To be built of brickwork, plaster and paint (10 FT HEIGHT)
CC – Tremix / Interlock 5” WIDTH
PAVER BLOCK/TREMIX WITH CURVSTONE
From Borewell to Overhead tanks to units 8 TANKS OF 25,000 LTR CAPACITY OF EACH
Septic tank with overflow connected to drains TO COVERED BY CONNECTION WITH STP
SEWER DRAIN DWC / RCC pipes of 500MM DIA STORM WATER DRAIN OF RCC WITH COVER BLOCKS
Green grass park with ample sitting and children playing arrangements ALONGWITH LANDSCAPING & HORTICULTURE WORK.
Complete tree planting around the boundary wall and foothpath and parks
Ample provision of street lights WITH 100WATT/200-WATT LED PANELS & HI-MASK LIGHTS WHEREVER REQUIRED
Community centre for the complex is proposed
Sewage Treatment Plant will be installed 400 KLD
Sewage Treatment Plant will be installed 400 KLD
Multiple rain water harvesting to be installed
Power saving lights of 100 KVA with rooftop solar system for common area lights / lifts
Appropriate installations of fire safety – including hydrant, pipelines, sprinklers will be done. MS ERW PIPES (TYPE C) OF DIA 200 MM, 150 MM, 100 MM, 80 MM, CO2 TYPE FIRE EXTINGUISHER, ABC TYPE FIRE EXTINGUISHER LOW PRESSURE HIGH PRESSURE MOTORS & JOCKEY PUMPS
Badmintion court, gym, swimming pool, libraries are proposed
Ample with of roads and setbacks
NA
Showing 4 blocks with 512 units
Total Carpet Area
62114.08 m²
668589.75 ft²
Total Units
512
2 different types
Blocks & Floors
4
16 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
26613.00 m²
286459.67 ft²