| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 4.79 |
| Shopping area | 0 |
| Roads & Pavements | 46.31 |
| Water Supply System | 52.7 |
| Storm Water Drainage | 19.16 |
| Parks and Playgrounds | 3.19 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 33.54 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | - | - | - |
| Electricity Supply System | 0 | - | - | - |
| Other | 1.53 | - | - | - |
| Parks and Playgrounds | 1.03 | - | - | - |
| Roads & Pavements | 14.82 | - | - | - |
| Sewerage treatment & garbage disposal | 10.73 | - | - | - |
| Shopping area | 0 | - | - | - |
| Storm Water Drainage | 6.13 | - | - | - |
| Water Supply System | 16.86 | - | - | - |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Other | 1.53 | 1.53 | 1.53 | 1.53 |
| Parks and Playgrounds | 1.02 | 1.02 | 1.02 | 1.02 |
| Roads & Pavements | 14.82 | 14.82 | 14.82 | 14.82 |
| Sewerage treatment & garbage disposal | 10.73 | 10.73 | 10.73 | 10.73 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 6.13 | 6.13 | 6.13 | 6.13 |
| Water Supply System | 16.86 | 16.86 | 16.86 | 16.86 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Other | 1.53 | 1.53 | 1.53 | 1.53 |
| Parks and Playgrounds | 1.02 | 1.02 | 1.02 | 1.02 |
| Roads & Pavements | 14.82 | 14.82 | 14.82 | 14.82 |
| Sewerage treatment & garbage disposal | 10.73 | 10.73 | 10.73 | 10.73 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 6.13 | 6.13 | 6.13 | 6.13 |
| Water Supply System | 16.86 | 16.86 | 16.86 | 16.82 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | 0 | - | 0 |
| Electricity Supply System | - | 0 | - | 0 |
| Other | - | 1.53 | - | 2.3 |
| Parks and Playgrounds | - | 1.02 | - | 1.53 |
| Roads & Pavements | - | 14.82 | - | 22.23 |
| Sewerage treatment & garbage disposal | - | 10.73 | - | 16.1 |
| Shopping area | - | 0 | - | 0 |
| Storm Water Drainage | - | 6.13 | - | 9.2 |
| Water Supply System | - | 16.86 | - | 25.3 |
Tivoli Holiday Village Phase-I (Block-1, 2, 3 (4 Unit), Block4, 5, Villa-5 & Ews) Far 43012.988sqm is located in Rewari.
Yes. Tivoli Holiday Village Phase-I (Block-1, 2, 3 (4 Unit), Block4, 5, Villa-5 & Ews) Far 43012.988sqm is registered under RERA-PKL-770-2019 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Tivoli Holiday Village Phase-I (Block-1, 2, 3 (4 Unit), Block4, 5, Villa-5 & Ews) Far 43012.988sqm is 31 December 2022.
Tivoli Holiday Village Phase-I (Block-1, 2, 3 (4 Unit), Block4, 5, Villa-5 & Ews) Far 43012.988sqm is developed by T. G. BUILDWELL PVT. LTD..
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.