Infrastructure Total Expenditure
No total expenditure data is currently available for this project.
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | - | 0 | 0 |
| Electricity Supply System | - | - | 1.84 | 1.84 |
| Other | - | - | 11.84 | 11.84 |
| Parks and Playgrounds | - | - | 2.24 | 2.24 |
| Roads & Pavements | - | - | 9.55 | 9.55 |
| Sewerage treatment & garbage disposal | - | - | 6.53 | 6.53 |
| Shopping area | - | - | 0 | 0 |
| Storm Water Drainage | - | - | 5.12 | 5.12 |
| Water Supply System | - | - | 7.59 | 7.59 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 1.84 | 1.84 | 1.84 | 1.84 |
| Other | 11.84 | 11.84 | 11.84 | 11.84 |
| Parks and Playgrounds | 2.24 | 2.24 | 2.24 | 2.24 |
| Roads & Pavements | 9.55 | 9.55 | 9.55 | 9.55 |
| Sewerage treatment & garbage disposal | 6.53 | 6.53 | 6.53 | 6.53 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 5.12 | 5.12 | 5.12 | 5.12 |
| Water Supply System | 7.59 | 7.59 | 7.59 | 7.59 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 1.84 | 1.84 | 1.84 | 1.84 |
| Other | 11.84 | 11.84 | 11.84 | 11.84 |
| Parks and Playgrounds | 2.24 | 2.24 | 2.24 | 2.24 |
| Roads & Pavements | 9.55 | 9.55 | 9.55 | 9.55 |
| Sewerage treatment & garbage disposal | 6.53 | 6.53 | 6.53 | 6.53 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 5.12 | 5.12 | 5.12 | 5.12 |
| Water Supply System | 7.59 | 7.59 | 7.59 | 7.59 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 1.84 | 1.84 | 1.84 | 1.84 |
| Other | 1.84 | 11.84 | 11.84 | 11.84 |
| Parks and Playgrounds | 2.24 | 2.24 | 2.24 | 2.24 |
| Roads & Pavements | 9.55 | 9.55 | 9.55 | 9.55 |
| Sewerage treatment & garbage disposal | 6.53 | 6.53 | 6.53 | 6.53 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 5.12 | 5.12 | 5.12 | 5.12 |
| Water Supply System | 7.59 | 7.59 | 7.59 | 7.59 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 1.84 | 1.84 | 1.84 | 1.84 |
| Other | 11.84 | 11.84 | 11.84 | 11.84 |
| Parks and Playgrounds | 2.24 | 2.24 | 2.24 | 2.24 |
| Roads & Pavements | 9.55 | 9.55 | 9.55 | 9.55 |
| Sewerage treatment & garbage disposal | 6.53 | 6.53 | 6.53 | 6.53 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 5.12 | 5.12 | 5.12 | 5.12 |
| Water Supply System | 7.59 | 7.59 | 7.59 | 7.59 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | - | - |
| Electricity Supply System | 1.84 | 1.84 | - | - |
| Other | 11.84 | 11.84 | - | - |
| Parks and Playgrounds | 2.24 | 2.24 | - | - |
| Roads & Pavements | 9.55 | 9.55 | - | - |
| Sewerage treatment & garbage disposal | 6.53 | 6.53 | - | - |
| Shopping area | 0 | 0 | - | - |
| Storm Water Drainage | 5.12 | 5.12 | - | - |
| Water Supply System | 7.59 | 7.59 | - | - |
The Flower City is located in Panipat.
Yes. The Flower City is registered under RERA-PKL-1124-2022 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for The Flower City is 23 June 2027.
The Flower City is developed by UPRIGHT INFRAHEIGHTS PRIVATE LIMITED.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.