Launch Date
Completion Date
RERA ID
Uploaded on: 17-02-2020
Uploaded on: 12-12-2019
Uploaded on: 12-12-2019
Uploaded on: 28-01-2021
Uploaded on: 07-02-2020
Uploaded on: 07-02-2020
Uploaded on: 07-02-2020
Uploaded on: 07-02-2020
Uploaded on: 07-02-2020
Uploaded on: 07-02-2020
Uploaded on: 07-02-2020
Uploaded on: 07-02-2020
Uploaded on: 07-02-2020
Uploaded on: 01-06-2021
Uploaded on: 22-07-2021
Uploaded on: 27-07-2021
Uploaded on: 28-07-2021
Uploaded on: 27-07-2021
Uploaded on: 27-07-2021
Uploaded on: 27-07-2021
Uploaded on: 28-07-2021




| Particulars | Expenditure (in Lakhs) |
|---|---|
| STP | 61.08 |
| Other | 0 |
| School | 0 |
| Parking | 0 |
| Shopping area | 0 |
| Security System | 0 |
| Street Lighting | 0 |
| Roads & Pavements | 18.15 |
| Water Supply System | 0 |
| Rainwater Harvesting | 6.08 |
| Storm Water Drainage | 35.87 |
| Electrical SubStation | 10.21 |
| Parks and Playgrounds | 0.33 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Underground Water Tank and Pump Room | 0 |
| Sewerage treatment & garbage disposal | 15.09 |
| Boundary Wall and Entrance and Exit Gates | 49 |
| Fire Fighting Services and Security System | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall and Entry Exit Gate and Signage etc | - | - | - | - |
| Clubhouse/community centres | - | - | - | 0 |
| Electrical Sub Station | - | - | - | - |
| Electrical SubStation | - | - | - | - |
| Electricity Supply System | - | - | - | 0 |
| Fire Fighting Services and Security | - | - | - | - |
| Fire Fighting System and Security | - | - | - | - |
| Other | - | - | - | 0 |
| Other Cost | - | - | - | - |
| Parking | - | - | - | - |
| Parks and Playgrounds | - | - | - | 0 |
| Rain Water Harvesting | - | - | - | - |
| Roads & Pavements | - | - | - | 0 |
| STP | - | - | - | - |
| School | - | - | - | - |
| Sewerage treatment & garbage disposal | - | - | - | 0 |
| Shopping area | - | - | - | 0 |
| Storm Water Drainage | - | - | - | 0 |
| Street Lighting | - | - | - | - |
| Underground Water Tank and Pump Room | - | - | - | - |
| Water Supply System | - | - | - | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall and Entry Exit Gate and Signage etc | - | - | - | - |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical Sub Station | - | - | - | - |
| Electrical SubStation | - | - | - | - |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Fire Fighting Services and Security | - | - | - | - |
| Fire Fighting System and Security | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| Other Cost | - | - | - | - |
| Parking | - | - | - | - |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain Water Harvesting | - | - | - | - |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| STP | - | - | - | - |
| School | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Street Lighting | - | - | - | - |
| Underground Water Tank and Pump Room | - | - | - | - |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall and Entry Exit Gate and Signage etc | 0 | - | 0 | 15 |
| Clubhouse/community centres | 0 | 0 | 0 | 39.5 |
| Electrical Sub Station | - | - | 50 | 50 |
| Electrical SubStation | - | - | - | - |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Fire Fighting Services and Security | - | - | - | - |
| Fire Fighting System and Security | 0 | 0 | 0 | 0 |
| Other | 0 | 0 | 1 | 1 |
| Other Cost | 0 | 0 | - | - |
| Parking | - | - | 5 | 5 |
| Parks and Playgrounds | 0 | 0 | 0 | 5 |
| Rain Water Harvesting | - | - | 0 | 5 |
| Roads & Pavements | 0 | 0 | 20 | 20 |
| STP | - | - | 5 | 5 |
| School | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 2 | 2 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 3 | 3 |
| Street Lighting | 0 | 0 | 3 | 5 |
| Underground Water Tank and Pump Room | 0 | 0 | 50 | 50 |
| Water Supply System | 0 | 0 | 3 | 3 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall and Entry Exit Gate and Signage etc | 15 | 0 | 3 | 0 |
| Clubhouse/community centres | 80 | 100 | 100 | 115 |
| Electrical Sub Station | - | - | - | - |
| Electrical SubStation | 100 | 30 | 30 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Fire Fighting Services and Security | 1.7 | 0 | 0 | 0 |
| Fire Fighting System and Security | - | - | - | - |
| Other | 1 | 0 | 0 | 1 |
| Other Cost | - | - | - | - |
| Parking | - | - | 0 | 5 |
| Parks and Playgrounds | 5 | 0 | 0 | 0 |
| Rain Water Harvesting | 3 | 0 | 0 | 0 |
| Roads & Pavements | 20 | 0 | 20 | 0 |
| STP | 32 | 0 | - | 5 |
| School | 0 | - | 0 | - |
| Sewerage treatment & garbage disposal | 1 | 0 | 1 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3 | 2 | 2 | 1 |
| Street Lighting | 5 | 0 | 0 | 2 |
| Underground Water Tank and Pump Room | 30 | 30 | - | 10 |
| Water Supply System | 3 | 0 | 0 | 2 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall and Entry Exit Gate and Signage etc | 3 | 0 | 0 | 5 |
| Clubhouse/community centres | 39.5 | 0 | 0 | 0 |
| Electrical Sub Station | - | - | - | - |
| Electrical SubStation | 10 | 20 | 0 | 11.91 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Fire Fighting Services and Security | 0 | 0 | 0 | 0 |
| Fire Fighting System and Security | - | - | - | - |
| Other | 1 | 1 | 1 | 1 |
| Other Cost | - | - | - | - |
| Parking | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 3 | 0 | 0 | 3.31 |
| Rain Water Harvesting | 0 | 0 | 0 | 0 |
| Roads & Pavements | 15 | 0 | 7.86 | 0 |
| STP | 0 | 0 | 5.45 | 0 |
| School | - | - | - | - |
| Sewerage treatment & garbage disposal | 1 | 0 | 0 | 0.77 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 1 | 1 | 1 | 1 |
| Street Lighting | 0 | 0 | 0 | 0 |
| Underground Water Tank and Pump Room | 0 | 0 | 0 | 10.96 |
| Water Supply System | 0 | 0 | 1.55 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall and Entry Exit Gate and Signage etc | - | - | - | - |
| Clubhouse/community centres | 0 | - | - | - |
| Electrical Sub Station | - | - | - | - |
| Electrical SubStation | 1 | - | - | - |
| Electricity Supply System | 0 | - | - | - |
| Fire Fighting Services and Security | - | - | - | - |
| Fire Fighting System and Security | - | - | - | - |
| Other | 3.1 | - | - | - |
| Other Cost | - | - | - | - |
| Parking | - | - | - | - |
| Parks and Playgrounds | 0 | - | - | - |
| Rain Water Harvesting | 1.43 | - | - | - |
| Roads & Pavements | 0 | - | - | - |
| STP | - | - | - | - |
| School | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | - | - | - |
| Shopping area | 0 | - | - | - |
| Storm Water Drainage | 0.48 | - | - | - |
| Street Lighting | 3.19 | - | - | - |
| Underground Water Tank and Pump Room | - | - | - | - |
| Water Supply System | 0 | - | - | - |