| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | - | - | 0 |
| Electric Substation | - | - | - | - |
| Electricity Supply System | - | - | - | 0 |
| Electrification Cost | - | - | - | - |
| Milk and Vegetable Booth | - | - | - | - |
| Other | - | - | - | 0 |
| Parks and Playgrounds | - | - | - | 0 |
| Rain Water Harvesting | - | - | - | - |
| Roads & Pavements | - | - | - | 0 |
| STP | - | - | - | - |
| Sewerage treatment & garbage disposal | - | - | - | 0 |
| Shopping area | - | - | - | 0 |
| Storm Water Drainage | - | - | - | 0 |
| Street Lighting | - | - | - | - |
| UGT | - | - | - | - |
| Water Supply System | - | - | - | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electric Substation | - | - | - | - |
| Electricity Supply System | 0 | 10 | 10 | 0 |
| Electrification Cost | - | - | - | - |
| Milk and Vegetable Booth | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain Water Harvesting | - | - | - | - |
| Roads & Pavements | 0 | 2.5 | 5 | 20 |
| STP | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 9 | 10 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 14 | 10 | 0 |
| Street Lighting | 0 | 0 | 0 | 4 |
| UGT | - | - | - | - |
| Water Supply System | 0 | 12.5 | 10 | 10 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electric Substation | 15 | 15 | 2 | 25 |
| Electricity Supply System | 10 | 10 | 10 | 3 |
| Electrification Cost | - | - | - | 125 |
| Milk and Vegetable Booth | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 3 | 3 | 0 |
| Rain Water Harvesting | - | - | - | 8 |
| Roads & Pavements | 30 | 40 | 40 | 40 |
| STP | 10 | 10 | 2 | 25 |
| Sewerage treatment & garbage disposal | 5 | 5 | 5 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 5 | 5 | 5 | 0 |
| Street Lighting | 0 | 0 | 0 | 3 |
| UGT | 10 | 10 | 2 | 25 |
| Water Supply System | 5 | 5 | 8 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | - | - | - |
| Electric Substation | 21 | - | - | - |
| Electricity Supply System | 11 | - | - | - |
| Electrification Cost | 125 | - | - | - |
| Milk and Vegetable Booth | 3.5 | - | - | - |
| Other | 0 | - | - | - |
| Parks and Playgrounds | 3 | - | - | - |
| Rain Water Harvesting | 7.5 | - | - | - |
| Roads & Pavements | 5.5 | - | - | - |
| STP | 29.5 | - | - | - |
| Sewerage treatment & garbage disposal | 0 | - | - | - |
| Shopping area | 0 | - | - | - |
| Storm Water Drainage | 0 | - | - | - |
| Street Lighting | - | - | - | - |
| UGT | 18 | - | - | - |
| Water Supply System | 0 | - | - | - |
Plaza 106 Ddjay is located in Gurugram.
Yes. Plaza 106 Ddjay is registered under RERA-GRG-953-2021 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Plaza 106 Ddjay is 31 December 2024.
Plaza 106 Ddjay is developed by MAGIC EYE DEVELOPERS PVT LTD.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.