| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | - | 0 | 0 |
| Electrical sub station | - | - | 339.06 | 339.06 |
| Electricity Supply System | - | - | 119.62 | 199.37 |
| Electrification till Site | - | - | - | - |
| Other | - | - | 0 | 0 |
| Others | - | - | - | - |
| Parking | - | - | - | - |
| Parks and Playgrounds | - | - | 1.2 | 2 |
| Rain water harvesting | - | - | 12.19 | 20.32 |
| Roads & Pavements | - | - | 154.27 | 257.12 |
| STP | - | - | - | 30 |
| Sewerage treatment & garbage disposal | - | - | 67.2 | 112 |
| Shopping area | - | - | 0 | 0 |
| Storm Water Drainage | - | - | 8.29 | 13.82 |
| Street Light | - | - | - | 17.3 |
| Underground tank | - | - | - | 7.4 |
| Water Supply System | - | - | 33.04 | 55.07 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical sub station | 339.06 | - | - | 678.12 |
| Electricity Supply System | 199.37 | 259.19 | 398.75 | 299.06 |
| Electrification till Site | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| Others | - | - | - | - |
| Parking | - | - | - | - |
| Parks and Playgrounds | 2 | 2.6 | 4 | 3 |
| Rain water harvesting | 20.32 | 26.42 | 40.65 | 30.48 |
| Roads & Pavements | 257.12 | 514.25 | 514.25 | 257.12 |
| STP | 30 | - | - | - |
| Sewerage treatment & garbage disposal | 112 | 145.6 | 223.99 | 168 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 13.82 | 17.97 | 27.64 | 20.73 |
| Street Light | 17.3 | 17.3 | 17.3 | 25.95 |
| Underground tank | 7.4 | - | - | - |
| Water Supply System | 55.07 | 71.59 | 110.14 | 82.6 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | - | - | - |
| Electrical sub station | 678.12 | - | - | - |
| Electricity Supply System | 219.31 | - | - | - |
| Electrification till Site | 187.52 | - | - | - |
| Other | 0 | - | - | - |
| Others | 145.15 | - | - | - |
| Parking | 8.41 | - | - | - |
| Parks and Playgrounds | 2.2 | - | - | - |
| Rain water harvesting | 22.36 | - | - | - |
| Roads & Pavements | 257.12 | - | - | - |
| STP | - | - | - | - |
| Sewerage treatment & garbage disposal | 123.2 | - | - | - |
| Shopping area | 0 | - | - | - |
| Storm Water Drainage | 15.2 | - | - | - |
| Street Light | 25.95 | - | - | - |
| Underground tank | - | - | - | - |
| Water Supply System | 60.58 | - | - | - |