Infrastructure Total Expenditure
No total expenditure data is currently available for this project.
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | - | 0 | 0 |
| Electricity Supply System | 0 | - | 15.625 | 15.625 |
| Other | 0 | - | 0 | 0 |
| Parks and Playgrounds | 0 | - | 0 | 0 |
| Roads & Pavements | 0 | - | 36.437 | 36.437 |
| STREET LIGHTING | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | - | 25 | 25 |
| Shopping area | 0 | - | 0 | 0 |
| Storm Water Drainage | 0 | - | 9.375 | 9.375 |
| Water Supply System | 0 | - | 8.312 | 8.312 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 15.625 | 15.625 | 15.625 | 15.625 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 36.437 | 36.437 | 36.437 | 36.437 |
| STREET LIGHTING | - | - | - | - |
| Sewerage treatment & garbage disposal | 25 | 25 | 25 | 25 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 9.375 | 9.375 | 9.375 | 9.375 |
| Water Supply System | 8.312 | 8.312 | 8.312 | 8.312 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 15.625 | 15.625 | 15.625 | 15.625 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 36.437 | 36.437 | 36.437 | 36.437 |
| STREET LIGHTING | - | - | - | - |
| Sewerage treatment & garbage disposal | 25 | 25 | 25 | 25 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 9.375 | 9.375 | 9.375 | 9.375 |
| Water Supply System | 8.312 | 8.312 | 8.312 | 8.312 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 15.625 | 15.625 | 15.625 | 15.625 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 36.437 | 36.437 | 36.437 | 36.437 |
| STREET LIGHTING | 18.75 | 18.75 | 18.75 | 18.75 |
| Sewerage treatment & garbage disposal | 25 | 25 | 25 | 25 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 9.375 | 9.375 | 9.375 | 9.375 |
| Water Supply System | 8.312 | 8.312 | 8.312 | 8.312 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 15.625 | 15.625 | 15.625 | 15.625 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 36.437 | 36.437 | 36.437 | 36.437 |
| STREET LIGHTING | 18.75 | 18.75 | 18.75 | 18.75 |
| Sewerage treatment & garbage disposal | 25 | 25 | 25 | 25 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 9.375 | 9.375 | 9.375 | 9.375 |
| Water Supply System | 8.312 | 8.312 | 8.312 | 8.312 |
Sector 18 Ambala Business Park is located in Ambala.
Yes. Sector 18 Ambala Business Park is registered under RERA-PKL-2045-2026 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Sector 18 Ambala Business Park is 15 March 2031.
Sector 18 Ambala Business Park is developed by NAVDESH ASSOCIATES LLP.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.