Infrastructure Total Expenditure
No total expenditure data is currently available for this project.
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Construction of Circular Road | 3.75 | 3.75 | 3.75 | 3.75 |
| Electrical Sub Station | 1.25 | 1.25 | 1.25 | 1.25 |
| Electricity Supply System | 8 | 8 | 8 | 8 |
| Other | 0 | 0 | 0 | 0 |
| Parking | 6.25 | 6.25 | 6.25 | 6.25 |
| Parks and Playgrounds | 0.41 | 0.41 | 0.41 | 0.41 |
| Rainwater Harvesting | 0.25 | 0.25 | 0.25 | 0.25 |
| Renewable Energy System | 0.63 | 0.63 | 0.63 | 0.63 |
| Roads & Pavements | 2.71 | 2.71 | 2.71 | 2.71 |
| STP | 1.5 | 1.5 | 1.5 | 1.5 |
| Security and Firefighting Services | 8 | 8 | 8 | 8 |
| Sewerage treatment & garbage disposal | 4.5 | 4.5 | 4.5 | 4.5 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 1.38 | 1.38 | 1.38 | 1.38 |
| Street Light | 0.44 | 0.44 | 0.44 | 0.44 |
| Underground Tank | 1.25 | 1.25 | 1.25 | 1.25 |
| Water Supply System | 3.74 | 3.74 | 3.74 | 3.74 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Construction of Circular Road | 26.25 | 26.25 | 26.25 | 26.25 |
| Electrical Sub Station | 8.75 | 8.75 | 8.75 | 8.75 |
| Electricity Supply System | 56.03 | 56.03 | 56.03 | 56.03 |
| Other | 0 | 0 | 0 | 0 |
| Parking | 43.75 | 43.75 | 43.75 | 43.75 |
| Parks and Playgrounds | 2.84 | 2.84 | 2.84 | 2.84 |
| Rainwater Harvesting | 1.75 | 1.75 | 1.75 | 1.75 |
| Renewable Energy System | 4.38 | 4.38 | 4.38 | 4.38 |
| Roads & Pavements | 81.96 | 18.96 | 18.96 | 18.96 |
| STP | 10.5 | 10.5 | 10.5 | 10.5 |
| Security and Firefighting Services | 56.03 | 56.03 | 56.03 | 56.03 |
| Sewerage treatment & garbage disposal | 31.5 | 31.5 | 31.5 | 31.5 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 9.63 | 9.63 | 9.63 | 9.63 |
| Street Light | 3.11 | 3.11 | 3.11 | 3.11 |
| Underground Tank | 8.75 | 8.75 | 8.75 | 8.75 |
| Water Supply System | 26.17 | 26.17 | 26.17 | 26.17 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Construction of Circular Road | 12 | 12 | 6 | 0 |
| Electrical Sub Station | 4 | 4 | 2 | 0 |
| Electricity Supply System | 25.61 | 25.61 | 12.81 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parking | 20 | 20 | 10 | - |
| Parks and Playgrounds | 1.3 | 1.3 | 0.65 | 0 |
| Rainwater Harvesting | 0.8 | 0.8 | 0.4 | 0 |
| Renewable Energy System | 2 | 2 | 1 | 0 |
| Roads & Pavements | 8.67 | 8.67 | 4.33 | 0 |
| STP | 4.8 | 4.8 | 2.4 | 0 |
| Security and Firefighting Services | 25.61 | 25.61 | 12.81 | 0 |
| Sewerage treatment & garbage disposal | 14.4 | 14.4 | 7.2 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 4.4 | 4.4 | 2.2 | 0 |
| Street Light | 1.42 | 1.42 | 0.71 | 0 |
| Underground Tank | 4 | 4 | 2 | 0 |
| Water Supply System | 11.97 | 11.97 | 5.98 | 0 |
Royal Green Heights is located in Gurugram.
Yes. Royal Green Heights is registered under RERA-GRG-995-2021 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Royal Green Heights is 28 July 2026.
Royal Green Heights is developed by M/S SYNERGYSHINE INFRA LLP IN COLLABORATION WITH GULMOHAR FINANCE LTD.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.