| Particulars | Expenditure (in Lakhs) |
|---|---|
| STP | 4.99 |
| Other | 0 |
| Parking | 236 |
| Horticulture | 6.35 |
| Street Light | 3.32 |
| Shopping area | 0 |
| Renewable Energy | 1.93 |
| Roads & Pavements | 20.09 |
| Water Supply System | 14.38 |
| Construction of Road | 9.63 |
| Storm Water Drainage | 10.49 |
| Parks and Playgrounds | 3.19 |
| Rain Water Harvesting | 2.16 |
| Electrical Sub Station | 10.85 |
| Underground Water Tank | 2.89 |
| Electricity Supply System | 0 |
| Security and Firefighting | 8.87 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 5.55 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | 0 | 0 | 0 |
| Construction of Circulation Road | - | - | - | - |
| Electrical Sub Station | - | 4.36 | 4.36 | 6.7 |
| Electricity Supply System | - | 0 | 0 | 0 |
| Horticulture | - | - | - | - |
| Other | - | 0 | 0 | 0 |
| Parking | - | 8.6 | 51.57 | 38.97 |
| Parks and Playgrounds | - | 0 | 0 | 0 |
| Rain Water Harvesting | - | 0 | 3.99 | 2.06 |
| Renewable Energy | - | - | - | - |
| Roads & Pavements | - | 1.96 | 1.96 | 1.7 |
| STP | - | 5.83 | 5.83 | 2.35 |
| Security and Firefighting | - | 0.55 | 0.55 | 4.48 |
| Sewerage treatment & garbage disposal | - | 0.31 | 0.62 | 1.09 |
| Shopping area | - | 0 | 0 | 0 |
| Storm Water Drainage | - | 0.59 | 1.18 | 2.06 |
| Street Light | - | 0.46 | 1.12 | 2.7 |
| Underground Water Tank | - | 3.17 | 2.93 | 2 |
| Water Supply System | - | 0.52 | 3.14 | 2.37 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Construction of Circulation Road | - | - | - | - |
| Electrical Sub Station | 8.82 | 6.18 | - | - |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Horticulture | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| Parking | 49.28 | 38.39 | 72.87 | 51 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain Water Harvesting | - | - | - | - |
| Renewable Energy | 3.6 | 1.8 | - | - |
| Roads & Pavements | 1.98 | 1.03 | 6.2 | 5.64 |
| STP | - | - | - | - |
| Security and Firefighting | 2.99 | 1.24 | 5.72 | 4.95 |
| Sewerage treatment & garbage disposal | 0.93 | 0.78 | 1.56 | 1.71 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 1.77 | 1.47 | 2.94 | 2.65 |
| Street Light | 1.3 | 1.12 | 2.61 | - |
| Underground Water Tank | - | - | - | - |
| Water Supply System | 3 | 2.34 | 4.44 | 3.11 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Construction of Circulation Road | - | - | 13.51 | 13.51 |
| Electrical Sub Station | - | - | - | - |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Horticulture | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| Parking | 49.28 | 86.12 | 79.49 | 64 |
| Parks and Playgrounds | 0.78 | 1.18 | 1.39 | 1.16 |
| Rain Water Harvesting | - | - | - | - |
| Renewable Energy | - | - | - | - |
| Roads & Pavements | 6.77 | 6.04 | 9.59 | 10.72 |
| STP | - | - | - | - |
| Security and Firefighting | 2.91 | 1.49 | - | - |
| Sewerage treatment & garbage disposal | 2.18 | 1.71 | 2.18 | 1.4 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 4.12 | 3.24 | 4.12 | 1.18 |
| Street Light | - | - | - | - |
| Underground Water Tank | - | - | - | - |
| Water Supply System | 3 | 5.25 | 4.84 | 3.9 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | - |
| Construction of Circulation Road | - | - | - | - |
| Electrical Sub Station | - | - | - | - |
| Electricity Supply System | 0 | 0 | 0 | - |
| Horticulture | 4.46 | 8.92 | 4.46 | - |
| Other | 0 | 0 | 0 | - |
| Parking | 72.87 | - | - | - |
| Parks and Playgrounds | 2.05 | 1.22 | 1.17 | - |
| Rain Water Harvesting | - | - | - | - |
| Renewable Energy | - | - | - | - |
| Roads & Pavements | 2.82 | 0 | 0 | - |
| STP | - | - | - | - |
| Security and Firefighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 1.09 | 0 | 0 | - |
| Shopping area | 0 | 0 | 0 | - |
| Storm Water Drainage | 1.47 | 1.18 | 1.47 | - |
| Street Light | - | - | - | - |
| Underground Water Tank | - | - | - | - |
| Water Supply System | 4.44 | 0 | 0 | - |
Godrej Icon Tower 4/E And Tower 5/F is located in Gurgaon.
Yes. Godrej Icon Tower 4/E And Tower 5/F is registered under RERA-GRG-1224-2022 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Godrej Icon Tower 4/E And Tower 5/F is 31 December 2029.
Godrej Icon Tower 4/E And Tower 5/F is developed by Godrej.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.
Developed by
49 Projects
EXECUTIVE SUMMARY Godrej Properties Limited (GPL) is the real estate development arm of the Godrej Industries Group, one of India's oldest and most respected conglomerates with a lineage dating to 1897. Incorporated orig…
Know More about Godrej