Launch Date
Completion Date
RERA ID
28.4999199
77.4272096
We have 3 side road plot of total size 100256 sq. mtr. (proposed project covered 33310 sq. mtr.) having 3 entrance gate towards east side (45 m. wide road), 2 entrance gate towards south side (45 m . Wide road) and 1 entrance gate towards west side (30 m. Wide road)
"Data Centre 2 - The total boundary wall height is 2400mm and barbed wire above. (Data Centre 3) - The total boundary wall height is 2400mm and barbed wire above."
Data Centre 2 & 3) - Minimum 6M wide driveways are planned in tremix.
" Data Centre 2 & 3) - Barrier free pedestrian movement is planned to connect different areas while avoiding vehicular clashes."
(Data Centre 2 &3 )Treated water supply is provided through WTP Plant Room.
"Combined STP Provided for Data Centre 1,IT Block of Phase 1 & Data Centre 2 also. MBBR STP provided in Campus."
Storm water drainage provided. Storm water from Terrace, Roads and other landscape area shall be connected to Storm water drain channel with its further connectivity to Rain water harvesting Pit for recharge the Ground water. Overflow from RWH Pit shall be connected to Municipal drain line.
" Data Centre 2 & 3) - Green area is planned along plot line and along the building. Multipurpose lawn is also planned."
" Data Centre 2 &3) - Trees are planned along boundary wall as buffer planting. Trees are also planned along building."
"Common Area and Base Build lighting shall be Planned . As far as concern of High Side electrical System shall be deigned by STT(Client) We will design & implement Electrical System as per NBC Code/ Local Electricity Board and will consider centralized Transformer, HT panel, LT Panel, Feeder Pillar and DG back for common service like External lighting, Fountain, STP, Pump room etc."
Not proposed
MBBR STP provided in Campus. All Sewerage water shall be go to the STP and overflow from the STP shall be connect with the Municipal sewerage system, when would come into force.
" Block B - Combined STP Provided for Data Centre1 ,IT Block of Phase 1 and Data Centre 2 also"
Project shall be planned with low flow fixtures as well dual flush cistern. Further rainwater harvesting system is also proposed to improve the ground water level.
" Data Centre 2 & 3 - We have provided LED Lighting for common area and external infra. Solar power generation we are using."
Fire Fighting and Fire Protection system is planned in campus as per NBC Code.
Not proposed.
Fire staircase shall be provided. And Refuse area shall also be provided as part of emergency evacuation services.
Not proposed
No: Merger of Land by way of amalgamation - DLF Commercial to DLF Home Developers | Date: -
No: Subsidiary Relationship between DLF home Developers and DLF Commercial | Date: -
No: Subsidiary Relationship between DLF home Developers and Urvasi Infratech | Date: -
No: Board Resolution authorizing Rajeev Singh as Authorized Signatory for RERA | Date: -
No: Scheme of Arrangement sanctioned by Honble High Court as per order dated 11.01.2011 | Date: -
Showing 2 blocks with 26 units
Total Carpet Area
114236.11 m²
1229626.06 ft²
Total Units
26
1 different types
Blocks & Floors
2
13 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
24.00 m²
258.33 ft²