RERA Received Date
Completion Date
RERA ID
29.00083333
29.00055556
Not Applicable
The boundary around the project will be developed by the Promoter comprising of RCC Column, beam, brick masonry and MS Railings.
The Approach road and internal roads are being developed by the Promoter comprising of subgrade, GSB, WMM, DLC and CC Pavers
The Footpaths are being developed by the Promoter over the compacted brick surface the pavers are placed with sand cushion.
The feeder line with HDPE/MDPE piper with necessary fittings will be provided by the Promoter. Underground water tanks of the estimated capacity with pumps will be provided in the basement pump room and distribution will be from overhand tanks proposed at the terrace of the tower.
Vertical stacks will be provided in the building through the shafts to which all toilets and kitchen disposals will be connected. This will be finally connected to the trunk sewer lines (constructed with RCC pipes and Manholes at desired intervals by the Promoter) and in turn finally to the project.
Vertical stacks will be provided in the building through the shafts to which all toilets and kitchen disposals will be connected. This will be finally connected to the trunk sewer lines (constructed with RCC pipes and Manholes at desired intervals by the Promoter) and in turn finally to the project.
All the parks as proposed in the layout will be developed by the Promoter
All the tree planting as proposed in the layout will be done by the Promoter
Based on the Electricity Code, 2005 of Govt of Uttar Pradesh, electrical loads of the building have been worked out and correspondingly substation for the four towers has been provided in the basement.
Not Applicable
Vertical stacks through the shafts to which all toilets and kitchen disposals will be connected will be provided in the building and finally connected to the trunk sewer lines of the project and in turn finally to the township trunk sewers and to the main treatment plant.
Garbages chutes planned with garbage collection rooms in the basement. From there the garbage will be collected by the maintainance agency for final treatment and disposal.
Rainwater harvesting pits proposed in the colony by the Promoter.
Solar Water heaters provided in the complex for supplying hot water to the apartment kitchen and toilets.
Provided as per the provisions of National Building Code 2016
Not Applicable
Provided as per provisions of the National Building Code 2016
Not Applicable
Showing 1 blocks with 32 units
Total Carpet Area
6876.22 m²
74014.94 ft²
Total Units
64
2 different types
Blocks & Floors
1
8 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
3744.00 m²
40300.04 ft²