| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 377.71 |
| Shopping area | 0 |
| Roads & Pavements | 155 |
| Water Supply System | 51.5 |
| Storm Water Drainage | 55.3 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 152 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 72.5 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| HVAC and Basement Electrical and Electrical Sub Station and Renewable Energy System and Electricity Supply System | - | - | - | - |
| Internal Roads and Pavements and Boundary Wall | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 54.5 | 54.5 | 54.5 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Street light and Security and Fire Fighting | 0 | 0 | 10.57 | 10.57 |
| Water Supply System | 0 | 0 | 0 | 0 |
| Water supply and Sewarage System and Storm Water and STP and Rain Water Harvesting and Underground Water Tank | - | - | - | - |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| HVAC and Basement Electrical and Electrical Sub Station and Renewable Energy System and Electricity Supply System | 42.3 | 42.3 | 63.45 | 63.45 |
| Internal Roads and Pavements and Boundary Wall | 25.5 | 34 | 34 | 17 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 81.75 | 81.75 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Street light and Security and Fire Fighting | 10.57 | 10.57 | 21.13 | 21.13 |
| Water Supply System | 0 | 0 | 0 | 0 |
| Water supply and Sewarage System and Storm Water and STP and Rain Water Harvesting and Underground Water Tank | 145.34 | 145.34 | 109 | 109 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| HVAC and Basement Electrical and Electrical Sub Station and Renewable Energy System and Electricity Supply System | 63.45 | 63.45 | 42.3 | 21.15 |
| Internal Roads and Pavements and Boundary Wall | 17 | 17 | 0 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 81.75 | 81.75 | 27.25 | 27.25 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Street light and Security and Fire Fighting | 31.7 | 31.7 | 21.13 | 21.13 |
| Water Supply System | 0 | 0 | 0 | 0 |
| Water supply and Sewarage System and Storm Water and STP and Rain Water Harvesting and Underground Water Tank | 72.67 | 72.67 | 72.67 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | - | - | - |
| Electricity Supply System | 0 | - | - | - |
| HVAC and Basement Electrical and Electrical Sub Station and Renewable Energy System and Electricity Supply System | 21.15 | - | - | - |
| Internal Roads and Pavements and Boundary Wall | - | - | - | - |
| Other | 0 | - | - | - |
| Parks and Playgrounds | 0 | - | - | - |
| Roads & Pavements | 0 | - | - | - |
| Sewerage treatment & garbage disposal | 0 | - | - | - |
| Shopping area | 0 | - | - | - |
| Storm Water Drainage | 0 | - | - | - |
| Street light and Security and Fire Fighting | 21.13 | - | - | - |
| Water Supply System | 0 | - | - | - |
| Water supply and Sewarage System and Storm Water and STP and Rain Water Harvesting and Underground Water Tank | - | - | - | - |
Ashiana Mulberry Phase Iv is located in Gurugram.
Yes. Ashiana Mulberry Phase Iv is registered under RERA-GRG-2030-2025 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Ashiana Mulberry Phase Iv is 31 August 2030.
Ashiana Mulberry Phase Iv is developed by Ashiana.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.
Developed by
15 Projects
EXECUTIVE SUMMARY OF ASHIANA Ashiana Housing Limited is a BSE and NSE listed residential real estate developer incorporated in 1986 and headquartered in New Delhi. The company is promoted by the Gupta family, with Vishal…
Know More about AshianaDeveloped by
4 Projects
EXECUTIVE SUMMARY Ashiana Landkraft is no longer active as a normal independent developer brand. The underlying company, Ashiana Landcraft Realty Private Limited, remains shown as an active corporate entity after an inso…
Know More about Ashiana Landkraft