Launch Date
Completion Date
Configurations
Sizes
Project Size
Total Floors
Launch Price
RERA ID
Uploaded on: 30-11-2024
Uploaded on: 30-11-2024
Uploaded on: 30-11-2024
Uploaded on: 30-11-2024
Uploaded on: 30-11-2024
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 09-01-2025
Uploaded on: 10-02-2025
Uploaded on: 10-02-2025
Uploaded on: 10-02-2025
Uploaded on: 10-02-2025
Uploaded on: 10-02-2025







| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | 0 | 0 | 0 |
| Electrical sub station | - | 28.52 | 57.05 | 17.11 |
| Electricity Supply System | - | 0 | 0 | 0 |
| Electrification Cost | - | 16.33 | 32.67 | 9.8 |
| Other | - | 0 | 0 | 0 |
| Parking | - | 0 | - | - |
| Parks and Playgrounds | - | 0 | 0 | 0 |
| Rain water harvesting | - | 4.68 | 9.35 | 2.81 |
| Roads & Pavements | - | 0 | 0 | 0 |
| STP MEP PART | - | 14.69 | 29.38 | 8.82 |
| Security and fire fighting | - | 0 | - | - |
| Sewerage treatment & garbage disposal | - | 0 | 0 | 0 |
| Shopping area | - | 0 | 0 | 0 |
| Storm Water Drainage | - | 0 | 0 | 0 |
| Street Lighting | - | 0 | - | - |
| Underground water tank | - | 7.69 | 15.38 | 4.61 |
| Water Supply System | - | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical sub station | 28.52 | 28.52 | 28.52 | 28.52 |
| Electricity Supply System | 0 | 0 | 0 | 35.21 |
| Electrification Cost | 16.33 | 16.33 | 16.33 | 16.33 |
| Other | 0 | 0 | 0 | 0 |
| Parking | - | - | - | 110.18 |
| Parks and Playgrounds | 0 | 0 | 0 | 35.73 |
| Rain water harvesting | 6.55 | 9.35 | 4.68 | 4.68 |
| Roads & Pavements | 30.56 | 61.12 | 18.34 | 42.79 |
| STP MEP PART | 20.57 | 29.38 | 14.69 | 14.69 |
| Security and fire fighting | - | - | - | 27.52 |
| Sewerage treatment & garbage disposal | 0 | 17.66 | 3.53 | 8.24 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 10.96 | 2.19 | 5.11 |
| Street Lighting | - | - | - | 32.85 |
| Underground water tank | 10.76 | 15.38 | 7.69 | 7.69 |
| Water Supply System | 0 | 95.67 | 19.13 | 44.65 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical sub station | 28.52 | 28.52 | 28.52 | 28.52 |
| Electricity Supply System | 14.08 | 7.04 | 7.04 | 7.04 |
| Electrification Cost | 16.33 | 16.33 | 16.33 | 16.33 |
| Other | 0 | 0 | 0 | 0 |
| Parking | 44.07 | 22.04 | 22.04 | 22.04 |
| Parks and Playgrounds | 14.29 | 7.15 | 7.15 | 7.15 |
| Rain water harvesting | 4.68 | 4.68 | 4.68 | 4.68 |
| Roads & Pavements | 61.12 | 30.56 | 30.56 | 30.56 |
| STP MEP PART | 14.69 | 14.69 | 14.69 | 14.69 |
| Security and fire fighting | 11.01 | 5.5 | 5.5 | 5.5 |
| Sewerage treatment & garbage disposal | 11.78 | 5.89 | 5.89 | 5.89 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 7.3 | 3.65 | 3.65 | 3.65 |
| Street Lighting | 13.14 | 6.57 | 6.57 | 6.57 |
| Underground water tank | 7.69 | 7.69 | 7.69 | 7.69 |
| Water Supply System | 63.78 | 31.89 | 31.89 | 31.89 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical sub station | 28.52 | 28.52 | 28.52 | 28.52 |
| Electricity Supply System | 7.04 | 7.04 | 7.04 | 18.31 |
| Electrification Cost | 16.33 | 16.33 | 16.33 | 16.33 |
| Other | 0 | 0 | 0 | 0 |
| Parking | 22.04 | 22.04 | 22.04 | 57.29 |
| Parks and Playgrounds | 7.15 | 7.15 | 7.15 | 18.58 |
| Rain water harvesting | 12.16 | 9.35 | 3.74 | 2.81 |
| Roads & Pavements | 30.56 | 30.56 | 30.56 | 79.46 |
| STP MEP PART | 38.2 | 29.38 | 11.75 | 8.82 |
| Security and fire fighting | 5.5 | 5.5 | 5.5 | 14.31 |
| Sewerage treatment & garbage disposal | 5.89 | 5.89 | 5.89 | 15.31 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3.65 | 3.65 | 3.65 | 9.5 |
| Street Lighting | 6.57 | 6.57 | 6.57 | 17.08 |
| Underground water tank | 19.99 | 15.38 | 6.15 | 4.61 |
| Water Supply System | 31.89 | 31.89 | 31.89 | 82.92 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical sub station | 28.52 | 28.52 | 28.52 | 39.93 |
| Electricity Supply System | 14.08 | 5.63 | 4.22 | 7.04 |
| Electrification Cost | 16.33 | 16.33 | 16.33 | 22.87 |
| Other | 0 | 0 | 0 | 0 |
| Parking | 44.07 | 17.63 | 13.22 | 22.04 |
| Parks and Playgrounds | 14.29 | 5.72 | 4.29 | 7.15 |
| Rain water harvesting | 4.68 | 0 | 0 | 0 |
| Roads & Pavements | 61.12 | 24.45 | 18.34 | 30.56 |
| STP MEP PART | 14.69 | 0 | 0 | 0 |
| Security and fire fighting | 11.01 | 4.4 | 3.3 | 5.5 |
| Sewerage treatment & garbage disposal | 11.78 | 4.71 | 3.53 | 5.89 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 7.3 | 2.92 | 2.19 | 3.65 |
| Street Lighting | 13.14 | 5.26 | 3.94 | 6.57 |
| Underground water tank | 7.69 | 0 | 0 | 0 |
| Water Supply System | 63.78 | 25.51 | 19.13 | 31.89 |