Launch Date
Completion Date
RERA ID
Uploaded on: 03-11-2021
Uploaded on: 03-11-2021
Uploaded on: 24-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021
Uploaded on: 26-11-2021




| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall | - | - | 2.35 | 2.35 |
| Clubhouse/community centres | 0 | - | 0 | 0 |
| Electrical Sub Station | - | - | - | - |
| Electricity Supply System | 0 | - | 0 | 0 |
| Other | 0 | - | 1.5 | 1.5 |
| Parking Marking | - | - | - | 6.69 |
| Parks and Playgrounds | 0 | - | 0 | 0 |
| Rain Water Harvesting | - | - | - | - |
| Renewable Energy | - | - | - | 0.69 |
| Roads & Pavements | 0 | - | 0 | 5.27 |
| STP | - | - | - | - |
| Security and Firefighting Services | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | - | 1.24 | 1.24 |
| Shopping area | 0 | - | 0 | 0 |
| Storm Water Drainage | 0 | - | 1.2 | 1.2 |
| Street Light | - | - | - | - |
| Underground Tank | - | - | - | - |
| Water Supply System | 0 | - | 2.24 | 2.24 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall | 4.69 | 4.69 | 4.69 | 4.69 |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical Sub Station | 10.82 | 10.82 | 10.82 | 0 |
| Electricity Supply System | 2.24 | 2.24 | 2.24 | 0 |
| Other | 3 | 3 | 3 | 3 |
| Parking Marking | 6.69 | 13.38 | 13.38 | 13.38 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain Water Harvesting | - | - | - | - |
| Renewable Energy | 0.69 | 1.38 | 1.38 | 1.38 |
| Roads & Pavements | 5.27 | 10.55 | 10.55 | 10.55 |
| STP | 0 | 0 | 0 | 1.88 |
| Security and Firefighting Services | 15.26 | 15.26 | 15.26 | 0 |
| Sewerage treatment & garbage disposal | 2.48 | 2.48 | 2.48 | 2.48 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 2.4 | 2.4 | 2.4 | 2.4 |
| Street Light | 0 | 0 | 0 | 0 |
| Underground Tank | 0 | 0 | 0 | 2.5 |
| Water Supply System | 4.47 | 4.47 | 4.47 | 4.47 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall | 9.38 | 7.04 | 4.69 | 2.35 |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical Sub Station | 21.64 | 21.64 | 21.64 | 10.82 |
| Electricity Supply System | 4.49 | 4.49 | 4.49 | 2.24 |
| Other | 6 | 4.5 | 3 | 1.5 |
| Parking Marking | 13.38 | 26.75 | 26.75 | 13.38 |
| Parks and Playgrounds | 5.79 | 5.79 | 5.79 | 5.79 |
| Rain Water Harvesting | 1.13 | 1.13 | 1.13 | 1.13 |
| Renewable Energy | 1.38 | 2.76 | 2.76 | 1.38 |
| Roads & Pavements | 10.55 | 21.1 | 21.1 | 10.55 |
| STP | 1.88 | 5.64 | 5.64 | 3.76 |
| Security and Firefighting Services | 30.51 | 30.51 | 42.61 | 27.36 |
| Sewerage treatment & garbage disposal | 4.95 | 3.71 | 2.48 | 1.24 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 4.8 | 3.6 | 2.4 | 1.2 |
| Street Light | 0 | 4.57 | 4.57 | 4.71 |
| Underground Tank | 2.5 | 7.5 | 7.5 | 5 |
| Water Supply System | 8.94 | 6.71 | 4.47 | 2.24 |