| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Boundary Wall | 25 |
| Shopping area | 0 |
| Roads & Pavements | 45 |
| Water Supply System | 90 |
| Storm Water Drainage | 30 |
| Parks and Playgrounds | 5 |
| Internal Sewerage Scheme | 81 |
| Electricity Supply System | 70 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 16 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall | - | - | - | - |
| Clubhouse/community centres | 0 | - | - | 0 |
| Electricity Supply System | 0 | - | - | 0 |
| Internal Sewerage Scheme | - | - | - | 0 |
| Other | 0 | - | - | 0 |
| Parks and Playgrounds | 0 | - | - | 0 |
| Roads & Pavements | 0 | - | - | 0 |
| Sewerage treatment & garbage disposal | 0 | - | - | 0 |
| Shopping area | 0 | - | - | 0 |
| Storm Water Drainage | 0 | - | - | 0 |
| Water Supply System | 0 | - | - | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall | - | 0 | 0 | 0 |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Internal Sewerage Scheme | - | 0 | 0 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall | 4 | 3.5 | 3.25 | 3.75 |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 3.54 | 3.18 | 3 | 2.83 |
| Internal Sewerage Scheme | 19.09 | 17.18 | 16.23 | 15.2 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0.25 | 0.23 | 0.21 | 0.19 |
| Roads & Pavements | 53.93 | 48.53 | 45.84 | 43.15 |
| Sewerage treatment & garbage disposal | 26.8 | 24.12 | 22.78 | 21.44 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 11.03 | 9.93 | 9.38 | 8.82 |
| Water Supply System | 28.95 | 25.92 | 24.45 | 23.01 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall | 3 | 2.5 | - | - |
| Clubhouse/community centres | 0 | 0 | - | - |
| Electricity Supply System | 2.68 | 2.47 | - | - |
| Internal Sewerage Scheme | 14.32 | 13.46 | - | - |
| Other | 0 | 0 | - | - |
| Parks and Playgrounds | 0.18 | 0.17 | - | - |
| Roads & Pavements | 40.45 | 37.75 | - | - |
| Sewerage treatment & garbage disposal | 20.1 | 18.76 | - | - |
| Shopping area | 0 | 0 | - | - |
| Storm Water Drainage | 8.27 | 7.75 | - | - |
| Water Supply System | 21.5 | 20.14 | - | - |