Have queries on this Project?
Uploaded on: 18-10-2023
Uploaded on: 19-04-2024
Uploaded on: 19-04-2024



| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parking | - | - | - | - |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| STP | 12 | 12 | 12 | 12 |
| Security and Firefighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Street Lighting | - | - | - | - |
| Underground Water Tank | 13 | 13 | 13 | 13 |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parking | - | - | - | - |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| STP | 12 | 12 | 12 | 12 |
| Security and Firefighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 34 | 34 | 34 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 34 | 34 | 34 |
| Street Lighting | - | - | - | - |
| Underground Water Tank | 13 | 13 | 13 | 13 |
| Water Supply System | 0 | 12.5 | 12.5 | 12.5 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 44 | 44 | 44 | 44 |
| Other | 0 | 0 | 0 | 0 |
| Parking | - | - | - | 8 |
| Parks and Playgrounds | 0 | 0 | 0 | 92.5 |
| Roads & Pavements | 0 | 18 | 18 | 18 |
| STP | 12 | 12 | 12 | 12 |
| Security and Firefighting | - | - | 11 | 11 |
| Sewerage treatment & garbage disposal | 34 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 34 | 0 | 0 | 0 |
| Street Lighting | - | - | - | 2 |
| Underground Water Tank | 13 | 13 | 13 | 13 |
| Water Supply System | 12.5 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | - |
| Electricity Supply System | 44 | 0 | 0 | - |
| Other | 0 | 0 | 0 | - |
| Parking | 8 | 8 | 8 | - |
| Parks and Playgrounds | 92.5 | 92.5 | 92.5 | - |
| Roads & Pavements | 18 | 0 | 0 | - |
| STP | 12 | 12 | 12 | - |
| Security and Firefighting | 11 | 11 | 11 | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | - |
| Shopping area | 0 | 0 | 0 | - |
| Storm Water Drainage | 0 | 0 | 0 | - |
| Street Lighting | 2 | 2 | - | - |
| Underground Water Tank | 13 | 13 | 13 | - |
| Water Supply System | 0 | 0 | 0 | - |
Bptp The Amaario is located in Gurgaon.
Yes. Bptp The Amaario is registered under RERA-GRG-1470-2023 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Bptp The Amaario is 30 September 2031.
Bptp The Amaario is developed by COUNTRYWIDE PROMOTERS PRIVATE LIMITED.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.