Have queries on this Project?
Uploaded on: 30-06-2024
Uploaded on: 30-06-2024
Uploaded on: 30-06-2024
Uploaded on: 30-06-2024




| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | 0 | 0 | 0 |
| Electricity Supply System | - | 7 | 7 | 5 |
| Electrification | - | 7 | 7 | 7 |
| Other | - | 0 | 0 | 0 |
| Parks and Playgrounds | - | 2 | 2 | 2 |
| Rain Water Harvesting | - | 2 | 2 | 2 |
| Roads & Pavements | - | 35 | 35 | 35 |
| Security and Firefighting Services | - | 2.5 | 2.5 | 2.5 |
| Sewerage | - | 25 | 25 | 20 |
| Sewerage treatment & garbage disposal | - | 8 | 8 | 8 |
| Shopping area | - | 0 | 0 | 0 |
| Storm Water Drainage | - | 25 | 25 | 20 |
| Street Lights | - | 6 | 6 | 6 |
| Underground Tank | - | 5 | 4 | 3 |
| Water Supply System | - | 35 | 35 | 35 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 5 | 4 | 4 | 4 |
| Electrification | 6 | 6 | 6 | 6 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 1 | 1 | 1 | 0.56 |
| Rain Water Harvesting | 1.5 | 1.5 | 1.5 | 1.5 |
| Roads & Pavements | 30 | 30 | 30 | 25 |
| Security and Firefighting Services | 2 | 2 | 2 | 2 |
| Sewerage | 20 | 15 | 15 | 15 |
| Sewerage treatment & garbage disposal | 7 | 7 | 7 | 7 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 16 | 15 | 8 | 8 |
| Street Lights | 5 | 5 | 4 | 4 |
| Underground Tank | 3 | 2 | 2 | 2 |
| Water Supply System | 30 | 0 | 15 | 10 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 4 | 3 | 3 | 3 |
| Electrification | 5 | 4 | 4 | 4 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0.5 | 0.35 | 0.35 | 0.35 |
| Rain Water Harvesting | 1 | 1 | 1 | 1 |
| Roads & Pavements | 25 | 15 | 10 | 5 |
| Security and Firefighting Services | 1.5 | 1.5 | 1.25 | 1.25 |
| Sewerage | 8 | 8 | 8 | 5 |
| Sewerage treatment & garbage disposal | 5 | 5 | 5 | 5 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 6 | 6 | 6 | 6 |
| Street Lights | 4 | 3 | 2.5 | 2 |
| Underground Tank | 2 | 2 | 2 | 2 |
| Water Supply System | 9 | 9 | 9 | 9 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 3 | 2.5 | 2.5 | 2.5 |
| Electrification | 4 | 3 | 3 | 3 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0.25 | 0.25 | 0.25 | 0.25 |
| Rain Water Harvesting | 0.5 | 0.5 | 0.25 | 0.25 |
| Roads & Pavements | 5 | 5 | 5 | 4 |
| Security and Firefighting Services | 1 | 1 | 1 | 0.5 |
| Sewerage | 4 | 2 | 2 | 2 |
| Sewerage treatment & garbage disposal | 4 | 4 | 4 | 3 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 5 | 5 | 5 | 5 |
| Street Lights | 1.5 | 1.5 | 1.5 | 1.5 |
| Underground Tank | 1.5 | 1.5 | 1.5 | 1.5 |
| Water Supply System | 8 | 8 | 5 | 5 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | - | - |
| Electricity Supply System | 2 | 0.75 | - | - |
| Electrification | 3 | 1.53 | - | - |
| Other | 0 | 0 | - | - |
| Parks and Playgrounds | 0.2 | 0 | - | - |
| Rain Water Harvesting | 0.25 | 0.25 | - | - |
| Roads & Pavements | 2 | 0.38 | - | - |
| Security and Firefighting Services | 0.5 | 0 | - | - |
| Sewerage | 2 | 0.85 | - | - |
| Sewerage treatment & garbage disposal | 1 | 0.4 | - | - |
| Shopping area | 0 | 0 | - | - |
| Storm Water Drainage | 2 | 1.36 | - | - |
| Street Lights | 1 | 0.7 | - | - |
| Underground Tank | 1.5 | 0.65 | - | - |
| Water Supply System | 3 | 2.41 | - | - |
Sirsa Greens is located in Sirsa.
Yes. Sirsa Greens is registered under RERA-PKL-1496-2024 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Sirsa Greens is 29 October 2028.
Sirsa Greens is developed by VANESSA BUILDERS AND DEVELOPERS PVT. LTD..
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.