| Particulars | Expenditure (in Lakhs) |
|---|---|
| STP | 46 |
| Other | 401.14 |
| Open Parking | 11.14 |
| Shopping area | 0 |
| Covered Parking | 537.18 |
| Street lighting | 6.94 |
| Renewable Energy | 0 |
| Roads & Pavements | 118.86 |
| Water Supply System | 163.38 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Under Ground Water Tank | 52.5 |
| Electricity Supply System | 72 |
| Security and FIre Fighting | 473.57 |
| Clubhouse/community centres | 0 |
| Electrical Sub station works | 564.21 |
| Sewerage treatment & garbage disposal | 30.63 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical substation | 90.5 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Renewable Energy | 19.5 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Storm water drainage | 0 | 5 | 0 | 0 |
| Water Supply System | 0 | 0 | 0 | 0 |