ONGOINGActive

ESFERA PHASE-II

GURUGRAM, KADIPUR ST
09-12-2019
Launch Date
ONGOING
Type
2024-06-30
Completion Date

Overview

Launch Date

09-12-2019

Completion Date

2024-06-30

RERA ID

RERA-GRG-355-2019

Basic Details

Project NameESFERA PHASE-II
Project IDRERA-GRG-355-2019
Project TypeONGOING
Applicant TypeCompany
Submission Date09-12-2019 03:04:45 AM
Builder NameRENUKA TRADERS PRIVATE LIMITED
CINU74899DL1983PTC014992
PANXXXX713C
EmailDSGILL@IMPERIASTRUCTURES.COM
WebsiteNot specified
Phone (Mobile)8586928776
Phone (Landline)01146469999
Registered AddressB-2/3, KH. NO. 8/8, CHHATTERPUR EXTN., NANDA HOSPITAL, NEW DELHI-110074
Project AddressSECTOR-37C, VILLAGE-GHAROLI AND BASAI
DistrictGURUGRAM
TehsilKADIPUR ST

Bank Details

Bank NameAXIS BANK LIMITED, GROUND FLOOR & BASEMENT PLOT NO. 51, POCKET I, JASOLA, NEW DELHI-110025
Account Number917020052733902
IFSC CodeUTIB0001148
MICR Code110211085
Branch Code001148

Account Related Information

Annex copy of the balance sheet of last 3 yearsYes
In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.Yes
Name and address of the person/persons who would ordinarily be operating the account (Change at any time must be intimated to the Authority)SHYAM S AGGARWAL, A-25, Mohan Cooperative Industrial Estate, Mathura Road, New Delhi-110044.
Attach certificate issued by a Chartered Accountant that the applicant has not defaulted in its debt liabilities in the past five years in folder D. (In case of default, give details)UPLOADED

Development Details

Land Area8.50 (Acre)
Proposed FAR1.75
Permissible FAR1.75
Total Licensed Land17 (Acre)

Land Usage

PLOTS TO BE SOLD493
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS8.5
CONSTRUCTION OF ROADS2.1
PAVEMENTS0.85
PARKS AND PLAYGROUNDS3.1
GREEN BELTS1.5
VEHICLE PARKINGS0.3
ELECTRICITY SUB-STATION0.4
CLUB HOUSE0.25
SEWAGE AND SOLID WASTE TREATMENT FACILITY0
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
ANY OTHER0
Total510

Cost Details

Land Cost3688 Lakhs
Other Cost3865.57 Lakhs
Estimated Project Cost24584.50 Lakhs
Estimated Infrastructure Cost2861.28 Lakhs
Estimated Apartment Construction Cost10014.47 Lakhs

Documents

ZONING PLAN

Uploaded on: 26-11-2019

A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS

Uploaded on: 26-11-2019

A COPY OF THE DRAFT AGREEMENT

Uploaded on: 27-11-2019

COPY OF LICENSE ALONG WITH SCHEDULE OF LAND

Uploaded on: 26-11-2019

A COPY OF THE DRAFT ALLOTMENT LETTER

Uploaded on: 27-11-2019

DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.

Uploaded on: 29-11-2019

REP-1 PART-E - LAYOUT PLAN-1

Uploaded on: 04-12-2019

REP-1 PART-E - FLOOR PLAN-TOWER C AND D

Uploaded on: 04-12-2019

REP-1 PART-E - ROADS AND PAVEMENT PLAN

Uploaded on: 04-12-2019

REP-1 PART-E - TOWER E_ELEVATIONS

Uploaded on: 04-12-2019

REP-1 PART-E - TOWER A & B_ELEVATIONS

Uploaded on: 04-12-2019

REP-1 PART-E - TOWER A & B_ELEVATIONS-01

Uploaded on: 04-12-2019

REP-1 PART-E - SITE PLAN

Uploaded on: 04-12-2019

CASH FLOW STATEMENT OF THE PROPOSED PROJECT

Uploaded on: 03-12-2019

BALANCE SHEET FOR 2017

Uploaded on: 03-12-2019

BALANCE SHEET FOR 2018

Uploaded on: 03-12-2019

BALANCE SHEET FOR 2019

Uploaded on: 03-12-2019

REP-1 PART-E - BUILDING PLAN-TOWER C AND D

Uploaded on: 04-12-2019

REP-1 PART-E - BUILDING PLAN-TOWER E

Uploaded on: 04-12-2019

REP-1 PART-E - FLOOR PLAN-TOWER A AND B

Uploaded on: 04-12-2019

IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN

Uploaded on: 04-12-2019

IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN

Uploaded on: 04-12-2019

REP-1 PART-E - TOWER C & D_ELEVATIONS

Uploaded on: 04-12-2019

REP-1 PART-E - ELECTRICITY SUPPLY PLAN

Uploaded on: 04-12-2019

REP-1 PART-E - FLOOR PLAN-TOWER E

Uploaded on: 04-12-2019

REP-1 PART-E - TOWER C & D_ELEVATIONS-02

Uploaded on: 04-12-2019

NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT

Uploaded on: 09-12-2019

REP-1 PART-E - BUILDING PLAN-TOWER A AND B

Uploaded on: 04-12-2019

DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD

Uploaded on: 04-12-2019

DEMARCATION PLAN

Uploaded on: 09-12-2019

SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN

Uploaded on: 05-12-2019

CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT

Uploaded on: 09-12-2019

Statutory Approvals

TOWN AND COUNTRY PLANING DEPARTMENTDate: 16-07-2011Status: ALREADY BEEN OBTAINED
FIRE DEPARTMENTDate: 13-12-2013Status: ALREADY BEEN OBTAINED
STATE ENVIRONMENT IMPACT ASSESSMENT AUTHORITY HARYANADate: 15-04-2015Status: ALREADY BEEN OBTAINED
HARYANA STATE POLLUTION CONTROL BOARD, PANCHKULADate: 01-01-2018Status: ALREADY BEEN OBTAINED
DEPUTY COMMISSIONER GURUGRAM - FOREST AND ARAVALIDate: 13-01-2014Status: ALREADY BEEN OBTAINED
AIRPORT AUTHORITY OF INDIADate: 20-02-2013Status: ALREADY BEEN OBTAINED
Lay out PlanApproved: Yes
Demarcation PlanApproved: Yes
Zoning PlanApproved: Yes
Building PlanApproved: Yes
Site PlanApproved: Yes
Floor PlanApproved: Yes
Apartment PlansApproved: Yes
Elevation SectionApproved: Yes
Detail of Permissible FARApproved: Yes
Detail of covered area achieved FARApproved: Yes
ROADS AND PAVEMENT PLANApproved: Yes
ELECTRICITY SUPPLY PLANApproved: Yes
WATER SUPPLY PLANApproved: No
SEWERAGE AND GARBAGE DISPOSAL PLANApproved: No
STROM WATER DRAINAGEApproved: No
10% LAND TO BE TRANSFERRED TO THE GOVT. FOR COMMUNITY FACILITYApproved: No
STREET LIGHTING PLANApproved: No
PARKING PLANApproved: No

Facilities

INTERNAL ROADS AND PAVEMENTSYET TO BE PREPARED
WATER SUPPLY SYSTEMYET TO BE PREPARED
STORM WATER DRAINAGEYET TO BE PREPARED
ELECTRICITY SUPPLY SYSTEMYET TO BE PREPARED
SEWAGE TREATMENT & GARBAGE DISPOSALYET TO BE PREPARED
STREET LIGHTINGYET TO BE PREPARED
SECURITY AND FIRE FIGHTINGYET TO BE PREPARED
PLAYGROUNDS AND PARKSYET TO BE PREPARED
CLUB HOUSE/COMMUNITY CENTREYET TO BE PREPARED
SHOPPING AREAYET TO BE PREPARED
RENEWABLE ENERGY SYSTEMYET TO BE PREPARED
SCHOOLYET TO BE PREPARED
HOSPITAL/DISPENSARYYET TO BE PREPARED
ANY OTHERYET TO BE PREPARED
PARKINGYET TO BE PREPARED
UNDERGROUND TANKYET TO BE PREPARED
RAIN WATER HARVESTINGYET TO BE PREPARED
ELCTRICAL SUB STATIONYET TO BE PREPARED

NOC

ROADSProvider: HSVPApproval Status: Approved
WATER SUPPLYProvider: HSVPApproval Status: Approved
ELECTRICITYProvider: DHBVNApproval Status: Approved
SEWAGE DISPOSALProvider: HSVPApproval Status: Approved
STORM WATER DRAINAGEProvider: HUDAApproval Status: Approved

Project Team

Authorized Representative

D S GILL
Name
D S GILL
PAN
XXXX107K
Email
DSGILL@IMPERIASTRUCTURES.COM
Mobile
8586928776
Landline
01146469901
Address
H-419 NARAINA VIHAR NEW DELHI-110028

Managing Director/CEO

HARPREET SINGH BATRA
Name
HARPREET SINGH BATRA
PAN
XXXX470R
Email
HARPREET@IMPERIASTRUCTURES.COM
Mobile
9810010611
Landline
01146469999
Address
B-9 CHIRAG ENCLAVE GREATER KAILASH - 1 New Delhi 110048

Directors

BRAJINDER SINGH BATRA
Name
BRAJINDER SINGH BATRA
PAN
XXXX929R
Email
BRAJINDER@IMPERIASTRUCTURES.COM
Mobile
9810056500
Landline
01146469999
Address
B-9 CHIRAG ENCLAVE GREATER KAILASH - 1 New Delhi 110048

Contact Details

Project ContactEmail: rera_gurugram@imperiastructures.inMobile: 9643104138Landline: 9643104138
Project Contact PersonName: JAGPAL SINGH DAGAREmail: rera_gurugram@imperiastructures.inMobile: 9643104138Landline: 9643104138

Land Details

Land Area8.50 (Acre)
Proposed FAR1.75
Permissible FAR1.75
Total Licensed Land17 (Acre)

Land Usage

Land Cost3688 Lakhs
Other Cost3865.57 Lakhs
Estimated Project Cost24584.50 Lakhs
Estimated Infrastructure Cost2861.28 Lakhs
Estimated Apartment Construction Cost10014.47 Lakhs

Total Infrastructure Expenditure

ParticularsExpenditure (in Lakhs)
Other0
Shopping area0
Roads & Pavements0
Water Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Electricity Supply System0
Clubhouse/community centres0
Sewerage treatment & garbage disposal0

Quarterly Infrastructure Expenditure

2019 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres--169.87-
Electrical Substation--318.51-
Electricity Supply System--276.04-
Other--0-
Parking--53.08-
Parks and Playgrounds--53.08-
Rain Water Harvesting Tanks--31.85-
Renewable Energy System--53.08-
Roads & Pavements--318.51-
Security and Fire Fighting--318.51-
Sewerage treatment & garbage disposal--159.25-
Shopping area--63.7-
Storm Water Drainage--106.17-
Street Light--42.47-
Underground Tanks--53.08-
Water Supply System--106.17-

Other Details

Construction Specifications

FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILES/WOODEN LAMINATED/CERAMIC TILES
WALL FINISHING DETAILSOBD/CERAMIC DADO
KITCHEN DETAILSVITRIFIED TILE ON FLOORING/CERAMIC TILES DADO & OBD PAINT
BATHROOM FITTINGSISI MARKED
WOOD WORK ETCN.A.
DOORS AND WINDOS FRAMESAL. EXTERNAL WOODEN DOOR FRAMES FOR INTERNAL DOORS
GLASS WORKISI MARKED
ELECTRIC FITTINGSISI MARKED
CONDUCTING AND WIRING DETAILSISI MARKED
CUPBOARD DETAILSN.A.
WATER STORAGEOHT/TOWER & UGT FOR WHOLE CAMPUS
LIFT DETAILSISI MARKED
EXTERNAL GLAZINGSISI MARKED
WINDOWS/GLAZINGSISI MARKED
DOORSAL. EXTERNAL FLUSH DOORS INTERNAL
MAIN DOORSFLUSH DOORS
INTERNAL DOORSFLUSH DOORS
AIR CONDITIONINGN.A.
ELECTRICAL FITTINGSISI MARKED
CNG PIPE LINEN.A.
PROVISION OF WIFI AND BROADBAND FACILITYN.A.
EXTERNAL FINISHING/COLOUR SCHEMEEXTERNAL GRADE PAINT
INTERNAL FINISHINGWALLS: OBD PAINT/CERAMIC TILES FLOORING: VITRIFIED TILES/CERMAIC TILES/WOODEN LAMINATE

Unit-wise Specifications

TOILET
FLOORCERAMIC TILES
WALLSCERAMIC TILE DADO
CEILINGFALSE CEILING
COUNTERSN.A.
SANITARY WARE/CP FITTINGSISI MARKED
FIXTURESISI MARKED
KITCHEN
FLOORVITRIFIED TILES
WALLSDADO IN CERAMIC TILES & OBD PAINT
CEILINGOBD PAINT
COUNTERSGRANITE
FIXTURESISI MARKED
KITCHEN APPLIANCESN.A.
SIT-OUTS
FLOORN.A.
WALLS & CEILINGN.A.
RAILINGSN.A.
FIXTURESN.A.
BED ROOMS
FLOORWOODEN LAMINATES
WALLSOBD PAINT
CEILINGOBD PAINT
WARDROBESN.A.
MASTER TOILET
FLOORCERAMIC TILES
WALLSCERAMIC TILES DADO
CEILINGFALSE CEILING
COUNTERSN.A.
SANITARY WARE/CP FITTINGSISI MARKED
FITTING/FIXTURESISI MARKED
MASTER BEDROOM/DRESSROOM
FLOORWOODEN LAMINATED
WALLSOBD PAINT
CEILINGOBD PAINT
MODULAR WARDROBESN.A.
LIVING/DINING/FOYER/FAMILY LOUNGE
FLOORVITRIFIED TILES
WALLSOBD PAINT
CEILINGOBD PAINT
UTILITY ROOMS/UTILITY BALCONY/TOILET
FLOORCERAMIC TILES
WALLS & CEILINGWALLS OBD PAINT/CERAMIC TILES DADO FLOORING: CERAMIC TILES
TOILETCERAMIC TILES FLOORING, CERAMIC TILES DADO
BALCONYCERAMIC TILES FLOORING

Fee Details

Payment 1
amount:604600
cheque no:13748
draft date:27-07-2017
payable to:HRERA Gurugram
payee bank:AXIS BANK