Plot Has Already been demarcated with boundary wall on all sides.
Plot Has Already been demarcated with boundary wall on all sides.
65% of Internal Roads work has been finished
65% of Internal Roads work has been finished
Authority is going to supply Ganga Water and they are working on the building a water treatment for the same.
STP is already operational for Raj Nagar Extension & sewer Line has already been laid.
80% of internal drain have been finished
50% of Parks have been developed
25 % of Tree Planting have been done
65% of Internal Street Lightning work has been finished.
Club building work has been Started
STP is getting installed at site & treated water is going to be used for horticulture & flushing need.
Fully Automatic Sewage treatment has been installed at site
Modern Rain Water harvesting system type has been installed at site.
Led Lights have been used in most common Areas and energy efficient equipments have been installed, wherever possible
Already Executed as per norms
Already Existed in the Vicinity
As per norms
As per norms
Showing 9 blocks with 231 units
Total Carpet Area
71072.60 m²
765018.36 ft²
Total Units
1190
5 different types
Blocks & Floors
9
17 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
28458.58 m²
306325.31 ft²