Have queries on this Project?
Project Size
Unit Configurations
Size
RERA Received
RERA Completion
RERA ID
BSP only. GST, PLC, Parking, IFMS could be add ons.
Get Full Cost BreakupUploaded on: 02-08-2023
Uploaded on: 08-09-2023
Uploaded on: 05-02-2024
Uploaded on: 24-05-2024





| Particulars | Expenditure (in Lakhs) |
|---|---|
| STP | 0 |
| Lift | 0 |
| Other | 0 |
| Parking | 18.31 |
| Shopping area | 0 |
| Electrification | 1.53 |
| Underground Tank | 2.44 |
| Roads & Pavements | 45.78 |
| Water Supply System | 4.58 |
| Storm Water Drainage | 1.22 |
| Electrical meter room | 0 |
| Parks and Playgrounds | 3.05 |
| Renewable Energy System | 0 |
| Electricity Supply System | 2.44 |
| Rain water harvesting pit | 1.22 |
| Clubhouse/community centres | 0 |
| Security and Fire Fighting Services | 2.44 |
| Sewerage treatment & garbage disposal | 6.41 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | - | 0 | 0 |
| Electrical meter room | - | - | 0 | 0 |
| Electricity Supply System | - | - | 0 | 0 |
| Electrification | - | - | 0 | 0 |
| Lift | - | - | 0 | 0 |
| Other | - | - | 0 | 0 |
| Parking | - | - | 14 | 10 |
| Parks and Playgrounds | - | - | 2 | 3 |
| Rain water harvesting pit | - | - | 2 | 2 |
| Renewable Energy System | - | - | 0 | 0 |
| Roads & Pavements | - | - | 14 | 10 |
| STP | - | - | 0 | 4 |
| Security and Fire Fighting Services | - | - | 2 | 3 |
| Sewerage treatment & garbage disposal | - | - | 5 | 4 |
| Shopping area | - | - | 0 | 0 |
| Storm Water Drainage | - | - | 2 | 2 |
| Underground Tank | - | - | 0 | 0 |
| Water Supply System | - | - | 4 | 4 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical meter room | 4 | 4 | 6 | 6 |
| Electricity Supply System | 2 | 3 | 4 | 2 |
| Electrification | 4 | 4 | 3 | 3.5 |
| Lift | 6 | 6 | 8 | 12 |
| Other | 0 | 0 | 0 | 0 |
| Parking | 8 | 7 | 5 | 5 |
| Parks and Playgrounds | 3 | 1 | 2 | 3 |
| Rain water harvesting pit | 1.5 | 0.6 | 1 | 0.8 |
| Renewable Energy System | 1 | 1 | 2 | 0.7 |
| Roads & Pavements | 12 | 12 | 8 | 8 |
| STP | 2 | 3 | 4 | 5 |
| Security and Fire Fighting Services | 3 | 1 | 2 | 2 |
| Sewerage treatment & garbage disposal | 3 | 3 | 4 | 5 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 1.5 | 0.6 | 1 | 0.8 |
| Underground Tank | 4 | 4 | 3 | 2 |
| Water Supply System | 3 | 4 | 2 | 2 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical meter room | 2 | 2 | 3 | 1 |
| Electricity Supply System | 2 | 2 | 2 | 1 |
| Electrification | 1 | 2 | 2 | 3 |
| Lift | 7 | 8 | 6 | 4 |
| Other | 0 | 0 | 0 | 0 |
| Parking | 7 | 6 | 3 | 2 |
| Parks and Playgrounds | 2 | 2 | 3 | 1.5 |
| Rain water harvesting pit | 0.5 | 0.5 | 0.5 | 0.25 |
| Renewable Energy System | 0.7 | 0.8 | 2 | 1 |
| Roads & Pavements | 6 | 6 | 5 | 7 |
| STP | 3 | 3 | 1.5 | 2 |
| Security and Fire Fighting Services | 1 | 1 | 1.5 | 1.5 |
| Sewerage treatment & garbage disposal | 3 | 3 | 1.5 | 1 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0.5 | 0.5 | 0.5 | 0.25 |
| Underground Tank | 1 | 1 | 2 | 1 |
| Water Supply System | 2 | 1 | 1 | 1 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical meter room | 2 | 0.52 | 0 | - |
| Electricity Supply System | 1 | 2 | 0.97 | 0 |
| Electrification | 3 | 2 | 1.49 | - |
| Lift | 2 | 1.5 | 0.54 | - |
| Other | 0 | 0 | 0 | 0 |
| Parking | 3 | 2 | 1.24 | - |
| Parks and Playgrounds | 2 | 2 | 0.97 | 0 |
| Rain water harvesting pit | 0.4 | 0.5 | 0.44 | - |
| Renewable Energy System | 1 | 1.2 | 0.81 | - |
| Roads & Pavements | 8 | 7 | 3.81 | 0 |
| STP | 2 | 1.02 | 0 | - |
| Security and Fire Fighting Services | 1.4 | 2 | 0.57 | - |
| Sewerage treatment & garbage disposal | 2 | 1 | 0.82 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0.4 | 0.5 | 0.44 | 0 |
| Underground Tank | 1.5 | 1.5 | 0.97 | - |
| Water Supply System | 0.7 | 0.8 | 0.44 | 0 |