Launch Date
Completion Date
RERA ID
Uploaded on: 05-03-2025
Uploaded on: 05-03-2025
Uploaded on: 05-03-2025
Uploaded on: 05-03-2025



| Particulars | Expenditure (in Lakhs) |
|---|---|
| MEP | 0 |
| Other | 0 |
| Finishing | 0 |
| Shopping area | 0 |
| Sub Structure | 0 |
| Super Structure | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | - | - | 0 |
| Electricity Supply System | - | - | - | 0 |
| Finishing | - | - | - | - |
| MEP | - | - | - | - |
| Other | - | - | - | 0 |
| Parks and Playgrounds | - | - | - | 0 |
| Roads & Pavements | - | - | - | 0 |
| Sewerage treatment & garbage disposal | - | - | - | 0 |
| Shopping area | - | - | - | 0 |
| Storm Water Drainage | - | - | - | 0 |
| Sub Structure | - | - | - | - |
| Super Structure | - | - | - | - |
| Water Supply System | - | - | - | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Finishing | 217.47 | 217.47 | 455.79 | 455.79 |
| MEP | 72.49 | 72.49 | 151.93 | 151.93 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Sub Structure | 144.98 | 144.98 | 303.86 | 303.86 |
| Super Structure | 289.96 | 289.96 | 607.73 | 607.73 |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Finishing | 1073.25 | 1073.25 | 1230.29 | 1230.29 |
| MEP | 357.75 | 357.75 | 410.09 | 410.09 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Sub Structure | 715.5 | 715.5 | 820.19 | 820.19 |
| Super Structure | 1431 | 1431 | 1640.38 | 1640.38 |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Finishing | 1256.74 | 1256.74 | 847.79 | 847.79 |
| MEP | 418.91 | 418.91 | 282.59 | 282.59 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Sub Structure | 837.83 | 837.83 | 565.19 | 565.19 |
| Super Structure | 1675.66 | 1675.66 | 1130.38 | 1130.38 |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Finishing | 400.97 | 400.97 | 73.3 | 73.3 |
| MEP | 133.65 | 133.65 | 24.43 | 24.43 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Sub Structure | 267.31 | 267.31 | 48.87 | 48.87 |
| Super Structure | 534.62 | 534.62 | 97.74 | 97.74 |
| Water Supply System | 0 | 0 | 0 | 0 |