Launch Date
Completion Date
RERA ID
28.797
77.271
As per Approved Lay out Plan
No Provision of Boundary wall
Trunk Roads of Mandola Vihar yojna are already constructed. Internal Roads of 9.0 m and 12.0 m are proposed, which will be constructed by UPAVP as per Parishad Specification
As per specification of UPAVP
Internal Water supply Line of PVC pipe of 110 mm dia will be laid as per design approved by the competent authority of UPAVP. Water supply will be given by Over head tank which will be constructed by parishad
Internal Sewer line of 250mm dia RCC NP2 and NP3 pipe will be laid as per design approved by the competant authority of UPAVP
Internal Storm water drain of CK and C type will be provided as per design approved by the competant authority of UPAVP
Open / Green will be provided as per approved layout.
Tree Planting will be done by UPAVP as per norms approved by horticulture section of Parishad
Electrification work and street light work will be done by UPAVP as per design and drawing approved by the competant authority of UPAVP. Electricity supply line will be handed over to UP Power corporation after completing and testing of line.
No Provision of Community Building
Will be done by UPAVP as per Specification
To be Provided as per UPAVP norms / specification
Presently not planned
Presently not planned
as per norms/ specification
Planned as per provision in the vicinity of the project
as per layout
No
Total Area
47304.00 m²
509175.53 ft²