Launch Date
Completion Date
RERA ID
25.388455
81.892688
Demarcation of plots will be done as per layout plans
9 /4 inch thick Boundary wall will be constructed as per drawing, using brick work /MS Railing with height 6 feet
6/9 mtr wide driveway /Road work will be constructed by promoter as per layout plan with inter lock tile/Black top
footpaths will be constructed on road sides / Green area using inter locking tiles or CC
Water supply including drinking water facilities will be developed as per plan. Water supply will be provided through UGT/OHT on terrace
sewerage systems including STP will be constructed at site as per norms /requirement and recycle water will be used in park/green area etc .
Underground drain will be provided and connected to existing drainage system
2442.52 sq mtr green area will be developed as per sanctioned drawing
Trees will be planted in green areas as per approved layout plan
Street Lighting will be provided and electric supply line will be laid by the promoter.
common community building will be provided as per layout
STP will be constructed at site and disposal as per requirement
Solid Waste Management and Disposal system will be provided as per Requirement
Rain water harvesting will be developed as per approved layout plan
Energy Management System including use of Renewable energy will be provided as per govt. norms and designed by promoter
Fire NOC Received and fire protection and fire safety system will be provided as per NOC
All social infrastructure and other public amenities including public health services will be provided as per approved layout plan
Will be provided as per approved plan if required
if required will be provided as requirements
Showing 3 blocks with 12 units
Total Carpet Area
9335.92 m²
100490.91 ft²
Total Units
88
1 different types
Blocks & Floors
3
4 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
22040.00 m²
237236.36 ft²