| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | - | 0 | 0 |
| ESS | - | - | - | - |
| Electricity Supply System | - | - | 0 | 0 |
| Hospital or Dispensary | - | - | - | - |
| Other | - | - | 0 | 0 |
| Parks and Playgrounds | - | - | 0 | 0 |
| RWH | - | - | - | - |
| Renewable Energy system | - | - | - | - |
| Roads & Pavements | - | - | 0 | 0 |
| School | - | - | - | - |
| Security and fire fighting | - | - | - | - |
| Sewerage treatment & garbage disposal | - | - | 72.33 | 91.16 |
| Shopping area | - | - | 0 | 0 |
| Storm Water Drainage | - | - | 0 | 0 |
| Street Lighting | - | - | - | - |
| UGT | - | - | - | - |
| Water Supply System | - | - | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 4.1 | 7.49 | 10.07 | 10.07 |
| ESS | - | - | - | - |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Hospital or Dispensary | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| RWH | - | - | - | - |
| Renewable Energy system | - | 9.92 | 19.84 | 13.37 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| School | - | - | - | - |
| Security and fire fighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 89.18 | 90.17 | 18.83 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Street Lighting | - | - | - | - |
| UGT | - | - | 71.54 | 90.16 |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 5.74 | 4.98 | 2.41 | 0 |
| ESS | - | - | - | - |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Hospital or Dispensary | - | - | 5.68 | 7.16 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| RWH | - | - | - | - |
| Renewable Energy system | - | - | - | - |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| School | - | 6.01 | 16.27 | 16.27 |
| Security and fire fighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Street Lighting | - | - | - | - |
| UGT | 88.2 | 89.18 | 18.62 | - |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| ESS | - | - | - | - |
| Electricity Supply System | 0 | 329 | 393.09 | 393.09 |
| Hospital or Dispensary | 7.08 | 7.08 | 1.4 | - |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| RWH | - | - | - | - |
| Renewable Energy system | - | - | - | - |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| School | 16.09 | 9.9 | - | - |
| Security and fire fighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 125.57 | 150.03 | 150.03 |
| Street Lighting | - | - | - | - |
| UGT | - | - | - | - |
| Water Supply System | 123.94 | 148.4 | 150.03 | 150.03 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | - |
| ESS | 6 | 546.39 | - | - |
| Electricity Supply System | 380.27 | 0 | 0 | - |
| Hospital or Dispensary | - | - | - | - |
| Other | 0 | 0 | 0 | - |
| Parks and Playgrounds | 0 | 22.06 | 9.96 | - |
| RWH | - | 94.77 | - | - |
| Renewable Energy system | - | - | - | - |
| Roads & Pavements | 3.11 | 283.3 | 273.96 | - |
| School | - | - | - | - |
| Security and fire fighting | 9.02 | 821.23 | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | - |
| Shopping area | 0 | 0 | 0 | - |
| Storm Water Drainage | 146.77 | 14.68 | 0 | - |
| Street Lighting | 0.8 | 72.41 | - | - |
| UGT | - | - | - | - |
| Water Supply System | 14.68 | 0 | 0 | - |