Launch Date
Completion Date
RERA ID
Uploaded on: 27-08-2021
Uploaded on: 27-08-2021
Uploaded on: 10-09-2021
Uploaded on: 10-09-2021
Uploaded on: 10-09-2021
Uploaded on: 10-09-2021
Uploaded on: 10-09-2021
Uploaded on: 10-09-2021
Uploaded on: 10-09-2021
Uploaded on: 10-09-2021
Uploaded on: 21-10-2021
Uploaded on: 21-10-2021
Uploaded on: 21-10-2021
Uploaded on: 10-11-2021
Uploaded on: 10-11-2021
Uploaded on: 10-11-2021
Uploaded on: 10-11-2021
Uploaded on: 10-11-2021
Uploaded on: 10-11-2021



| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical Panels | - | - | - | - |
| Electrical Sub Station | - | - | - | - |
| Electricity Supply System | 0 | 0 | 0 | 1.38 |
| Miscellaneous Works | - | - | - | - |
| Miscellanous Works | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| Other cost including Contingencies and LC and GST | 0.4 | 0.63 | 1.31 | 2.38 |
| Parking | - | - | - | - |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rainwater Harvesting System | - | - | - | - |
| Roads & Pavements | 0.39 | 0.79 | 0.39 | 0 |
| STP | - | - | - | - |
| Security and Fire Fighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 0.44 | 0.65 | 1.74 | 2.61 |
| Shopping area | 0 | 0 | 0 | 0 |
| Signages and Plot Demarcation | - | - | - | - |
| Sinages and Plot Demarcation | - | - | - | - |
| Storm Water Drainage | 0.92 | 1.39 | 3.69 | 5.54 |
| Street Lights | - | - | - | - |
| Switching Station Works | - | - | - | - |
| UG Tank | - | - | - | - |
| Water Supply System | 0 | 0 | 0 | 0.97 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical Panels | - | - | - | - |
| Electrical Sub Station | 0 | 0 | 0 | 5.96 |
| Electricity Supply System | 3.46 | 7.61 | 11.06 | 15.21 |
| Miscellaneous Works | - | - | - | - |
| Miscellanous Works | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| Other cost including Contingencies and LC and GST | 4.44 | 12.87 | 22.01 | 29.95 |
| Parking | - | - | - | - |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rainwater Harvesting System | - | - | - | - |
| Roads & Pavements | 1.58 | 7.89 | 10.26 | 14.99 |
| STP | 0 | 8.03 | 19.57 | 14.55 |
| Security and Fire Fighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 3.92 | 3.92 | 3.05 | 2.18 |
| Shopping area | 0 | 0 | 0 | 0 |
| Signages and Plot Demarcation | - | - | - | - |
| Sinages and Plot Demarcation | - | - | - | - |
| Storm Water Drainage | 8.31 | 8.31 | 6.46 | 4.62 |
| Street Lights | - | - | - | - |
| Switching Station Works | 0 | 9.67 | 24.18 | 53.19 |
| UG Tank | 0 | 6.24 | 15.21 | 11.31 |
| Water Supply System | 2.42 | 5.33 | 7.75 | 10.66 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical Panels | 0 | 5.49 | 54.85 | 43.88 |
| Electrical Sub Station | 14.41 | 16.89 | 10.93 | 1.49 |
| Electricity Supply System | 13.14 | 8.99 | 5.53 | 2.77 |
| Miscellaneous Works | - | - | - | - |
| Miscellanous Works | 0 | 0 | 5.89 | 4.71 |
| Other | 0 | 0 | 0 | 0 |
| Other cost including Contingencies and LC and GST | 36.23 | 48.85 | 61.92 | 45.29 |
| Parking | 0 | 0 | 2.86 | 4.48 |
| Parks and Playgrounds | 7.94 | 37.43 | 56.55 | 42.13 |
| Rainwater Harvesting System | 0 | 0 | 1.97 | 3.08 |
| Roads & Pavements | 14.99 | 11.05 | 7.89 | 4.73 |
| STP | 10.54 | 11.21 | 11.37 | 7.36 |
| Security and Fire Fighting | 0 | 0 | 1.05 | 1.65 |
| Sewerage treatment & garbage disposal | 1.52 | 1.09 | 0.65 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Signages and Plot Demarcation | 0 | 0 | 4.22 | 6.61 |
| Sinages and Plot Demarcation | - | - | - | - |
| Storm Water Drainage | 3.23 | 2.31 | 1.39 | 0 |
| Street Lights | 0 | 0 | 4.61 | 7.23 |
| Switching Station Works | 77.37 | 106.38 | 91.88 | 62.86 |
| UG Tank | 8.19 | 8.71 | 8.84 | 5.72 |
| Water Supply System | 9.21 | 6.3 | 3.88 | 1.94 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | - | - | - |
| Electrical Panels | 5.49 | - | - | - |
| Electrical Sub Station | 0 | - | - | - |
| Electricity Supply System | 0 | - | - | - |
| Miscellaneous Works | 0.59 | - | - | - |
| Miscellanous Works | - | - | - | - |
| Other | 0 | - | - | - |
| Other cost including Contingencies and LC and GST | 22.36 | - | - | - |
| Parking | 2.19 | - | - | - |
| Parks and Playgrounds | 17.99 | - | - | - |
| Rainwater Harvesting System | 1.51 | - | - | - |
| Roads & Pavements | 3.95 | - | - | - |
| STP | 1 | - | - | - |
| Security and Fire Fighting | 0.81 | - | - | - |
| Sewerage treatment & garbage disposal | 0 | - | - | - |
| Shopping area | 0 | - | - | - |
| Signages and Plot Demarcation | - | - | - | - |
| Sinages and Plot Demarcation | 3.23 | - | - | - |
| Storm Water Drainage | 0 | - | - | - |
| Street Lights | 3.54 | - | - | - |
| Switching Station Works | 58.03 | - | - | - |
| UG Tank | 0.78 | - | - | - |
| Water Supply System | 0 | - | - | - |