Infrastructure Total Expenditure
No total expenditure data is currently available for this project.
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | - | - | - |
| Electricity Supply System | 0 | - | - | - |
| Other | 0 | - | - | - |
| Parks and Playgrounds | 0 | - | - | - |
| Roads & Pavements | 0 | - | - | - |
| Sewerage treatment & garbage disposal | 0 | - | - | - |
| Shopping area | 0 | - | - | - |
| Storm Water Drainage | 0 | - | - | - |
| Water Supply System | 0 | - | - | - |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 15 | 27 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 5 | 10 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Water Supply System | 0 | 0 | 5 | 8 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 30 | 28 | 28 | 28 |
| Other | 0 | 0 | 0 | 3 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 5 | 5 |
| Sewerage treatment & garbage disposal | 15 | 15 | 12 | 9 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 2 | 0 | 0 |
| Water Supply System | 15 | 15 | 15 | 15 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 28 | 7.5 | 4 | 10 |
| Other | 8 | 20 | 28.5 | 7.5 |
| Parks and Playgrounds | 0 | 5 | 5 | 5 |
| Roads & Pavements | 5 | 10 | 10 | 10 |
| Sewerage treatment & garbage disposal | 4 | 10 | 5 | 10 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 2.5 | 2.5 | 2.5 |
| Water Supply System | 15 | 5 | 5 | 15 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | - | - |
| Electricity Supply System | 5.5 | 0 | - | - |
| Other | 16.5 | 0.15 | - | - |
| Parks and Playgrounds | 5 | 0.5 | - | - |
| Roads & Pavements | 20 | 0 | - | - |
| Sewerage treatment & garbage disposal | 5 | 0 | - | - |
| Shopping area | 0 | 0 | - | - |
| Storm Water Drainage | 3 | 0 | - | - |
| Water Supply System | 5 | 5 | - | - |
Avenue 81 is located in Gurugram.
Yes. Avenue 81 is registered under RERA-GRG-808-2021 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Avenue 81 is 31 December 2025.
Avenue 81 is developed by M/S GLS INFRACON PVT. LTD..