OngoingActive

NOIDA ONE --TOWER A (PHASE II)

Gautam Buddha Nagar, Uttar Pradesh
01-09-2012
Launch Date
Ongoing
Type
28-12-2020
Completion Date

Overview

Launch Date

01-09-2012

Completion Date

28-12-2020

RERA ID

UPRERAPRJ3841

Basic Details

Project TypeOngoing
Project CategoryCommercial
Total area in round figure (Sq.mt.)5283
Project NameNOIDA ONE --TOWER A (PHASE II)
Registration Fee (in Rs.)63000
AddressNot specified
Village/Locality/Sector etc.Not specified
StateUttar Pradesh
Project Duration (In month)100
DistrictGautam Buddha Nagar
Original Start Date01-09-2012
TehsilGautam Buddha Nagar
Proposed Start Date01-09-2012
Sanctioning Competent AuthorityNoida Authority
Project Cost (in Lacs)4600
Proposed Completion Date28-12-2020

Location

Latitude

28 degree 36' 15' N

Longitude

77 degree 21.8' 28 ' E

Bank Details

Account no.917020052998536
Name Of Account HolderPioneer eServe Private Limited RERA Account
Bank NameAXIS BANK Limited
Branch AddressF-43,Kirti Nagar, New Delhi-110015
Branch NameF-43,Kirti Nagar
IFSC CodeUTIB0000250

Development Works

Demarcation of Plots

On the East side Plot No. B-09, West Side Green Belt. Noth 45 Meter wide Road, South 18 Meter Wide Road

Boundary Wall

Front Boundary Wall - Brick Wall with Grill . Rear Side Boundary Wall- Solid Brick Wall

Road Work

Cement Concrete Road with Trimix finish

Footpaths

Raised footpath with Pavit tiles

Water Supply Including Drinking Water Facilities

Domestic tank of 150 KL with pumps and boosting arrangement for terrace tanks. Also have Water Softner Plant

Sewer System

Dual plumbing system, segregation of black and grey water. STP of 250 KLD of MBBR Technology for Sewer Treatment.

Drain

Under ground RCC pipe drainage system with rain water harvesting system

Parks

Green area developed with grassing and indigenous plants

Tree Planting

Indigenous varity of trees including Alstonia Scholaris, Ficus Benjamina, Plumeria Alba, etc

Design For Electric Supply Including Street Lighting

Electric Sub-Station in basement with dry type Transformer of 2250 KVA. 100% DG Backup. Dual metering of individual units, All LED Lights for Street with 10 KW Solar Power Plant on terrace

Community Buildings

NIL

Treatment and Disposal System of Sewage and Sullage water

Sewage treated STP of 250 KLD, Treated water using for Flushing, Horticulture and Cooling tower

Solid Waste Management And Disposal System

Solid waste collected from each floor is stored in basement after segregation. Bio-di-gradable waste will be send to municipal base facility. Recyclable waste will be sold to authorized vendors

Water Conservation System

Low Flow Sanitary Fixtures, treated water used for flushing and horticulture. Drip irrigation system also installed for gardening

Energy Management System Including Use of Renewable Energy

All common area lighting is with LED lighting and also has 10 KW Solar Power Plant

Fire Protection And Fire Safety System

UG tank of 200KL, Fire Ring Main and Yard Hydrants, Sprinklers System

Social Infrastructure And Other Public Amenities Including Public Health Services

Adjoining plot is Green belt area. Hospitals, Education Centers, Bus Station, Taxi Stand is within 2KM radius

Emergency Evacuation Services

Floor Signage, Fire Escape Staircase, Fire Refuge Area

Other Miscellaneous Work

NIL

Documents

Lease Deed

No: 6835/6834 | Date: 22-07-2006

Allotment Letter issued by Competent Authority

No: NOIDA/INSTT/05/3998 | Date: 30-11-2005

Details of Encumbrances

Other Plan(If Any)

Proforma of Conveyance Deed

Proforma of Completion Certificate(Occupancy)

Details of Encumbrances

Uploaded: 28-01-2019

Commencement Certificate

Uploaded: 10-07-2019

Proforma of Application Form

Uploaded: 31-07-2018

Proforma of Allotment Letter

Uploaded: 31-07-2018

Waste Disposal Plan

Uploaded: 31-07-2018

Water Supply Plan

Uploaded: 31-07-2018

Electricity Supply Plan

Uploaded: 31-07-2018

Development Work Plan

Uploaded: 31-07-2018

Affidavit

Uploaded: 31-07-2018

CA CERTIFICATE

Uploaded: 31-07-2018

ARCHITECT CERTIFICATE

Uploaded: 31-07-2018

ENGINEERS CERTIFICATE

Uploaded: 31-07-2018

Registry Document In Case of Own Land

Uploaded: 28-07-2017

Authentic copy of Approval of Project

Uploaded: 28-07-2017

Sanctioned Layout Plan (Of Entire Project)

Uploaded: 28-07-2017

Sanctioned Building/ Block Plan (Add Plans for All Buildings or Blocks)

Uploaded: 28-07-2017

Waste Disposal Plan

Uploaded: 28-07-2017

Floor plans of all types

Uploaded: 28-07-2017

Water Supply Plan

Uploaded: 28-07-2017

Electricity Supply Plan

Uploaded: 28-07-2017

Development Work Plan

Uploaded: 28-07-2017

Proforma of Application Form

Uploaded: 28-07-2017

Proforma of Allotment Letter

Uploaded: 28-07-2017

Proforma of Conveyance Deed

Uploaded: 28-07-2017

Affidavit

Uploaded: 28-07-2017

Permits

Orignal Permit No2012/225
Orignal Permit Date14-03-2012
Valid Upto13-03-2017
Revalidated Permit No-
Revalidated Permit Date-
Revalidated Permit Valid Upto-
Permit Extendable Upto13-03-2022
End Date30-06-2019
Uploaded Approve LayoutOpen
Uploaded Sanctioned LetterOpen
Uploaded Approved MapOpen
Uploaded Floor Plan Of All TypesOpen
Uploaded Project SpecificationsOpen
Uploaded Sajra DetailNot Specified
Orignal Permit No2012/225
Orignal Permit Date14-03-2012
Valid Upto13-03-2017
Revalidated Permit No-
Revalidated Permit Date-
Revalidated Permit Valid Upto-
Permit Extendable Upto13-03-2022
End Date30-06-2019
Uploaded Approve LayoutOpen
Uploaded Sanctioned LetterOpen
Uploaded Approved MapOpen
Uploaded Floor Plan Of All TypesOpen
Uploaded Project SpecificationsOpen
Uploaded Sajra DetailNot Specified
Orignal Permit No2012/225
Orignal Permit Date14-03-2012
Valid Upto13-03-2017
Revalidated Permit No2012/225
Revalidated Permit Date14-03-2012
Revalidated Permit Valid Upto13-03-2022
Permit Extendable Upto13-03-2022
End Date30-06-2019
Uploaded Approve LayoutOpen
Uploaded Sanctioned LetterOpen
Uploaded Approved MapOpen
Uploaded Floor Plan Of All TypesOpen
Uploaded Project SpecificationsOpen
Uploaded Sajra DetailNot Specified
Orignal Permit No2012/225
Orignal Permit Date14-03-2012
Valid Upto13-03-2017
Revalidated Permit No2012/225
Revalidated Permit Date14-03-2012
Revalidated Permit Valid Upto12-03-2022
Permit Extendable Upto12-03-2022
End Date30-06-2019
Uploaded Approve LayoutOpen
Uploaded Sanctioned LetterOpen
Uploaded Approved MapOpen
Uploaded Floor Plan Of All TypesOpen
Uploaded Project SpecificationsOpen
Uploaded Sajra DetailNot Specified

Project Team

Contractor Name (if any)Not specified
Contractor AddressNot specified
Architect NameNot specified
Architect AddressNot specified
Architect Licence NumberNot specified
Structural Engineer NameNot specified
Structural Engineer AddressNot specified
Mobile number(Project Co-ordinator)9811450005

Land Details

AFS

Showing 1 blocks with 228 units

Property Summary

Total Carpet Area

11044.93 m²

118886.52 ft²

Total Units

233

2 different types

Blocks & Floors

1

11 floors across all blocks

Parking

0

0 garages, 0 open

Average unit size:47.40 m²
Balconies:30
Parking ratio:0.00 per unit

Block A

228 units

Khasra Details

Total Area

20000.00 m²

215278.00 ft²

1 plot
Plot
TypePlot
Khasra/Plot NoB 08 SECTOR 62
Area(In Sq. Mt.)20000

Other Details

Contractor Name (if any)Not specified
Contractor AddressNot specified
Architect NameNot specified
Architect AddressNot specified
Architect Licence NumberNot specified
Structural Engineer NameNot specified
Structural Engineer AddressNot specified
Mobile number(Project Co-ordinator)9811450005