RERA Received Date
Completion Date
RERA ID
Uploaded on: 22-11-2018
Uploaded on: 22-11-2018
Uploaded on: 22-11-2018



| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| SCHOOL | 0 |
| Shopping area | 0 |
| STREET LIGHTING | 0 |
| Roads & Pavements | 0 |
| HOSPITAL DISPENSARY | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| RENEWABLE ENERGY SYSTEM | 0 |
| Electricity Supply System | 0 |
| SECURITY AND FIREFIGHTING | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 25 | 25 | 25 | 25 |
| Hospital Dispensary | 0 | 0 | 0 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 10 | 20 | 30 | 30 |
| Renewable Energy System | 0 | 0 | 0 | 0 |
| Roads & Pavements | 50 | 80 | 80 | 52 |
| School | 0 | 0 | 0 | 0 |
| Security and Fire Fighting | 5 | 5 | 5 | 5 |
| Sewerage treatment & garbage disposal | 5 | 5 | 5 | 5 |
| Shopping area | 0 | 0 | 25 | 25 |
| Storm Water Drainage | 25 | 25 | 25 | 25 |
| Street Lighting | 5 | 5 | 5 | 5 |
| Water Supply System | 25 | 25 | 25 | 25 |