B
  • Avenue 81
    M/S GLS INFRACON PVT. LTD., SECTOR 81,GURUGRAM, SITUATED IN THE REVENUE ESTATE OF VILLAGE NAWADA FATEHPUR, DISTRICT GURUGRAM, HARYANA
    RERA completion 31 Dec 2025; address names Sector 81
  • City Centre 92
    SHISHTA BUILDWELL LLP, VILLAGE-MEKWA , SECTOR-92,GURUGRAM, HARYANA
    RERA completion 31 Dec 2032; address names Sector 92
  • Devasya Bharat
    DEVASYA DEVELOPERS PVT. LTD (FORMERLY KNOWN AS NEXT GENERATION PROJECTS PVT LTD), SECTOR 88A, GURUGRAM
    RERA completion 30 Sep 2033; address names Sector 88A
  • Flora Avenue 88a
    GCC INFRA, SECTOR-88A
    RERA completion 5 Jan 2028; address names Sector 88A
  • Gls Courtyard
    GLS Infra, REVENUE ESTATE OF VILLAGE DHORKA, SECTOR 95, GURUGRAM, HARYANA
    RERA completion 10 Jul 2028; address names Sector 95
  • Godrej Oasis
    Godrej, SECTOR 88-A & 89-A, HARSARU, GURUGRAM
    RERA completion 30 Sep 2019; address names Sector 88
  • Gratitude 84
    LAMOSE INFRA LLP, SECTOR 84, VILLAGE SIKANDEPUR BADHA, GURUGRAM
    RERA completion 30 Apr 2032; address names Sector 84
  • Green Court
    ASTER INFRAHOME PVT. LTD., SECTOR-90, VILLAGE- HAYATPUR, GURUGRAM
    RERA completion 22 Jul 2024; address names Sector 90
  • Group Housing Colony
    ADANI M2K PROJECTS LLP, KHEDKI MAZRA, SECTOR 102/102A, GURUGRAM
    RERA completion 30 Sep 2019; address names Sector 102
  • Hero Earth Commercial Shops
    Hero Homes, SECTOR 85, VILLAGE SIKANDARPUR BADHA, GURGRAM-122004
    RERA completion 30 Jun 2027; address names Sector 85
  • High Street (Phase I)
    VATIKA LTD., SECTOR-83, VILLAGE SHIKOHPUR, SUB-TEHSIL MANESAR, DIST. GURUGRAM
    RERA completion 2 Oct 2022; registration lapsed; address names Sector 83
  • Imperial Garden
    EMAAR MGF LAND LTD, SECTOR-102, KHERKI DAULLA, GURUGRAM
    RERA completion 31 Dec 2019; address names Sector 102
  • Imperial Garden Phase 2
    EMAAR MGF LAND LTD., SECTOR- 102, GURUGRAM
    RERA completion 17 Oct 2018; address names Sector 102
  • Independent Floors At Dlf Gardencity Sector 91/92
    DLF, DLF GARDEN CITY, SECTOR 91 / 92,
    RERA completion 21 Jun 2024; address names Sector 91
  • Independent Floors At Dlf Gardencity Sector 91/92
    DLF, DLF GARDEN CITY, SECTOR 91 / 92,
    RERA completion 20 Jun 2024; address names Sector 91
  • India Rashtra
    NEXT GENERATION PROJECTS PVT LTD, SECTOR 88A
    RERA completion 30 Nov 2026; address names Sector 88A
  • India Worldmart
    BETTERCHOICE REALTORS PRIVATE LIMITED, SECTOR- 88A
    RERA completion 31 Dec 2029; address names Sector 88A
  • Ivory Arches
    ZAKSPACES & INTERIORS PRIVATE LIMITED, VATIKA INDIA NEXT-II, SECTOR 88B
    RERA completion 30 Sep 2029; address names Sector 88B
  • Jms Group Capital Square
    JMS, SECTOR 95, VILLAGE-WAZIRPUR
    RERA completion 31 Mar 2028; address names Sector 95
  • Jms Group Premier Floors-Ii
    JMS, SECTOR 95, VILLAGE-WAZIRPUR
    RERA completion 31 Dec 2026; address names Sector 95
  • Jms Group Pride Avenue
    JMS, SECTOR 95-A, VILLAGE-WAZIRPUR
    RERA completion 30 Sep 2027; address names Sector 95
  • Kashi Residences
    Ganga Realty, VILLAGE BADHA AND HAYATPUR, SECTOR 89 & 93
    RERA completion 5 Jan 2028; address names Sector 89
  • Klj Square ( Commercial Project)
    KLJ REALTECH PRIVATE LIMITED, SECTOR-83, SHIKOHPUR, GURUGRAM
    RERA completion 30 Jun 2024; address names Sector 83
  • Landmark Avana
    Landmark Group, SECTOR 95, GURUGRAM
    RERA completion 29 Jan 2028; address names Sector 95
  • Landmark Avana - 1st Phase
    Landmark Group, SECTOR 95, GURUGRAM
    RERA completion 31 Jul 2027; address names Sector 95
  • Landmark The Homes 81
    Landmark Group, SECTOR 81, GURUGRAM
    RERA completion 28 Feb 2026; address names Sector 81
  • Lifestyle Homes
    VATIKA LTD., SECTOR 83, VILLAGE HARSARU, GURUGRAM
    RERA completion 31 Dec 2019; registration lapsed; address names Sector 83
  • M3m 84 Market
    M3M INDIA PRIVATE LIMITED, SECTOR-84, GURUGRAM
    RERA completion 30 Apr 2023; address names Sector 84
  • Maceo
    ANANT RAJ LTD., SECTOR-91, MANESAR, GURUGRAM
    RERA completion 17 Aug 2020; address names Sector 91
  • Mahira Homes 88b
    MAHIRA HOMES PVT LTD, VILLAGE- HARSARU , SECTOR - 88B
    RERA completion 31 Dec 2026; address names Sector 88B
  • Market City
    Orris, SECTOR - 89,90 ,GURUGRAM
    RERA completion 31 Dec 2026; address names Sector 89
  • Microtek Success Hub
    Microtek, VILLAGE WAZIRPUR SECTOR 95-A GURUGRAM
    RERA completion 31 Jul 2025; address names Sector 95
  • Mohinder Kaur & Others
    SPAZE TOWERS PVT. LTD., SECTOR 84, VILLAGE SIHI, GURUGRAM, HARYANA
    RERA completion 30 Dec 2020; address names Sector 84
  • Mrg Primark
    MRG Group, VILLAGE BADHA, SECTOR-90, GURUGRAM
    RERA completion 31 Jul 2027; address names Sector 90
  • Orchard Avenue - 3
    SIGNATURE BUILDERS PRIVATE LIMITED, VILLAGE - HAYATPUR, SECTOR -93, GURUGRAM, HARYANA
    RERA completion 31 Jul 2028; address names Sector 93
  • Orchard Avenue 2
    SIGNATURE BUILDERS PRIVATE LIMITED, VILLAGE HAYATPUR SECTOR 93 GURUGRAM HARYANA
    RERA completion 30 Sep 2024; address names Sector 93
  • Oyster Arcade
    ADANI M2K PROJECTS LLP, VILLAGE KHERKI MAJRA, SECTOR 102 GURUGRAM
    RERA completion 24 Nov 2025; address names Sector 102
  • Oyster Grande-Tower G
    ADANI M2K PROJECTS LLP, SECTOR 102/102A, VILLAGE KHEDKI MAZRA, GURUGRAM
    RERA completion 30 Sep 2024; registration lapsed; address names Sector 102
  • Palm Gardens
    EMAAR MGF LAND LTD., SECTOR-83, VILLAGE KHERKI DAULLA, GURUGRAM, HARYANA
    RERA completion 31 Dec 2019; address names Sector 83
  • Park Street
    KS PROPMART PVT. LTD., SECTOR-85, GURUGRAM
    RERA completion 30 Jun 2023; registration lapsed; address names Sector 85
  • Phase-Iii Part - 2 - (Block T5 - Tower T6, T7, T8, T9, T10, T11, T12) & (Block T4 -Tower T14)
    Saare Homes, SECTOR-92
    RERA completion 31 Dec 2030; address names Sector 92
  • Premier Floors
    JMS INFRA REALITY PVT. LTD., SECTOR 95, VILLAGE-WAZIRPUR
    RERA completion 31 Dec 2026; address names Sector 95
  • Raheja Market Sector- 83 & Raheja Market Sector- 84
    RAHEJA DEVELOPERS LIMITED, VILLAGE SIHI, SECTOR-83 & 84
    RERA completion 13 Sep 2024; registration lapsed; address names Sector 83
  • Raheja Trinity
    Raheja Developers, SECTOR-84, GURUGRAM
    RERA completion 25 Jul 2022; registration lapsed; address names Sector 84
  • Rama Homes
    Pareena, VILLAGE HAYATPUR SECTOR 89
    RERA completion 11 Aug 2026; address names Sector 89
  • Ramprastha City - Sector 92, 93 & 95
    Ramprastha, SECTOR 92, 93 & 95 GURUGRAM
    RERA completion 31 Dec 2024; registration lapsed; address names Sector 92
  • Rof Aalayas Phase Ii
    ROF, SECTOR-102, GURUGRAM
    RERA completion 2 Jul 2023; address names Sector 102
  • Rof Atulyas
    ROF, VILLAGE HYATPUR, SECTOR 93
    RERA completion 31 Dec 2025; address names Sector 93
  • Rof Insignia Park
    DIVERSE DEVELOPERS LLP, VILLAGE- BADHA &HAYATPUR, SECTOR-93
    RERA completion 31 May 2026; address names Sector 93
  • Rof Insignia Park 88
    ROF, VILLAGE- HARSARU, SECTOR-88A, DISTRICT- GURUGRAM, HARYANA
    RERA completion 31 Dec 2027; address names Sector 88A
  • Rof Insignia Park Ii
    ROF, VILLAGE-WAZIRPUR, SECTOR-95
    RERA completion 24 May 2027; address names Sector 95
  • Rof Insignia Souk
    DIVERSE DEVELOPERS LLP, SECTOR-93, BADHA
    RERA completion 31 Mar 2026; address names Sector 93
  • Rof Pravasa
    ROF, VILLAGE HARSARU, SEC-88A, GURUGRAM
    RERA completion 30 Apr 2030; address names Sector 88A
  • Sapphire 84
    Ameya, SECTOR - 84, REV ESTATE OF OF VILLAGE HAYATPUR, GURUGRAM, HARYANA
    RERA completion 30 Nov 2028; address names Sector 84
  • Sapphire Eightythree
    SAPHIRE LANDCRAFT PVT. LTD., SECTOR 83, VILLAGE SIHI, DISTRICT GURUGRAM, HARYANA
    RERA completion 31 Mar 2018; address names Sector 83
  • Sapphire Ninety
    CROWN PROPBUILD PVT.LTD, SECTOR-90, VILLAGE NAWADA FATEHPUR
    RERA completion 30 Jun 2020; address names Sector 90
  • Seven Elements
    Vatika, SECTOR 89-A, VILLAGE HARSARU AND HAYATPUR, GURUGRAM
    RERA completion 31 Jan 2026; address names Sector 89
  • Shanti Vihar ( Tower A To R)
    ARMY WELFARE HOUSING ORGANISATION, SECTOR-95, WAZIRPUR
    RERA completion 31 Dec 2020; address names Sector 95
  • Shree Vardhman Flora
    SHREE VARDHMAN INFRAHOME PVT. LTD, SECTOR 90, HAYATPUR, GURUGRAM
    RERA completion 30 Jun 2019; registration lapsed; address names Sector 90
  • Signature Global City 81
    STERNAL BUILDCON PRIVATE LIMITED, VILLAGE NAKHDOLA, SECTOR 81
    RERA completion 27 Feb 2025; registration lapsed; address names Sector 81
  • Signature Global City 81
    STERNAL BUILDCON PRIVATE LIMITED, VILLAGE NAKHDOLA, SECTOR 81
    RERA completion 28 Jun 2025; address names Sector 81
  • Signature Global City 92
    SIGNATURE INFRBUILD PVT. LTD., VILLAGE MEVKA, WAZIRPUR, SECTOR-92, GURUGRAM
    RERA completion 29 Dec 2025; address names Sector 92
  • Signature Global City 92
    SIGNATURE INFRBUILD PVT. LTD., VILLAGE MEVKA, WAZIRPUR, SECTOR-92, GURUGRAM
    RERA completion 28 Apr 2025; registration lapsed; address names Sector 92
  • Signature Global City 92-(Ii)
    SIGNATURE INFRABUILD PVT. LTD., VILLAGE MEVKA, WAZIRPUR, SECTOR-92, GURUGRAM
    RERA completion 30 Mar 2026; address names Sector 92
  • Signature Global City 93
    SIGNATURE BUILDERS PRIVATE LIMITED, VILLAGE WAZIRPUR, SECTOR 93, GURUGRAM, HARYANA
    RERA completion 29 Apr 2026; address names Sector 93
  • Signature Global Superbia
    STERNAL BUILDCON PRIVATE LIMITED, VILLAGE DHORKA, SECTOR 95, GURUGRAM, HARYANA
    RERA completion 30 Dec 2025; address names Sector 95
  • South Avenue
    M/S GLS INFRAPROJECTS PVT. LTD, SOUTH AVENUE, VILLAGE WAZIRPUR, SECTOR-92
    RERA completion 31 Aug 2024; address names Sector 92
  • Ss Linden
    SS Group, SECTOR-84 & 85, GURUGRAM
    RERA completion 31 Dec 2026; address names Sector 84
  • Ss Linden Residential Floors
    SS Group, SS LINDEN, SECTOR-84
    RERA completion 28 Feb 2025; registration lapsed; address names Sector 84
  • SS The Coralwood and Almeria
    SS Group, SECTOR 84, VILLAGE SIHI,GURUGRAM,HARYANA
    RERA completion 31 Dec 2019; registration lapsed; address names Sector 84
  • Street Drive-93
    GGANBU LAND PRIVATE LIMITED, SECTOR-93, GURUGRAM
    RERA completion 31 Dec 2028; address names Sector 93
  • Synera
    SIGNATUREGLOBAL DEVELPERS PVT. LTD, SECTOR-81, GURURGAM
    RERA completion 31 May 2021; address names Sector 81
  • The Ark
    HERO REALTY PRIVATE LIMITED, SECTOR 85, VILLAGE SIKANDARPUR BADHA, GURGRAM-122004
    RERA completion 30 Jun 2025; address names Sector 85
  • The Balcony
    PYRAMID PROPMOTO PVT. LTD., SECTOR-93, GURUGRAM
    RERA completion 3 Jan 2024; registration lapsed; address names Sector 93
  • The Meridian
    MRG INFRABUILD PVT. LTD., SECTOR-89, VILLAGE HAYATPUR, GURUGRAM
    RERA completion 24 Mar 2025; registration lapsed; address names Sector 89
  • The Nation
    JMS INFRA REALITY PRIVATE LIMITED, SECTOR 95, WAZIRPUR
    RERA completion 31 Jan 2027; address names Sector 95
  • The Nation
    JMS, SECTOR 95, VILLAGE- WAZIRPUR
    RERA completion 31 Dec 2026; address names Sector 95
  • The Pearl
    JMS INFRA REALITY PVT. LTD., SECTOR- 95,
    RERA completion 29 Feb 2028; address names Sector 95
  • Town Square (Block D)
    VATIKA LTD., SECTOR -82-A, VILLAGE SHIKOHPUR, TEHSIL MANESAR,DISTRICT GURUGRAM, HARYANA
    RERA completion 31 Dec 2018; registration lapsed; address names Sector 82
  • Town Square-2
    VATIKA LIMITED, VILLAGE SHIKOHPUR SECTOR 82
    RERA completion 31 Mar 2022; address names Sector 82
  • Tristaar
    SPAZE TOWERS PVT. LTD., SEC-92, VILLAGE DHORKA
    RERA completion 30 Jun 2020; address names Sector 92
  • Ultimus
    B D INFRADEVELOPERS PRIVATE LIMITED, VILLAGE BADHA, SECTOR 90, GURUGRAM
    RERA completion 29 Jun 2025; address names Sector 90
  • Ultimus 2.0
    MRG WORLD LLP, SECTOR 90 GURUGRAM
    RERA completion 14 Jul 2026; address names Sector 90
  • Urban Homes-Ii Extension
    PYRAMID INFRATECH PRIVATE LIMITED, VILLAGE BADHA, SECTOR-86
    RERA completion 15 Nov 2023; address names Sector 86
  • Vatika India Next (Phase-Ii)
    Vatika, VILLAGE SIHI, SHIKOHPUR, SIKANDERPUR BADHA, & KHERKIDAULA, SECTOR- 81-85
    RERA completion 31 Mar 2029; address names Sector 81
  • Verde 92
    WAL, VILLAGE DHORKA, SECTOR-92, GURUGRAM
    RERA completion 9 Jul 2029; address names Sector 92
  • Vipul Lavanya Apartments-Tower 2&3
    Vipul, SECTOR-81,GURUGRAM
    RERA completion 31 Aug 2019; registration lapsed; address names Sector 81
  • Vista Avenue
    PEERAGE BUILDWELL PRIVATE LIMITED, VILLAGE-BADHA & HAYATPUR, SECTOR-89, GURUGRAM, HARYANA
    RERA completion 30 Nov 2030; address names Sector 89
  • Vista Centre
    RECEPTIVE BUILDWELL LLP, VILLAGE-BADHA , SECTOR-89,GURUGRAM, HARYANA
    RERA completion 31 Dec 2032; address names Sector 89
  • Vista Corner
    COPIOUS REALTORS PRIVATE LIMITED, VILLAGE- BADHA, SECTOR-89, GURUGRAM, HARYANA
    RERA completion 30 Sep 2027; address names Sector 89
  • Wal Street 88a
    WAL, SECTOR-88A, VILLAGE-HARSARU, GURUGRAM
    RERA completion 15 Nov 2029; address names Sector 88A
  • Woodview Residencies
    Orris, SECTOR 89-90, GURUGRAM
    RERA completion 15 Jul 2023; registration lapsed; address names Sector 89

Comparing projects in New Gurgaon? A ReraTracker advisor can talk you through RERA dates, builders and prices.

Prices

Builder asking prices for apartments from 23 projects, updated Oct 2025–Sep 2026.

Median ₹/sq ft
₹15,000
Lowest ₹11,000Highest ₹18,000
Since launch
+11%
median change, 17 projects

Homes by size

From the unit types builders list. Carpet efficiency is the carpet area as a share of the area you pay for.

  • 2 BHK

    6 projects

    ₹2.11–2.9 Cr

    Carpet
    894 sq ft
    Efficiency
    64%
    ₹/carpet sq ft
    ₹23,591
  • 3 BHK

    19 projects

    ₹1.59–5.17 Cr

    Carpet
    1,161 sq ft
    Efficiency
    56%
    ₹/carpet sq ft
    ₹26,577
  • 4 BHK

    11 projects

    ₹3.42–6.55 Cr

    Carpet
    1,654 sq ft
    Efficiency
    56%
    ₹/carpet sq ft
    ₹27,885

Delivery record

RERA completion dates after extensions, from the RERA filings.

Past RERA date
28
neither ready to move nor cancelled
With a RERA date
147
of 148 projects
Registration lapsed
32
as marked by HRERA

Projects due each year

Due 2026–2028: 48 projects, 2,196 homes

By RERA completion year. Hatched columns are years already past.

  1. 2019: 2 projects, past
  2. 2020: 11 projects, 420 homes, past
  3. 2021: 4 projects, past
  4. 2022: 6 projects, 7 homes, past
  5. 2023: 6 projects, 200 homes, past
  6. 2024: 16 projects, past
  7. 2025: 32 projects, 643 homes, past
  8. 2026: 20 projects
  9. 2027: 14 projects, 1,102 homes
  10. 2028: 14 projects, 1,094 homes
  11. 2029: 6 projects, 1,336 homes
  12. 2030: 5 projects, 796 homes
  13. 2031: 5 projects, 2,785 homes
  14. 2032: 5 projects, 2,630 homes
  15. 2033: 1 project, 344 homes

Builders here

Most projects first. A chip marks projects past their RERA date, lapsed or extended; no chip means none.

Show all 64 builders
  • GCC INFRA3 projects
    3 past date1 lapsed
  • GLS INFRAPROJECTS PVT. LTD.3 projects
    2 past date
  • SIGNATURE INFRABUILD PVT. LTD.3 projects
    1 lapsed
  • Smartworld3 projects
    1 past date
  • ADHIKAANSH REALTORS PRIVATE LIMITED ,AAWAM RESIDENCY PRIVATE LIMITED2 projects
    1 past date1 lapsed
  • ALTON BUILDTECH INDIA PVT. LTD.2 projects
    1 lapsed
  • Ameya2 projects
    2 lapsed
  • BPTP2 projects
  • COUNTRYWIDE PROMOTERS PRIVATE LIMITED2 projects
    1 past date1 lapsed
  • GLS Infra2 projects
    1 past date1 lapsed
  • JMS2 projects
  • SOLUTREAN BUILDING TECHNOLOGIES PVT LTD2 projects
    1 past date
  • VATIKA LIMITED2 projects
    1 past date1 lapsed
  • 3b Realty1 project
  • ACE Group1 project
    1 lapsed
  • AIPL1 project
  • AMB INFRAVENTURES PVT LTD1 project
  • ARTTECH ELEGANT HOMES LLP1 project
  • AURA BUILDERS AND DEVELOPERS PRIVATE LIMITED1 project
  • BD INFRADEVELOPERS LLP1 project
    1 past date
  • Breez1 project
  • CHIRAG BUILDTEC PRIVATE LIMITED1 project
  • County Group1 project
  • DREAMHOME INFRASTRUCTURE PVT. LTD.1 project
    1 past date
  • ELAN1 project
  • ELAN BUILDCON PVT. LTD.1 project
  • EMAAR MGF LAND LTD.1 project
  • EMPERIUM INFRASTRUCTURE PRIVATE LIMITED1 project
  • FIDATOCITY HOMES PRIVATE LIMITED1 project
  • GLS INFRACON PVT. LTD.1 project
  • HCBS1 project
  • JMS BUILDTECH PVT. LTD1 project
  • JMS BUILDTECH PVT. LTD./RAMAPRASTHA ESTATE PVT. LTD.1 project
  • MANISH BUILDWELL PVT. LTD.1 project
    1 past date1 lapsed
  • Microtek1 project
  • NANI RESORTS & FLORICULTURE PVT. LTD.1 project
    1 lapsed
  • NORTH STAR TOWERS PRIVATE LIMITED1 project
  • ORA LAND AND HOUSINGPRIVATE LIMITED1 project
  • Orris1 project
  • PEGASUS DEVELOPERS PRIVATE LIMITED1 project
    1 past date
  • RADHA ESTATES PVT. LTD. ,ORRIS INFRASTRUCTURES PVT. LTD. & THREE C SHELTERS PVT. LTD.1 project
    1 lapsed
  • REAL TOWN PROPERTIES PVT LTD1 project
  • ROF1 project
    1 past date
  • S.V HOUSING PVT. LTD.1 project
    1 lapsed
  • SAAN PROCON PVT. LTD.1 project
  • SARE GURUGRAM PRIVATE LIMITED1 project
  • Satya Group1 project
  • SIGNATURE BUILDERS PRIVATE LIMITED1 project
  • Silverglades1 project
  • STERNAL BUILDCON PRIVATE LIMITED1 project
  • SUNCITY PROJECTS PVT LTD1 project
  • Trehan IRIS1 project

Sectors

Our team defines each micro-market by its sectors; a sector can belong to more than one. Prices are the median apartment ₹/sq ft where 3 or more projects list one.

Most projects first; deeper tiles have more.

  • Sector 102

    11 projects₹17,500/sq ft

    Also in Dwarka Expressway

  • Sector 88A

    10 projects

  • Sector 89

    9 projects

  • Sector 85

    8 projects₹15,000/sq ft

  • Sector 92

    8 projects

  • Sector 95

    7 projects

  • Sector 83

    6 projects

  • Sector 93

    6 projects₹14,000/sq ft

Show all 17 sectors
  • Sector 84

    4 projects

  • Sector 86

    4 projects

  • Sector 91

    4 projects

  • Sector 81

    3 projects

  • Sector 89A

    3 projects

  • Sector 88

    2 projects

  • Sector 82

    1 project

  • Sector 88B

    1 project

  • Sector 90

    1 project

Also covers sectors 81A, 87 and 94, with no checked projects yet.

60 projects with no recorded sector of this micro-market.

What’s around

Named places inside the micro-market, then those within 1 km of its edge.

2 railway stations

Within 1 km:
  • Garhi Harsaru Junction
  • Basai Dhankot

2 hospitals

Within 1 km:
  • Queen’s Multispeciality Hospital
  • S.R.S. Hospital and Critical Care Unit

1 mall

  • Satya The Hive

Map data © OpenStreetMap contributors. Outlines are approximate.

News

About projects here first, then about builders active here.

  • 13 Mar 2026

    Haryana RERA Order Elan Buildcon: Haryana RERA orders Elan Buildcon to pay fixed returns, execute conveyance deed in Gurugram commercial unit case (opens in a new tab)

    Haryana RERA Order Elan Buildcon: H-RERA Gurugram has ordered Elan Buildcon to pay outstanding fixed returns to commercial unit allottees in 'Elan Miracle' and execute conveyance deeds within three months. The authority capped recovery for increased super area to 5% and mandated maintenance charges only from the offer of possession date.,Haryana RERA Order Elan Buildcon: H-RERA Gurugram has ordered Elan Buildcon to pay outstanding fixed returns to commercial unit allottees in 'Elan Miracle' and execute conveyance deeds within three months. The authority capped recovery for increased super area to 5% and mandated maintenance charges only from the offer of possession date.

  • 6 Mar 2026

    Supreme Court orders CBI Probe into DLF's Gurugram housing project (opens in a new tab)

    The Supreme Court has ordered a CBI investigation into DLF's Primus Garden City project in Gurugram over delayed possession and unmet amenities promised to homebuyers since 2012. Citing a "huge mismatch" between legal requirements and ground realities, the apex court warned the case may not be an isolated incident in India's organised real estate sector.,The Supreme Court has ordered a CBI investigation into DLF's Primus Garden City project in Gurugram over delayed possession and unmet amenities promised to homebuyers since 2012. Citing a "huge mismatch" between legal requirements and ground realities, the apex court warned the case may not be an isolated incident in India's organised real estate sector.

  • 21 Dec 2025

    Ashiana Housing buys 22 acre land parcel in Gurgaon (opens in a new tab)

    The land located in Gurgaon will be used to develop a high-rise children-centric residential project. The land with a development potential of 21 lakh sq ft will mark Ashiana Housings foray in the Gurgaon real estate space. The firm plans to develop over 1200 units—1750 and 1800 sq. ft—over the next 4-5 years.,The land located in Gurgaon will be used to develop a high-rise children-centric residential project. The land with a development potential of 21 lakh sq ft will mark Ashiana Housings foray in the Gurgaon real estate space. The firm plans to develop over 1200 units—1750 and 1800 sq. ft—over the next 4-5 years.

  • 20 Dec 2025

    Emaar India to invest ₹1600 crore on a luxury project in Gurugram; to develop around 1000 apartments | Real Estate News (opens in a new tab)

    Gurugram real estate: Emaar India said the project, Serenity Hills, in New Gurugram, will comprise about 1,000 apartments priced between ₹3- ₹5.7 crore per unit | Real Estate News,Gurugram real estate: Emaar India said the project, Serenity Hills, in New Gurugram, will comprise about 1,000 apartments priced between ₹3- ₹5.7 crore per unit | Real Estate News

Nearby micro-markets

How New Gurgaon compares with the micro-markets around it.

  • New launch
  • Under construction
  • Ready to move
  • Stalled or on hold
  • Cancelled
  • New Gurgaon

    This micro-market

    148 projects₹15,000/sq ft19% past date

  • 8 projects₹22,350/sq ft0% past date

  • 44 projects₹15,000/sq ft18% past date

  • SPR

    Gurgaon

    81 projects₹15,000/sq ft15% past date

  • 160 projects₹17,500/sq ft11% past date

  • Manesar

    Gurgaon, Manesar

    8 projects₹12,500/sq ft13% past date

  • 28 projects₹23,250/sq ft29% past date

Frequently asked questions

How many RERA projects are in New Gurgaon?

ReraTracker lists 148 RERA-registered projects in New Gurgaon, checked by our team.

What is the price per sq ft in New Gurgaon?

The median builder asking price for apartments in New Gurgaon is ₹15,000 per sq ft, from ₹11,000 to ₹18,000, across 23 priced projects, updated Oct 2025–Sep 2026.

Which builders have projects in New Gurgaon?

The builders with the most projects in New Gurgaon are DLF, Signature Global and SS Group.

Which sectors are in New Gurgaon?

New Gurgaon covers sectors 81, 81A, 82–88, 88A, 88B, 89, 89A, 90–95 and 102. Its boundary is approximate.

How many projects in New Gurgaon are past their RERA completion date?

28 projects in New Gurgaon are past their RERA completion date and are neither ready to move nor cancelled.

Projects and dates come from RERA filings (UP RERA, HRERA and Delhi RERA) and ReraTracker’s research. Prices are builder asking prices. Outlines are approximate. Map data © OpenStreetMap contributors.