| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Circular Road | - | - | - | - |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical Sub Station | - | - | - | - |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain Water Harvesting | - | - | - | - |
| Rain water Harvesting | - | - | - | - |
| Rainwater Harvesting | - | - | - | - |
| Roads & Pavements | 30.3 | 30.3 | 30.3 | 30.3 |
| STP | - | - | - | - |
| Security and Firefighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 44.8 | 44.8 | 44.8 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 72 | 72 | 72 |
| Street Lighting | - | - | - | - |
| Under Ground water Tank | - | - | - | - |
| Water Supply System | 0 | 31.9 | 47.85 | 47.85 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Circular Road | - | - | - | 60 |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical Sub Station | - | - | 0 | 93 |
| Electricity Supply System | 0 | 0 | 0 | 281.8 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain Water Harvesting | - | - | - | 56 |
| Rain water Harvesting | - | - | - | - |
| Rainwater Harvesting | - | - | 56 | - |
| Roads & Pavements | 60.6 | 60.6 | 60.6 | 60.6 |
| STP | - | - | - | - |
| Security and Firefighting | - | - | 199.25 | 199.25 |
| Sewerage treatment & garbage disposal | 44.8 | 44.8 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 72 | 72 | 0 | 0 |
| Street Lighting | - | - | 28.8 | 28.8 |
| Under Ground water Tank | - | - | - | - |
| Water Supply System | 47.85 | 47.85 | 47.85 | 47.85 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Circular Road | 60 | 60 | 60 | 60 |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical Sub Station | 93 | 156 | 93.45 | 93.45 |
| Electricity Supply System | 281.8 | 281.8 | 281.8 | 281.8 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 30.5 | 30.5 |
| Rain Water Harvesting | - | - | - | - |
| Rain water Harvesting | 56 | 56 | - | - |
| Rainwater Harvesting | - | - | - | - |
| Roads & Pavements | 60.6 | 60.6 | 60.6 | 60.6 |
| STP | 80 | 199 | 134 | 134 |
| Security and Firefighting | 199.25 | 199.25 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Street Lighting | 21.6 | 21.6 | 21.6 | 21.6 |
| Under Ground water Tank | 53.25 | 53.25 | 53.25 | 53.25 |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Circular Road | - | - | - | - |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical Sub Station | 93.45 | 93.45 | 124.6 | 124.6 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 30.5 | 30.5 | 0 | 0 |
| Rain Water Harvesting | - | - | - | - |
| Rain water Harvesting | - | - | - | - |
| Rainwater Harvesting | - | - | - | - |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| STP | 53.5 | 80.25 | 80.25 | 80.25 |
| Security and Firefighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Street Lighting | - | - | - | - |
| Under Ground water Tank | - | - | - | - |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Circular Road | - | - | - | - |
| Clubhouse/community centres | 0 | 0 | 0 | - |
| Electrical Sub Station | - | - | - | - |
| Electricity Supply System | 0 | 0 | 0 | - |
| Other | 0 | 0 | 0 | - |
| Parks and Playgrounds | 0 | 0 | 0 | - |
| Rain Water Harvesting | - | - | - | - |
| Rain water Harvesting | - | - | - | - |
| Rainwater Harvesting | - | - | - | - |
| Roads & Pavements | 0 | 0 | 0 | - |
| STP | 80.25 | 80.25 | 80.25 | - |
| Security and Firefighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | - |
| Shopping area | 0 | 0 | 0 | - |
| Storm Water Drainage | 0 | 0 | 0 | - |
| Street Lighting | - | - | - | - |
| Under Ground water Tank | - | - | - | - |
| Water Supply System | 0 | 0 | 0 | - |
Savannah is located in Gurugram.
Yes. Savannah is registered under RERA-GRG-1214-2022 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Savannah is 10 November 2027.
Savannah is developed by FAITH BUILDTECH PRIVATE LIMITED.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.