NEWActive

THE VENETIAN

GURUGRAM, BADSHAHPUR ST
19-04-2020
Launch Date
NEW
Type
2024-09-02
Completion Date

Overview

Launch Date

19-04-2020

Completion Date

2024-09-02

RERA ID

RERA-GRG-629-2020

Basic Details

Project NameTHE VENETIAN
Project IDRERA-GRG-629-2020
Project TypeNEW
Applicant TypeCompany
Submission Date19-04-2020 02:55:46 AM
Builder NameOCEAN SEVEN BUILDTECH PVT LTD
CINU45201RJ2006PTC022751
PANXXXX039J
Emailcorporate@osbgroup.co.in
Websitehttp://www.osbgroup.co.in
Phone (Mobile)9205484982
Phone (Landline)01244234290
Registered Address505-506,5TH FLOOR, TOWER B-4, SPAZE I-TECH PARK, SECTOR-49, GURUGRAM
Project AddressSECTOR-70,BADSHAHPUR
DistrictGURUGRAM
TehsilBADSHAHPUR ST

Bank Details

Bank NameAXIS BANK, SECTOR-49,GURUGRAM
Account Number920020023430126
IFSC CodeUTIB0001262
MICR Code110211104
Branch Code1262

Account Related Information

Annex copy of the balance sheet of last 3 yearsYes
In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.No
Name and address of the person/persons who would ordinarily be operating the account (Change at any time must be intimated to the Authority)Ram Autar Rohilla
Attach certificate issued by a Chartered Accountant that the applicant has not defaulted in its debt liabilities in the past five years in folder D. (In case of default, give details)UPLOADED

Development Details

Land Area5.10 (Acre)
Proposed FAR2.25
Permissible FAR2.25
Total Licensed Land5.10 (Acre)

Land Usage

PLOTS TO BE SOLD0
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS2640.00
CONSTRUCTION OF ROADS0
PAVEMENTS0
PARKS AND PLAYGROUNDS0
GREEN BELTS3387.551
VEHICLE PARKINGS8304.122
ELECTRICITY SUB-STATION25.00
CLUB HOUSE185.00
SEWAGE AND SOLID WASTE TREATMENT FACILITY178.627
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
ANY OTHER4757.446
ANGANWADI185.00
COMMERCIAL917.510
Total20580.256

Cost Details

Land Cost5995.512 Lakhs
Other Cost1420.00 Lakhs
Estimated Project Cost15692.145 Lakhs
Estimated Infrastructure Cost592.480 Lakhs
Estimated Apartment Construction Cost7684.153 Lakhs

Documents

APARTMENT PLANS

Uploaded on: 02-11-2020

SUPERIMPOSED SITE PLAN

Uploaded on: 02-11-2020

DUAL PIPEING

Uploaded on: 02-11-2020

ELEVATIONS

Uploaded on: 02-11-2020

STRUCTURAL DRAWINGS

Uploaded on: 02-11-2020

ELECTRICITY

Uploaded on: 02-11-2020

ROAD PLAN

Uploaded on: 02-11-2020

DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD

Uploaded on: 02-11-2020

FIRE FIGHTING LAYOUT

Uploaded on: 02-11-2020

FLOOR PLANS

Uploaded on: 02-11-2020

LICENSE INFORMATION

Uploaded on: 02-11-2020

STORM WATER

Uploaded on: 02-11-2020

PARKING PLAN

Uploaded on: 02-11-2020

COLLABORATION AGREEMENT

Uploaded on: 02-11-2020

PLUMBING DRG

Uploaded on: 02-11-2020

SECTION PLANS

Uploaded on: 02-11-2020

SEWARAGE LAYOUT

Uploaded on: 02-11-2020

STREET LIGHT AND LANDSCAPE PLAN

Uploaded on: 02-11-2020

SWM PLAN

Uploaded on: 02-11-2020

WATER PLAN

Uploaded on: 02-11-2020

IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN

Uploaded on: 24-02-2020

A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS

Uploaded on: 26-02-2020

SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN

Uploaded on: 26-02-2020

DEMARCATION PLAN

Uploaded on: 22-03-2020

COPY OF LICENSE ALONG WITH SCHEDULE OF LAND

Uploaded on: 25-03-2020

CASH FLOW STATEMENT OF THE PROPOSED PROJECT

Uploaded on: 18-04-2020

NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT

Uploaded on: 18-04-2020

CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT

Uploaded on: 18-04-2020

DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.

Uploaded on: 18-04-2020

IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN

Uploaded on: 18-04-2020

ZONING PLAN

Uploaded on: 21-02-2020

Statutory Approvals

LICENSEDate: 05-09-2019Status: ALREADY BEEN OBTAINED
BUILDING PLANDate: 07-02-2020Status: ALREADY BEEN OBTAINED
Lay out PlanApproved: Yes
Demarcation PlanApproved: Yes
Zoning PlanApproved: Yes
Building PlanApproved: Yes
Site PlanApproved: Yes
Floor PlanApproved: Yes
Apartment PlansApproved: Yes
Elevation SectionApproved: Yes
Detail of Permissible FARApproved: Yes
Detail of covered area achieved FARApproved: Yes

Facilities

INTERNAL ROADS AND PAVEMENTSSUBMITTED TO HUDA
WATER SUPPLY SYSTEMSUBMITTED TO HUDA
STORM WATER DRAINAGESUBMITTED TO HUDA
ELECTRICITY SUPPLY SYSTEMSUBMITTED TO HUDA
SEWAGE TREATMENT & GARBAGE DISPOSALSUBMITTED TO HUDA
STREET LIGHTINGSUBMITTED TO HUDA
SECURITY AND FIRE FIGHTINGSUBMITTED TO HUDA
PLAYGROUNDS AND PARKSSUBMITTED TO HUDA
CLUB HOUSE/COMMUNITY CENTRESUBMITTED TO HUDA
SHOPPING AREASUBMITTED TO HUDA
RENEWABLE ENERGY SYSTEMSUBMITTED TO HUDA
SCHOOLYET TO BE PREPARED
HOSPITAL/DISPENSARYYET TO BE PREPARED
ANY OTHERYET TO BE PREPARED
UGTSUBMITTED TO HUDA
PARKINGSUBMITTED TO HUDA
RAIN WATER HARVESTINGSUBMITTED TO HUDA
ELECTRICAL SUB STATIONSUBMITTED TO HUDA
STPSUBMITTED TO HUDA

NOC

ROADSProvider: HUDAApproval Status: Approved
WATER SUPPLYProvider: GMDA/HUDAApproval Status: Approved
ELECTRICITYProvider: DHBVNApproval Status: Approved
SEWAGE DISPOSALProvider: GMDA/HUDAApproval Status: Approved
STORM WATER DRAINAGEProvider: GMDA/HUDAApproval Status: Approved

Project Team

Authorized Representative

SANJEEV KUMAR
Name
SANJEEV KUMAR
PAN
XXXX859H
Email
sanjeev@osbgroup.co.in
Mobile
9205484982
Landline
0124423490
Address
H.NO 2395 MOGA COLONY BADSHAHPUR

Managing Director/CEO

SWARAJ SINGH YADAV
Name
SWARAJ SINGH YADAV
PAN
XXXX882J
Email
corporate@osbgroup.co.in
Mobile
7620340557
Landline
0124423490
Address
VILL WARHE TEHSIL RAIGADMAHARASHTRA

Directors

DESH RAJ
Name
DESH RAJ
PAN
XXXX852P
Email
corporate@osbroup.co.in
Mobile
9928080811
Landline
0124423490
Address
VILL WARHE TEHSIL RAIGAD MAHARASHTRA

Contact Details

Project ContactEmail: corporate@osbgroup.co.inMobile: 9205484982Landline: 0124423490
Project Contact PersonName: SANJEEV KUMAREmail: sanjeev@osbgroup.co.inMobile: 9205484982Landline: 0124423491

Land Details

Land Area5.10 (Acre)
Proposed FAR2.25
Permissible FAR2.25
Total Licensed Land5.10 (Acre)

Land Usage

Land Cost5995.512 Lakhs
Other Cost1420.00 Lakhs
Estimated Project Cost15692.145 Lakhs
Estimated Infrastructure Cost592.480 Lakhs
Estimated Apartment Construction Cost7684.153 Lakhs

Total Infrastructure Expenditure

ParticularsExpenditure (in Lakhs)
Other0
Shopping area0
Roads & Pavements2.46
Water Supply System0.02
Storm Water Drainage0
Parks and Playgrounds0
Electricity Supply System0
Clubhouse/community centres0
Sewerage treatment & garbage disposal0

Quarterly Infrastructure Expenditure

2020 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres0000
Electrical Sub Station0000
Electricity Supply System0.16000.02
Other0000
Parking0---
Parks and Playgrounds0000
Rain Water Harvesting0000
Renewable Energy0000
Roads & Pavements4005
STP0.53000
Security and Fire Fighting0000
Sewerage treatment & garbage disposal0000
Shopping area0000
Storm Water Drainage0000
Street Light0.06000
Underground Tank0.1000
Water Supply System0.13000
2021 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres500050
Electrical Sub Station020.230
Electricity Supply System000.050
Other0000
Parking010.280
Parks and Playgrounds000.680
Rain Water Harvesting010.240
Renewable Energy00.200
Roads & Pavements5022
STP000.50.5
Security and Fire Fighting00.2310
Sewerage treatment & garbage disposal00.590.50.5
Shopping area0000
Storm Water Drainage00.9801
Street Light0000
Underground Tank0110
Water Supply System52356
2022 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres050500
Electrical Sub Station2000
Electricity Supply System5052
Other0000
Parking0000
Parks and Playgrounds0000
Rain Water Harvesting0000
Renewable Energy0010
Roads & Pavements3515
STP0000
Security and Fire Fighting001.771.23
Sewerage treatment & garbage disposal2003
Shopping area0000
Storm Water Drainage0110
Street Light0000
Underground Tank0000
Water Supply System1091010
2023 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres0000
Electrical Sub Station5052
Electricity Supply System103105
Other0000
Parking2---
Parks and Playgrounds0000
Rain Water Harvesting1000
Renewable Energy21.5211
Roads & Pavements551010
STP1000
Security and Fire Fighting3221
Sewerage treatment & garbage disposal2.552.55
Shopping area0000
Storm Water Drainage5252
Street Light2121
Underground Tank0.5010
Water Supply System2020520
2024 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres-00-
Electrical Sub Station-11-
Electricity Supply System-2.52.5-
Other-00-
Parking----
Parks and Playgrounds-20-
Rain Water Harvesting-0.50.5-
Renewable Energy-11-
Roads & Pavements-510-
STP-10-
Security and Fire Fighting-11-
Sewerage treatment & garbage disposal-2.52.5-
Shopping area-00-
Storm Water Drainage-2.52.5-
Street Light-11-
Underground Tank-0.50.5-
Water Supply System-55-

Other Details

Construction Specifications

FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILES
WALL FINISHING DETAILSOIL BOND DISTEMPER
KITCHEN DETAILSVITRIFIED TILES/ CERAMIC TILES
BATHROOM FITTINGSISI MARKED CP FITTINGS, W.C & WASHBASIN
WOOD WORK ETCHARDWOOD
DOORS AND WINDOS FRAMESHARD WOOD/ ALUMINIUM /UPVC/SS
GLASS WORKWINDOWS
ELECTRIC FITTINGSCOPPER ELECTRICAL WIRING, ISI MARKED SWITCHES & SWITCHES
CONDUCTING AND WIRING DETAILSISI MARKED SWITCHES & SWITCHES
CUPBOARD DETAILSNIL
WATER STORAGERCC
LIFT DETAILSISI MARKED
EXTERNAL GLAZINGSG.I/SS/UPVC
WINDOWS/GLAZINGSG.I/SS/UPVC
DOORSHARDWOOD
MAIN DOORSHARDWOOD
INTERNAL DOORSBOTH SIDE LAMINATED FLUSH DOOR
AIR CONDITIONINGNO
ELECTRICAL FITTINGSISI MARKED
CNG PIPE LINENO
PROVISION OF WIFI AND BROADBAND FACILITYNO
EXTERNAL FINISHING/COLOUR SCHEMEYELLOW
INTERNAL FINISHINGTILES

Unit-wise Specifications

TOILET
FLOORVITRIFIED TILES/ CERAMIC TILES
WALLSOIL BOND DISTEMPER
CEILINGOIL BOND DISTEMPER
COUNTERSNIL
SANITARY WARE/CP FITTINGSISI MARKED
FIXTURESISI MARKED
KITCHEN
FLOORVITRIFIED TILES/CERAMIC TILES
WALLSOIL BOND DISTEMPER
CEILINGOIL BOND DISTEMPER
COUNTERSGREEN MARBLE/GRANITE
FIXTURESISI MARKED
KITCHEN APPLIANCESNIL
SIT-OUTS
FLOORNIL
WALLS & CEILINGNIL
RAILINGSNIL
FIXTURESNIL
BED ROOMS
FLOORVITRIFIED TILES
WALLSOIL BOND DISTEMPER
CEILINGOIL BOND DISTEMPER
WARDROBESNIL
MASTER TOILET
FLOORVITRIFIED TILES
WALLSOIL BOND DISTEMPER
CEILINGOIL BOND DISTEMPER
COUNTERSGREEN MARBLE/GRANITE
SANITARY WARE/CP FITTINGSISI MARKED
FITTING/FIXTURESISI MARKED
MASTER BEDROOM/DRESSROOM
FLOORVITRIFIED TILES
WALLSOIL BOND DISTEMPER
CEILINGOIL BOND DISTEMPER
MODULAR WARDROBESNIL
LIVING/DINING/FOYER/FAMILY LOUNGE
FLOORVITRIFIED TILES
WALLSOIL BOND DISTEMPER
CEILINGOIL BOND DISTEMPER
UTILITY ROOMS/UTILITY BALCONY/TOILET
FLOORNIL
WALLS & CEILINGNIL
TOILETNIL
BALCONYNIL

Fee Details

Payment 1
amount:1064423
cheque no:11730
draft date:24-08-2020
payable to:HRERA Gurugram
payee bank:AXIS BANK
Payment 2
amount:464950
cheque no:11731
draft date:24-08-2020
payable to:HRERA Gurugram
payee bank:AXIS BANK
Payment 3
amount:14800
cheque no:11733
draft date:25-08-2020
payable to:HRERA Gurugram
payee bank:AXIS BANK
Payment 4
amount:150
cheque no:11734
draft date:25-08-2020
payable to:HRERA Gurugram
payee bank:AXIS BANK