Demarcation of the plot has been done by GNIDA, plot area is 20914.10 SQM.
Construction of the Boundary wall has been completed.
Construction of the internal road is in progress.
Construction of the internal footpath is in progress.
Water supply pipe line has been laid upto the project by the concerned authority.
Sewer system work in progress.
Drainage system work in progress.
Work in developing phase.
Tree planting remains to be done.
Electric supply including street light is to be completed as per the sanctioned plan.
Community building construction yet to be completed.
Sewage and sullage water treatment plant work is under progress.
Solid waste management and disposal provision has been made at each floor of all buildings.
Under ground water reservoir has been constructed and overhead water tanks also constructed.
Alternate generator for energy management to be provided.
Water sprinkle systems has been installed in every flat and fire water tanks of 25000 capacity has been constructed.
Normal social infrastructure and public amenities under developing phase.
Emergency evacuation is feasible.
Miscellaneous work in progress.
Showing 3 blocks with 112 units
Total Carpet Area
24819.12 m²
267150.53 ft²
Total Units
346
3 different types
Blocks & Floors
3
23 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
8330.00 m²
89663.29 ft²