Launch Date
Completion Date
RERA ID
77 25 23.0
28 36 34.0
Not Applicable
Brick Wall of 2150 from internal road finised well
Internal road as 6m wide for traffic and fire tender movement
Using Interlocking pavers for footpaths
The domestic water stored in the Centralized underground domestic water tank shall be supplied through to OHT Through a Hydro-pneumatic System for Overhead tanks fillings water supply to the toilets and Kitchens through the gravity.
"C.I. Pipes For exposed pipes running along the basement ceiling for final disposal to external sewerage system as per site conditions. "
The network of storm water system shall be mostly catch basins and RCC pipe network, as per requirements. For Roof Drainage.
AS PER LANDSCAPE LAYOUT PLAN AND EXTERNAL DEVELOPMENT PLAN
AS PER LANDSCAPE LAYOUT PLAN AND EXTERNAL DEVELOPMENT PLAN
"Sub-station 2 x 2000 KVA, 33KV / 0.433V, OIL type Compact Substation DG Sets 3 x 1500 KVA, 415V 3phase Radiator cooled DG Sets"
yes, Club House
Sewerage Treatment Plant of 400 kld is proposed at the project.Treated water shall be used for flushing, irrigation, pathways cleaning and excess sewage shall be discharged in the municipal sewer.
Organic waste management through composter machine.
Provision of Rain Water Harvesting and Water Conservation
Not Applicable
Centralized Static Underground storage fire tank of 300 m3 capacity and terrace tanks of 25 m3 capacities each towers.
Not Applicable
Fire Staircase and Fire cum service lifts
Not Applicable
Showing 9 blocks with 437 units
Total Carpet Area
63512.27 m²
683639.72 ft²
Total Units
758
4 different types
Blocks & Floors
9
23 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
20947.00 m²
225471.41 ft²