OngoingActive

PALM RESORT

Ghaziabad, Uttar Pradesh
16-11-2013
Launch Date
Ongoing
Type
31-12-2024
Completion Date

Overview

Launch Date

Invalid Date

Completion Date

31-12-2024

RERA ID

UPRERAPRJ7354

Basic Details

Project TypeOngoing
Project CategoryResidential
Total area in round figure (Sq.mt.)28567
Project NamePALM RESORT
Registration Fee (in Rs.)148000
AddressNot specified
Village/Locality/Sector etc.Not specified
StateUttar Pradesh
Project Duration (In month)134
DistrictGhaziabad
Original Start Date16-11-2013
TehsilGhaziabad
Proposed Start Date16-11-2013
Sanctioning Competent AuthorityGhaziabad Development Authority
Project Cost (in Lacs)16700
Proposed Completion Date31-12-2024

Location

Latitude

28 42''15.38 N

Longitude

77 25' ' 29.74E

Bank Details

Account no.00761132000200
Name Of Account HolderMRJV CONSTRUCTION COMPANY
Bank NamePUNJAB NATIONAL BANK
Branch AddressSECTOR-63, NOIDA
Branch NameLCB BRANCH, SECTOR-63, NOIDA
IFSC CodePUNB0093110

Development Works

Demarcation of Plots

Total plot area 37048.12. Sq. m. located at Khasra No. 1037,1042,1043,1044,1045,1046,1047,1051,1067 & 1068 Village Noornagar, Ghaziabad, U.P.

Boundary Wall

2100 mm high, along entire periphery.

Road Work

Interlocking Tremix

Footpaths

Interlocking Pavers

Water Supply Including Drinking Water Facilities

UGT Of domestic tank capacity 275 K.L.

Sewer System

Underground system using UPVC/RCC Sewer pipes.

Drain

Underground system using UPVC/RCC Sewer pipes.

Parks

Parks having total area of 4,943.24 sq. m. shall be provided.

Tree Planting

151 nos. trees are to be planted out of that 50% will be evergreen tree.

Design For Electric Supply Including Street Lighting

Electricity Transformers 02 nos. of 1600 KVA capacity each & 01 no. of 2000 KVA shall be used along with necessary switch-gear for distributing electricity at LT voltage.

Community Buildings

Applicable.

Treatment and Disposal System of Sewage and Sullage water

STP of capacity 300 KLD shall be provided. Treated water shall be used for flushing, irrigation, pathways cleaning and excess sewage shall be discharged in the municipal sewer.

Solid Waste Management And Disposal System

Manual collection and organic waste converter shall be provided.

Water Conservation System

10 No. sets of recharge Pits (2 x 1.75 x 1m effective depth) and desilting tank (5 x 1.75 x 2 m effective depth) shall be provided.

Energy Management System Including Use of Renewable Energy

Solar panels shall be provided on terrace for renewable energy. Single point metering will be there for energy purchased from the grid/ power supply company.

Fire Protection And Fire Safety System

Fire tender path shall be provided as per NBC. Fire fighting systems along with pumps and UGT of Fire tank capacity 200 K.L. (common) and OHT of Fire tanks (at each block terrace) shall be provided as per NBC & NOC from fire depp.

Social Infrastructure And Other Public Amenities Including Public Health Services

STP, organic waste converter shall be provided.

Emergency Evacuation Services

Staircases shall be provided In Basement & all the Towers for fire/ emergency exit as per NBC.

Other Miscellaneous Work

-

Documents

Extract of Khatauni

No: 1415-1420 | Date: -

Extract of Khatauni

No: 1415-1420 | Date: -

Allotment Letter issued by Competent Authority

No: GDA/BP/21-22/1502 | Date: 22-05-2023

Sale Deed

No: APPROVED MAP | Date: 22-05-2023

Commencement Certificate

Other Plan(If Any)

Proforma of Conveyance Deed

Proforma of Completion Certificate(Occupancy)

Details of Encumbrances

Uploaded: 31-08-2022

Other Plan(If Any)

Uploaded: 31-05-2021

Proforma of Application Form

Uploaded: 25-07-2018

Proforma of Allotment Letter

Uploaded: 25-07-2018

Waste Disposal Plan

Uploaded: 25-07-2018

Water Supply Plan

Uploaded: 25-07-2018

Electricity Supply Plan

Uploaded: 25-07-2018

Development Work Plan

Uploaded: 25-07-2018

Affidavit

Uploaded: 25-07-2018

CA CERTIFICATE

Uploaded: 06-07-2018

ARCHITECT CERTIFICATE

Uploaded: 06-07-2018

ENGINEERS CERTIFICATE

Uploaded: 06-07-2018

Other

Uploaded: 21-01-2022

Registry Document In Case of Own Land

Uploaded: 17-10-2017

Sanctioned Layout Plan (Of Entire Project)

Uploaded: 31-01-2018

Sanctioned Layout Plan (Of Entire Project)

Uploaded: 31-01-2018

Authentic copy of Approval of Project

Uploaded: 31-01-2018

Permits

Orignal Permit No711/Zone-I/14-15
Orignal Permit Date10-02-2017
Valid Upto09-02-2022
Revalidated Permit No-
Revalidated Permit Date-
Revalidated Permit Valid Upto-
Permit Extendable Upto09-02-2022
End Date27-03-2022
Uploaded Approve LayoutOpen
Uploaded Sanctioned LetterOpen
Uploaded Approved MapOpen
Uploaded Floor Plan Of All TypesOpen
Uploaded Project SpecificationsOpen
Uploaded Sajra DetailNot Specified
Orignal Permit No711/Zone-I/14-15
Orignal Permit Date10-02-2017
Valid Upto09-02-2022
Revalidated Permit NoGDA/BP/21-22/1502
Revalidated Permit Date22-05-2023
Revalidated Permit Valid Upto01-01-2025
Permit Extendable Upto01-01-2025
End Date27-03-2022
Uploaded Approve LayoutOpen
Uploaded Sanctioned LetterOpen
Uploaded Approved MapOpen
Uploaded Floor Plan Of All TypesOpen
Uploaded Project SpecificationsOpen
Uploaded Sajra DetailNot Specified
Orignal Permit NoGroup housing/04073/GDA/BP/21-22/1502/21112022
Orignal Permit Date01-06-2023
Valid Upto17-06-2025
Revalidated Permit NoGroup housing/04073/GDA/BP/21-22/1502/21112022
Revalidated Permit Date01-06-2023
Revalidated Permit Valid Upto01-01-2025
Permit Extendable Upto01-01-2025
End Date27-03-2022
Uploaded Approve LayoutOpen
Uploaded Sanctioned LetterOpen
Uploaded Approved MapOpen
Uploaded Floor Plan Of All TypesOpen
Uploaded Project SpecificationsOpen
Uploaded Sajra DetailNot Specified
Orignal Permit NoGDA/BP/21-22/1502
Orignal Permit Date01-06-2023
Valid Upto01-06-2023
Revalidated Permit NoGDA/BP/21-22/1502
Revalidated Permit Date19-03-2025
Revalidated Permit Valid Upto19-07-2028
Permit Extendable Upto17-06-2025
End Date23-05-2024
Uploaded Approve LayoutOpen
Uploaded Sanctioned LetterOpen
Uploaded Approved MapOpen
Uploaded Floor Plan Of All TypesOpen
Uploaded Project SpecificationsOpen
Uploaded Sajra DetailNot Specified

Project Team

Contractor Name (if any)N/A
Contractor AddressN/A
Architect NameVishal Mittal
Architect AddressB 34 Sector 67 Noida U.P.
Architect Licence NumberCA/98/23185
Structural Engineer NameV D SHARMA
Structural Engineer AddressB 24 sector 67 Noida U.P.
Mobile number(Project Co-ordinator)9999498937

Land Details

AFS

Showing 20 blocks with 239 units

Property Summary

Total Carpet Area

54143.97 m²

582800.28 ft²

Total Units

935

4 different types

Blocks & Floors

20

19 floors across all blocks

Parking

0

0 garages, 0 open

Average unit size:57.91 m²
Balconies:635
Parking ratio:0.00 per unit

Block Block-1 Tower D2

15 units

Block Block-1 Tower G1 (Type 1)

15 units

Block Block-1 Tower G1 (Type 2)

15 units

Block Block-1 Tower G1 (Type 3)

14 units

Block Block-1 Tower A2 (Type 1)

15 units

Block Block-1 Tower A2 (Type 2)

15 units

Block Block-2 Tower C

15 units

Block Block-2 Tower F (Type 1)

14 units

Block Block-2 Tower F (Type 2)

14 units

Block Block-2 Tower F (Type 3)

14 units

Block Block-2 Tower E1 (Type 1)

10 units

Block Block-2 Tower E1 (Type 2)

11 units

Block Block-2 Tower E1 (Type 3)

11 units

Block Block-2 Tower E1 (Type 4)

11 units

Block Block-2 Tower E1 (Type 5)

11 units

Block E.W.S.

18 units

Block L.I.G.

18 units

Block Shop (Type 1)

1 units

Block Shop (Type 2)

1 units

Block Shop (Type 3)

1 units

Khasra Details

Total Area

37048.12 m²

398782.26 ft²

1 plot
Khasra
TypeKhasra
Khasra/Plot No1042, 1045, 1046, 1047, 1067, 1068
Area(In Sq. Mt.)37048.12

Other Details

Contractor Name (if any)N/A
Contractor AddressN/A
Architect NameVishal Mittal
Architect AddressB 34 Sector 67 Noida U.P.
Architect Licence NumberCA/98/23185
Structural Engineer NameV D SHARMA
Structural Engineer AddressB 24 sector 67 Noida U.P.
Mobile number(Project Co-ordinator)9999498937