| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | - | 0 | 0 |
| Electrical Sub Station | - | - | 0 | 7.11 |
| Electricity Supply System | - | - | 217.97 | 208.5 |
| Other | - | - | 0 | 0 |
| Parks and Playgrounds | - | - | 0 | 0 |
| Rainwater Harvesting | - | - | - | - |
| Roads & Pavements | - | - | 2.92 | 134.39 |
| STP | - | - | 193.05 | 193.05 |
| Security and Fire Fighting | - | - | 0 | 4.16 |
| Sewerage treatment & garbage disposal | - | - | 42.56 | 42.56 |
| Shopping area | - | - | 0 | 0 |
| Storm Water Drainage | - | - | 57.84 | 57.84 |
| Street Lighting | - | - | - | - |
| Street lighting | - | - | 0 | 0.6 |
| Underground Water Tank | - | - | 213.74 | 213.74 |
| Water Supply System | - | - | 109.54 | 109.54 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical Sub Station | 159.93 | 161.7 | 97.73 | - |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 56.87 | 69.76 | 9.86 |
| Rainwater Harvesting | 2.2 | 50 | 30.22 | - |
| Roads & Pavements | 131.46 | 132.93 | 134.39 | 121.24 |
| STP | 180.46 | - | - | - |
| Security and Fire Fighting | 93.51 | 89.35 | - | - |
| Sewerage treatment & garbage disposal | 41.64 | 42.1 | 39.32 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 56.58 | 57.21 | 53.44 | 0 |
| Street Lighting | 13.6 | 12.99 | - | - |
| Street lighting | - | - | - | - |
| Underground Water Tank | 199.8 | - | - | - |
| Water Supply System | 107.16 | 108.35 | 101.2 | 0 |
Ganga Kashi is located in Sector 89, Gurgaon. The project is spread across 5.00 acres.
Yes. Ganga Kashi is registered under RERA-GRG-2013-2025 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Ganga Kashi is 11 January 2027.
Ganga Kashi is developed by JAI GANGA REALTECH LLP.
Ganga Kashi comprises a total of 276 units.