Have queries on this Project?
77.310786
28.290890
Showing 1 blocks with 163 units
Total Carpet Area
5523.34 m²
59452.68 ft²
Total Units
215
3 different types
Blocks & Floors
1
24 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
2313.47 m²
24901.96 ft²
East - Plot no 3, West- Plot no 5, North Delta )) Residential, South - Road
Made of RCC, Brick Work with MS Railing and Gate. Side Boundary Wall of 2000 mm height and Front Boundary Wall of 1500 MM high with 500 high MS Railing
Total proposed development will be having approximate Road area of 906.21 Sq Meter and the Road will be made of Trimix Concrete and Pavers over the WMM /WBM.
The Proposed development will be having Pavers, Natural stone like Granite/Marble and Tiles on footpaths/ alongside the road and the total area will approximately 135 Sq Meter.
From GNIDA with WTP of adequate capacity as per design to cater the daily Water Requirement of 13,25,000 Liter per day.
Sewerage and Sullage will be treated in multistage process at STP of 77 KLD Capacity. The process includes screening and grit removal, primary settling of the Solids, biological breakdown of organic matter and disinfection along with Advanced Filtration Treatment. Sludge will be separated and disposed of or reused, while the Final treated Water (effluent) will be reused in Horticulture and AC System or Discharged. The MBBR Technology will be most appropriate to be used.
Overflow of rain Water harvesting pit to storm Water Drain of GNIDA is being proposed. Peak hourly discharge has been taken 78.29 Nu meters. One Number of Rain water Harvesting Pit is also proposed to be installed to recharge the Ground water.
Green area is being provided as per GNIDA Norms. The Green Area Required as Total Site Area is 347.39 Sq Meter . However the Proposed Green Area is 348.49 Sq Meter.
Evergreen Tree Planted as per GNIDA Norms. 14 nos Trees are required as per the Development Authority Norms. Keeping the commitment of Green Noida, 16 nos of Evergreen Trees are Proposed for better and developed Green areas. The Details of Trees are mentioned in the Attached Landscape Plan.
Electrical load calculated as per requirement and prevailing norms. Street Lighting with Energy saving LED Street Lights. are Proposed. Total Electrical is 1084 KVA with 0.95 Power Factor. The Proposed Transformer Capacity is 1275 KW with 0.85 Loading. One Number DG Set of 750 KVA is also Proposed with 0.5 Loading Factor.
Not Provided
Sewage and Sullage will be treated in a Multistage Process at STP with Advanced Filtration system. Sludge is separated and will be used / disposed off, while the final treated water will be reused in Flushing, gardening and AC system. Separate Kitchen waste line connected to ETP through grease Trap
Separating waste into different categories at the source to facilitate reuse, recycling as per norms. The residue waste will be sent for processing or disposal Sites.
Techniques and Technologies to manage the Water resources efficiently, aiming to reduce waste Rain Water Harvesting, reduction in wastage of Water by using Low Flow Fixtures.
Optimize energy distribution system to reduce wastage and overall energy usage by installing Low energy consuming Light Fixtures etc. Install Solar Panels and Install Heat Efficient glass to reduce heat gain.
Combination of strategies, equipment and protocols designated to prevent, detect, control, and suppress fires. Ensuring the safety of people and property. It consists Fire Safety Systems- Active and Passive Components. Active Components such as Fire Alarms, Sprinklers an Extinguishers, While Passive Systems like Fire Resistant Materials, and Fire Barriers, Contain and Limit Fire Spread. All Installations will as Per NBC norms to prevent the Fire incidences, effective Fire Detection and Fire Fighting Systems.
Physical Facilities and Services that Support public well being such as Handicap Toilet, Public Toilet, Drinking Water Facilities etc. Each Shopping Floor from Lower Ground Till Third Floor will be having Ladies and Gents Toilet and a Differently Abled Toilet at LG Floor. is being Provided. The total nos of Toilets are as per Statuary requirements
To Move people from a high risk location to safe areas like Fire Refuge Balconies, Fire Escape Staircases ahve been provided as per NBC Norms. 5th Floor Refuge Balcony Area = 51.649 Sq Mts. 9th Floor Refuge Balcony Area = 51.649 Sq. Mts. 14th Floor Refuge Balcony Area = 45.598 Sq. Mts 18th Floor Refuge Balcony Area = 45.598 Sq. Mts. 21st Floor Refuge Balcony Area = 45.598 Sq. Mts.
Not Applicable