Total Units
456
2 unit types
Carpet Area
4,13,552 ft²
38,420.23 m² · carpet only, excludes balcony
Blocks & Floors
4
93 floors across all blocks
Parking
0
0 garages, 0 open
Average carpet area 907 ft² (84.25 m²)Balconies 812Parking per unit 0.004 of 204 rows list no units (4 floors are empty), so they add nothing to these totals
All blocks
Showing 50 of 204 rows · 9 of 12 columns
| Block | Floor | Type | Units | Carpet Areaper unit | Balconies | Balcony Areatotal | Verandahs | Verandah Areatotal |
|---|---|---|---|---|---|---|---|---|
| T-34 | 1 | 3 BHK | 1 | 922 ft²85.70 m² | 3 | 170 ft²15.83 m² | 1 | 197 ft²18.34 m² |
| T-34 | 1 | 3 BHK | 1 | 997 ft²92.62 m² | 4 | 211 ft²19.56 m² | 1 | 538 ft²50.02 m² |
| T-34 | 1 | 3 BHK | 1 | 997 ft²92.62 m² | 4 | 211 ft²19.56 m² | 1 | 461 ft²42.80 m² |
| T-34 | 1 | 3 BHK | 1 | 1,152 ft²107.06 m² | 5 | 270 ft²25.05 m² | 2 | 399 ft²37.09 m² |
| T-34 | 1 | 3 BHK | 1 | 1,152 ft²107.06 m² | 5 | 270 ft²25.05 m² | 1 | 2,117 ft²196.70 m² |
| T-34 | 1 | 3 BHK | 1 | 922 ft²85.70 m² | 3 | 170 ft²15.83 m² | 1 | 1,262 ft²117.22 m² |
| T-34 | 2 | 3 BHK | 1 | 922 ft²85.70 m² | 4 | 208 ft²19.33 m² | 1 | 134 ft²12.43 m² |
| T-34 | 2 | 3 BHK | 2 | 997 ft²92.62 m² | 4 | 211 ft²19.56 m² | — | — |
| T-34 | 2 | 3 BHK | 2 | 1,152 ft²107.06 m² | 5 | 270 ft²25.05 m² | — | — |
| T-34 | 2 | 3 BHK | 1 | 922 ft²85.70 m² | 4 | 208 ft²19.33 m² | 1 | 139 ft²12.93 m² |
| T-34 | 3 | 3 BHK | 2 | 922 ft²85.70 m² | 4 | 208 ft²19.33 m² | — | — |
| T-34 | 3 | 3 BHK | 2 | 997 ft²92.62 m² | 4 | 211 ft²19.56 m² | — | — |
| T-34 | 3 | 3 BHK | 2 | 1,152 ft²107.06 m² | 5 | 270 ft²25.05 m² | — | — |
| T-34 | 4 | 3 BHK | 2 | 922 ft²85.70 m² | 4 | 208 ft²19.33 m² | — | — |
| T-34 | 4 | 3 BHK | 2 | 997 ft²92.62 m² | 4 | 211 ft²19.56 m² | — | — |
| T-34 | 4 | 3 BHK | 2 | 1,152 ft²107.06 m² | 5 | 270 ft²25.05 m² | — | — |
| T-34 | 5 | 3 BHK | 2 | 922 ft²85.70 m² | 4 | 208 ft²19.33 m² | — | — |
| T-34 | 5 | 3 BHK | 2 | 997 ft²92.62 m² | 4 | 211 ft²19.56 m² | — | — |
| T-34 | 5 | 3 BHK | 2 | 1,152 ft²107.06 m² | 5 | 270 ft²25.05 m² | — | — |
| T-34 | 6 | 3 BHK | 2 | 922 ft²85.70 m² | 4 | 208 ft²19.33 m² | — | — |
| T-34 | 6 | 3 BHK | 2 | 997 ft²92.62 m² | 4 | 211 ft²19.56 m² | — | — |
| T-34 | 6 | 3 BHK | 2 | 1,152 ft²107.06 m² | 5 | 270 ft²25.05 m² | — | — |
| T-34 | 7 | 3 BHK | 2 | 922 ft²85.70 m² | 4 | 208 ft²19.33 m² | — | — |
| T-34 | 7 | 3 BHK | 2 | 997 ft²92.62 m² | 4 | 211 ft²19.56 m² | — | — |
| T-34 | 7 | 3 BHK | 2 | 1,152 ft²107.06 m² | 5 | 270 ft²25.05 m² | — | — |
| T-34 | 8 | 3 BHK | 2 | 922 ft²85.70 m² | 4 | 208 ft²19.33 m² | — | — |
| T-34 | 8 | 3 BHK | 2 | 997 ft²92.62 m² | 4 | 211 ft²19.56 m² | — | — |
| T-34 | 8 | 3 BHK | 2 | 1,152 ft²107.06 m² | 5 | 270 ft²25.05 m² | — | — |
| T-34 | 9 | 3 BHK | 2 | 922 ft²85.70 m² | 4 | 208 ft²19.33 m² | — | — |
| T-34 | 9 | 3 BHK | 2 | 997 ft²92.62 m² | 4 | 211 ft²19.56 m² | — | — |
| T-34 | 9 | 3 BHK | 2 | 1,152 ft²107.06 m² | 5 | 270 ft²25.05 m² | — | — |
| T-34 | 10 | 3 BHK | 2 | 922 ft²85.70 m² | 4 | 208 ft²19.33 m² | — | — |
| T-34 | 10 | 3 BHK | 2 | 997 ft²92.62 m² | 4 | 211 ft²19.56 m² | — | — |
| T-34 | 10 | 3 BHK | 2 | 1,152 ft²107.06 m² | 5 | 270 ft²25.05 m² | — | — |
| T-34 | 11 | 3 BHK | 2 | 922 ft²85.70 m² | 4 | 208 ft²19.33 m² | — | — |
| T-34 | 11 | 3 BHK | 2 | 997 ft²92.62 m² | 4 | 211 ft²19.56 m² | — | — |
| T-34 | 11 | 3 BHK | 2 | 1,152 ft²107.06 m² | 5 | 270 ft²25.05 m² | — | — |
| T-34 | 12 | 3 BHK | 2 | 922 ft²85.70 m² | 4 | 208 ft²19.33 m² | — | — |
| T-34 | 12 | 3 BHK | 2 | 997 ft²92.62 m² | 4 | 211 ft²19.56 m² | — | — |
| T-34 | 12 | 3 BHK | 2 | 1,152 ft²107.06 m² | 5 | 270 ft²25.05 m² | — | — |
| T-34 | 13 | 3 BHK | — | — | — | — | — | — |
| T-34 | 14 | 3 BHK | 2 | 922 ft²85.70 m² | 4 | 208 ft²19.33 m² | — | — |
| T-34 | 14 | 3 BHK | 2 | 997 ft²92.62 m² | 4 | 211 ft²19.56 m² | — | — |
| T-34 | 14 | 3 BHK | 2 | 1,152 ft²107.06 m² | 5 | 270 ft²25.05 m² | — | — |
| T-34 | 15 | 3 BHK | 2 | 922 ft²85.70 m² | 4 | 208 ft²19.33 m² | — | — |
| T-34 | 15 | 3 BHK | 2 | 997 ft²92.62 m² | 4 | 211 ft²19.56 m² | — | — |
| T-34 | 15 | 3 BHK | 2 | 1,152 ft²107.06 m² | 5 | 270 ft²25.05 m² | — | — |
| T-34 | 16 | 3 BHK | 2 | 922 ft²85.70 m² | 4 | 208 ft²19.33 m² | — | — |
| T-34 | 16 | 3 BHK | 2 | 997 ft²92.62 m² | 4 | 211 ft²19.56 m² | — | — |
| T-34 | 16 | 3 BHK | 2 | 1,152 ft²107.06 m² | 5 | 270 ft²25.05 m² | — | — |
Total Plot Area
24.71 acres
99,991.40 m² · plot area
Plot Area of the Nirala Estate Ph-V, is 9568 sqmt. and is part of total plot area 99991.4 sqmt. at GH-04, Techzone-IV, Greater Noida West, U.P. allotted by Greater Noida Industrial Development Authority. The demarcation of total plot and Nirala Estate Ph-V plot is attached with Layout plan.
Yes, 1500 mm high masonry boundary wall will be constructed with RCC and brickwork. It is mixed with pillars and M.S. railing/Grills to create elevation. Top surface painted with soothing color to given even shade.
Yes, 6 mtrs wide RCC road with top finish iwth trimix/ Interlocking block road with intermittent Tile/ Stone paving.
1500 to 2000 mm wide pathways finish with Pavers/Stone/Trimix footpath in park area.
Yes, GNIDA water supply System in underground water reservoirs. Terrace tanks filled with pumps.
Yes, RCC hume pipe with manhole, chambers and collection chambers and connections.
Yes, RCC hume/PVC pipe with manhole open drain with concrete perforated cover chamber, collection chamber with rain water harvesting.
Yes, Landscape with civil work with masonry and stone, horticulture work and various type of plantation, shrubs.
Yes, tree planting along some parts of the road and park in the project.
Yes, pole light will be provided along with internal road side.
Yes, community building with conference hall, gym, coffee shop, library, steam, suana, swimming pool, jaccuzzi, kids play area, guest room, indoor games facilities etc. (Common for all phases that will be provided on completion of total project)
In house STP and through GNIDA sewerage system.
Yes, Organic waste converter and collection bins..
Yes, adequate rain water harvesting pits are provided in the projects.
Lighting illuminating arrangement of common area are through solar PV, Solar arrangements are given at the roof top and solar water heating systems for upper floors.
As per approved fire drawings, smoke detector, fire alarm system, sprinkler etc.
Proper water supply and sanitary facilities at one point in the project.
As per plan approved including main gate and emergency gate etc.
Yes, guard room, entrance and exit gates, commercial facilities,.
Nirala Estate Phase-V is located in Gautam Buddha Nagar.
Yes. Nirala Estate Phase-V is registered under UPRERAPRJ788191 with the Uttar Pradesh RERA (UP-RERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Nirala Estate Phase-V is 30 November 2027.
Nirala Estate Phase-V is developed by Nirala Group.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.
Developed by
10 Projects
EXECUTIVE SUMMARY OF NIRALA GROUP Nirala Group is a privately held real estate developer headquartered in Sector 63, Noida, with operations spanning approximately three decades since its founding in 1996. The group opera…
Know More about Nirala Group