Infrastructure Total Expenditure
No total expenditure data is currently available for this project.
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | 0 | 0 | 0 |
| Electrical Sub Station | - | 0 | 0 | 0 |
| Electricity Supply System | - | 9.48 | 8.75 | 9.48 |
| Other | - | 0 | 0 | 0 |
| Parks and Playgrounds | - | 0 | 0 | 0 |
| Rain Water Harvesting | - | 0 | 0 | 3.06 |
| Roads & Pavements | - | 0 | 0 | 0 |
| STP | - | 8.13 | 7.5 | 8.13 |
| Security and Fire Fighting | - | 19.32 | 17.83 | 19.32 |
| Sewerage treatment & garbage disposal | - | 8.95 | 8.26 | 8.95 |
| Shopping area | - | 0 | 0 | 0 |
| Storm Water Drainage | - | 0 | 0 | 0 |
| Street Light | - | 0 | 0 | 0 |
| Underground Water Tank | - | 4.8 | 4.43 | 4.8 |
| Water Supply System | - | 16.61 | 15.33 | 16.61 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical Sub Station | 0 | 25 | 25 | 25 |
| Electricity Supply System | 8.75 | 9.48 | 8.75 | 9.48 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 3.23 | 3.23 | 3.23 | 3.23 |
| Rain Water Harvesting | 2.88 | 3.06 | 2.88 | 3.06 |
| Roads & Pavements | 0 | 37.85 | 37.85 | 37.85 |
| STP | 7.5 | 8.13 | 7.5 | 8.13 |
| Security and Fire Fighting | 17.83 | 19.32 | 17.83 | 19.32 |
| Sewerage treatment & garbage disposal | 8.26 | 8.95 | 8.26 | 8.95 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 10.8 | 10.8 | 10.8 | 10.8 |
| Street Light | 0 | 3.63 | 3.63 | 3.63 |
| Underground Water Tank | 4.43 | 4.8 | 4.43 | 4.8 |
| Water Supply System | 15.33 | 16.61 | 15.33 | 16.61 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | - | - | - |
| Electrical Sub Station | 25 | - | - | - |
| Electricity Supply System | 8.75 | - | - | - |
| Other | 0 | - | - | - |
| Parks and Playgrounds | 3.23 | - | - | - |
| Rain Water Harvesting | 3.06 | - | - | - |
| Roads & Pavements | 37.85 | - | - | - |
| STP | 7.5 | - | - | - |
| Security and Fire Fighting | 17.83 | - | - | - |
| Sewerage treatment & garbage disposal | 8.26 | - | - | - |
| Shopping area | 0 | - | - | - |
| Storm Water Drainage | 10.8 | - | - | - |
| Street Light | 3.63 | - | - | - |
| Underground Water Tank | 4.43 | - | - | - |
| Water Supply System | 15.33 | - | - | - |
Vista Corner is located in Gurugram.
Yes. Vista Corner is registered under RERA-GRG-1155-2022 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Vista Corner is 30 September 2027.
Vista Corner is developed by COPIOUS REALTORS PRIVATE LIMITED.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.