| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Boundry Wall | 45 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| ELECTRICAL SUB STATION | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| CONSTRUCTION OF CIRCULAR ROAD | 0 |
| Sewerage treatment & garbage disposal | 0 |
| MTC CHARGES INCLUDING RESURFACING OF ROADS | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Construction Of Circular Road | - | 0.3 | 0.5 | 0.5 |
| Electrical Sub Station | - | 0.9 | 1.3 | 1.3 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| MTC Charges Including Resurfacing Of Roads | - | 3.4 | 5 | 5 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 1.3 | 2 | 2 |
| Roads & Pavements | 0 | 3.1 | 4.6 | 4.6 |
| Sewerage treatment & garbage disposal | 0 | 2.1 | 3.1 | 3.1 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 2.4 | 3.6 | 3.6 |
| Street Lighting | - | 0.5 | 0.8 | 0.8 |
| Water Supply System | 0 | 2.2 | 3.2 | 3.2 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Construction Of Circular Road | 0.5 | 0.5 | 0.5 | 0.5 |
| Electrical Sub Station | 1.3 | 1.3 | 1.3 | 1.3 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| MTC Charges Including Resurfacing Of Roads | 5 | 5 | 5 | 5 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 2 | 2 | 2 | 2 |
| Roads & Pavements | 4.6 | 4.6 | 4.6 | 4.6 |
| Sewerage treatment & garbage disposal | 3.1 | 3.1 | 3.1 | 3.1 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3.6 | 3.6 | 3.6 | 3.6 |
| Street Lighting | 0.8 | 0.8 | 0.8 | 0.8 |
| Water Supply System | 3.2 | 3.2 | 3.2 | 3.2 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Construction Of Circular Road | 0.5 | 0.5 | 0.5 | 0.5 |
| Electrical Sub Station | 1.3 | 1.3 | 1.3 | 1.3 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| MTC Charges Including Resurfacing Of Roads | 5 | 5 | 5 | 5 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 2 | 2 | 2 | 2 |
| Roads & Pavements | 4.6 | 4.6 | 4.6 | 4.6 |
| Sewerage treatment & garbage disposal | 3.1 | 3.1 | 3.1 | 3.1 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3.6 | 3.6 | 3.6 | 3.6 |
| Street Lighting | 0.8 | 0.8 | 0.8 | 0.8 |
| Water Supply System | 3.2 | 3.2 | 3.2 | 3.2 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Construction Of Circular Road | 0.5 | 0.5 | 0.5 | 0.5 |
| Electrical Sub Station | 1.3 | 1.3 | 1.3 | 1.3 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| MTC Charges Including Resurfacing Of Roads | 5 | 5 | 5 | 5 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 2 | 2 | 2 | 2 |
| Roads & Pavements | 4.6 | 4.6 | 4.6 | 4.6 |
| Sewerage treatment & garbage disposal | 3.1 | 3.1 | 3.1 | 3.1 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3.6 | 3.6 | 3.6 | 3.6 |
| Street Lighting | 0.8 | 0.8 | 0.8 | 0.8 |
| Water Supply System | 3.2 | 3.2 | 3.2 | 3.2 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Construction Of Circular Road | 0.5 | 0.5 | 0.5 | 0.5 |
| Electrical Sub Station | 1.3 | 1.3 | 1.3 | 1.3 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| MTC Charges Including Resurfacing Of Roads | 5 | 5 | 5 | 5 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 2 | 2 | 2 | 2 |
| Roads & Pavements | 4.6 | 4.6 | 4.6 | 4.6 |
| Sewerage treatment & garbage disposal | 3.1 | 3.1 | 3.1 | 3.1 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3.6 | 3.6 | 3.6 | 3.6 |
| Street Lighting | 0.8 | 0.8 | 0.8 | 0.8 |
| Water Supply System | 3.2 | 3.2 | 3.2 | 3.2 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | - | - | - |
| Construction Of Circular Road | 0.5 | - | - | - |
| Electrical Sub Station | 1.3 | - | - | - |
| Electricity Supply System | 0 | - | - | - |
| MTC Charges Including Resurfacing Of Roads | 5 | - | - | - |
| Other | 0 | - | - | - |
| Parks and Playgrounds | 2 | - | - | - |
| Roads & Pavements | 4.6 | - | - | - |
| Sewerage treatment & garbage disposal | 3.1 | - | - | - |
| Shopping area | 0 | - | - | - |
| Storm Water Drainage | 3.6 | - | - | - |
| Street Lighting | 0.8 | - | - | - |
| Water Supply System | 3.2 | - | - | - |