Have queries on this Project?
Uploaded on: 07-02-2024
Uploaded on: 19-06-2024
Uploaded on: 19-06-2024
Uploaded on: 19-06-2024



| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall | - | - | - | - |
| Circular Road | - | - | - | - |
| Clubhouse/community centres | - | 0 | 0 | 0 |
| Electrical sub station | - | - | - | - |
| Electricity Supply System | - | 0 | 0 | 0 |
| Electrification | - | - | - | - |
| Other | - | 0 | 0 | 0 |
| Parks and Playgrounds | - | 0 | 0 | 0 |
| Rain water harvesting | - | 31.4 | 31.4 | 31.4 |
| Roads & Pavements | - | 178.6 | 178.6 | 178.6 |
| STP | - | - | - | - |
| Security and fire system | - | - | - | - |
| Sewerage treatment & garbage disposal | - | 36.4 | 36.4 | 36.4 |
| Shopping area | - | 0 | 0 | 0 |
| Storm Water Drainage | - | 53.4 | 53.4 | 53.4 |
| Under ground water tank | - | - | - | - |
| Water Supply System | - | 44.4 | 44.4 | 44.4 |
| streetlight | - | - | - | - |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall | - | - | 30.5 | 30.5 |
| Circular Road | - | - | - | - |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical sub station | - | - | - | - |
| Electricity Supply System | 0 | 0 | 160.75 | 160.75 |
| Electrification | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain water harvesting | 31.4 | 31.4 | - | - |
| Roads & Pavements | 178.6 | 178.6 | 0 | 0 |
| STP | - | - | - | - |
| Security and fire system | - | - | 113.75 | 113.75 |
| Sewerage treatment & garbage disposal | 36.4 | 36.4 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 53.4 | 53.4 | 0 | 0 |
| Under ground water tank | - | - | - | - |
| Water Supply System | 44.4 | 44.4 | 0 | 0 |
| streetlight | - | - | 8 | 8 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall | 30.5 | 30.5 | - | - |
| Circular Road | - | - | - | - |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical sub station | - | - | - | - |
| Electricity Supply System | 160.75 | 160.75 | 0 | 0 |
| Electrification | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 25.75 | 25.75 |
| Rain water harvesting | - | - | - | - |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| STP | - | - | - | - |
| Security and fire system | 113.75 | 113.75 | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Under ground water tank | - | - | - | - |
| Water Supply System | 0 | 0 | 0 | 0 |
| streetlight | 8 | 8 | - | - |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall | - | - | - | - |
| Circular Road | - | - | 155.5 | 155.5 |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical sub station | - | - | 170.75 | 170.75 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Electrification | - | - | 150 | 150 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 25.75 | 25.75 | 0 | 0 |
| Rain water harvesting | - | - | - | - |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| STP | - | - | 125 | 125 |
| Security and fire system | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Under ground water tank | - | - | 105 | 105 |
| Water Supply System | 0 | 0 | 0 | 0 |
| streetlight | - | - | - | - |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall | - | - | - | - |
| Circular Road | 155.5 | 155.5 | - | - |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical sub station | 170.75 | 170.75 | - | - |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Electrification | 150 | 150 | 0 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain water harvesting | - | - | - | - |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| STP | 125 | 125 | - | - |
| Security and fire system | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Under ground water tank | 105 | 105 | - | - |
| Water Supply System | 0 | 0 | 0 | 0 |
| streetlight | - | - | - | - |
Pride Park is located in Gurugram.
Yes. Pride Park is registered under RERA-GRG-1515-2023 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Pride Park is 17 January 2029.
Pride Park is developed by FAITH BUILDTECH PRIVATE LIMITED.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.