Launch Date
Completion Date
RERA ID
Uploaded on: 04-02-2019
Uploaded on: 04-02-2019
Uploaded on: 04-02-2019
Uploaded on: 27-02-2019
Uploaded on: 20-02-2019




| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 818.9 |
| Shopping area | 0 |
| security system | 286.42 |
| Roads & Pavements | 119.44 |
| Water Supply System | 89.2 |
| Storm Water Drainage | 89.2 |
| Parks and Playgrounds | 12 |
| Electricity Supply System | 167.94 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 59.47 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | - | 0 | - |
| Electricity Supply System | - | - | 0 | - |
| Other | - | - | 0 | - |
| Parks and Playgrounds | - | - | 0 | - |
| Roads & Pavements | - | - | 0 | - |
| Sewerage treatment & garbage disposal | - | - | 0 | - |
| Shopping area | - | - | 0 | - |
| Storm Water Drainage | - | - | 0 | - |
| Water Supply System | - | - | 0 | - |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Other | 312 | 50 | 122 | 248 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 21 | 0 | 0 | 0 |
| Other | 6.3 | 404 | 336 | 382 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 1.5 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 1.65 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0.9 | 0 | 0 | 0 |
| Water Supply System | 4 | 0 | 0 | 0 |