Get Full Cost BreakupUploaded on: 15-05-2024
Uploaded on: 15-05-2024
Uploaded on: 15-05-2024
Uploaded on: 24-07-2024





| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electric Sub Station | - | - | 50.65 | - |
| Electric Substation | - | - | 50.65 | - |
| Electricity Supply System | 0 | 0 | 247 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parking | - | - | - | 41.67 |
| Parks | - | - | - | - |
| Parks and Playgrounds | 0 | 0 | 0 | 15.46 |
| Rain water Harvesting | - | - | 24.73 | - |
| Rain water harvesting | - | - | 24.73 | - |
| Renewable Energy System | - | - | - | 37.65 |
| Renewable energy system | - | - | - | 37.65 |
| Roads & Pavements | 0 | 0 | 18.56 | 18.56 |
| Security and Fire Fighting | - | - | 61.84 | - |
| Sewerage treatment & garbage disposal | 0 | 30.92 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Storm water drainage | - | 24.69 | - | - |
| Street light | 12.35 | 12.35 | - | - |
| Water Supply System | 0 | 24.69 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | - | - |
| Electric Sub Station | - | - | - | - |
| Electric Substation | - | - | - | - |
| Electricity Supply System | 0 | 0 | - | - |
| Other | 0 | 0 | - | - |
| Parking | 41.67 | - | - | - |
| Parks | - | 41.67 | - | - |
| Parks and Playgrounds | 15.46 | 0 | - | - |
| Rain water Harvesting | - | - | - | - |
| Rain water harvesting | - | - | - | - |
| Renewable Energy System | - | - | - | - |
| Renewable energy system | 37.65 | - | - | - |
| Roads & Pavements | 0 | 0 | - | - |
| Security and Fire Fighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | - | - |
| Shopping area | 0 | 0 | - | - |
| Storm Water Drainage | 0 | 0 | - | - |
| Storm water drainage | - | - | - | - |
| Street light | - | - | - | - |
| Water Supply System | 0 | 0 | - | - |
Emperium Premio is located in 37c, Gurgaon. The project is spread across 3.79 acres.
Yes. Emperium Premio is registered under RERA-GRG-1651-2024 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Emperium Premio is 31 March 2030.
Emperium Premio is developed by EMPERIUM INFRASTRUCTURE PRIVATE LIMITED.
Emperium Premio offers 2 BHK, 3 BHK, 4 BHK and Penthouse Duplex configurations.