RERA Received Date
Completion Date
RERA ID
28.974849
79.366153
E- 12 mtr road, W- other property N 12, mtr road, S-Chak Road
RCC and Brick Work structure with MS railing with plaster finish and paint, as per plan
two layer WBM , black top /CC paver on top, curve stone etc
paver tile over base of PCC
water supply through bore well/ Municipal supply collected in under ground water tank and pumped to over head water tank, further distribution from over head tank to individual units under gravity
Sewer system with RCC hume pipes connected to STP, treated water will be used for gardening and flushing, excess treated water would be disposed in green area / municipal line.
Storm water Drain system with RCC pipes connected to Rain Water Harvesting Pits.
parks will be provided as per the approved plan
tree planting will be done as per the approved plan
electrical supply including street light (GI poles) will be provided as per the scheme approval
NA
Sewer system with RCC pipes connected to STP, treated water will be used for gardening and flushing, excess treated water would be disposed in green area/ municipal area
would be provided as per guidelines given in EC approval
rain water harvesting pits are planned (as required) for recharging of under ground water aquifers
solar panel used as far as possible for energy conservation. CFL/LED bulbs would be used for common area lighting
fire hydrant would be provided as per norms
would be provided as per guidelines given in EC approval
Na
boundary wall and main gate would be constructed for security of the complex, CCTV camera would be used on main gate for visitor monitoring
Showing 8 blocks with 265 units
Total Carpet Area
33763.51 m²
363427.05 ft²
Total Units
214
4 different types
Blocks & Floors
8
14 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
49106.87 m²
528581.44 ft²