Have queries on this Project?
28.659212
77.405313
Showing 1 blocks with 135 units
Total Carpet Area
5993.48 m²
64513.22 ft²
Total Units
137
2 different types
Blocks & Floors
1
7 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
4000.88 m²
43065.07 ft²
We have total plot size of 4000.88 Sq Mtrs. having main entrance from the 50m wide road.
2m High and 230mm thick brick work and RCC work in column and beam. At the Center face of boundary wall there would be a logo of the project which give a beautiful iconic design to boundary wall.
From the main entrance gate we have 80mm thick interlocking brick/RCC road through the project whose wideness starts from 6 Meters.
We would not provide any Footpath.
We will provide Treated water through underground water tank of capacity 21 KLD. We will have 3 Fire water tank out of which 2 underground tanks are of capacity 50 KLD each and 1 overhead tank of 10 KLD. We will have 1 underground raw water tank of 21 KLD and 2 overhead domestic water tank of 15 KLD each.
A Modular Sewerage system shall be provided. All sewerage water shall go to the STP which is of capacity of 55 KLD which will be connected with the Municipal sewerage system when come into force.
Storm water management shall be provided. Storm water generated from roads and other landscapes area shall be connect to the storm water drain channel and will go to the rain water harvesting pit for recharge the ground water and overflow shall be connected with the municipal drain line.
Landscape is proceeded as per norms, but no parks are provided.
A variety of trees will be planted along the boundary wall and throughout the green areas to enhance the landscape and improve the environment. A total of 50 trees shall be provided as part of the plantation plan.
Power Backup Capacity of 1600 kVA with 2 sets of Gensets. PSS Capacity will be of 2000 kVA. Line Capacity of 11kV. The electrical system shall be designed and implemented in accordance with the requirements and standards of the local electricity board. the design will incorporate a centralized transformer, HT panel, LT panel, feeder pillars, and DG backup to ensure reliable power supply for common services including the UGT, pump room, STP, external lighting and HVAC systems. The Street lighting will be provided.
No community buildings are provided
A sewerage system shall be provided for the project. all sewage generated shall be collected and conveyed to the sewage treatment plant (STP) for treatment. Excess treated water or overflow from the the STP shall be connected to the Municipal Sewerage System as and when the Municipal network becomes operational.
A designated garbage collection areas is provided for solid waste management. We have provided the STP of capacity of 55 KLD.
We will suggest to individual to use the low flow fixtures as well as dual flush cistern and rain water harvesting system to reduce the water consumption and improve the ground water level.
We will use LED lights fitting in external areas as well as the solar lights. In pump room also all the equipment shall have energy efficient motors.
The complete fire fighting system shall be provided throughout the entire area in accordance with the applicable fire safety codes and statutory fire norms.
Toilets and other facilities are provided in the project on every floor.
All staircases and egress facilities are provided as per codal requirements
NA
Epic is located in Ghaziabad.
Yes. Epic is registered under UPRERAPRJ883685/08/2026 with the Uttar Pradesh RERA (UP-RERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Epic is 31 May 2031.
Epic is developed by JINDALSONS INFRATEX PVT. LTD.OVEARTH PRIVATE LIMITED.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.