Have queries on this Project?
Uploaded on: 02-03-2020
Uploaded on: 10-07-2020
Uploaded on: 10-07-2020
Uploaded on: 06-02-2020



| Particulars | Expenditure (in Lakhs) |
|---|---|
| STP | 74.64 |
| Other | 0 |
| Parking | 218.01 |
| Schools | 0 |
| UG Tank | 30.7 |
| Street light | 2.75 |
| Shopping area | 273 |
| Renewable energy | 5.54 |
| Roads & Pavements | 243.17 |
| Water Supply System | 312.09 |
| Storm Water Drainage | 84.25 |
| Parks and Playgrounds | 16.56 |
| Rain Water Harvesting | 17.6 |
| Electrical Sub station | 205.07 |
| Electricity Supply System | 86.06 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 46.25 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | - | - |
| Electricity Supply System | 0 | 0 | - | - |
| Other | 0 | 0 | - | - |
| Parks and Playgrounds | 0 | 0 | - | - |
| Roads & Pavements | 0 | 0 | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | - | - |
| Shopping area | 0 | 0 | - | - |
| Storm Water Drainage | 0 | 0 | - | - |
| Water Supply System | 0 | 0 | - | - |
Palm Hills-Phase Ii is located in Gurugram.
Yes. Palm Hills-Phase Ii is registered under RERA-GRG-612-2020 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Palm Hills-Phase Ii is 2 October 2022.
Palm Hills-Phase Ii is developed by EMAAR MGF LAND LIMITED.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.