NEWActive

ROF PRAVASA

GURUGRAM, HARSARU ST
25-11-2024
Launch Date
NEW
Type
2030-04-30
Completion Date

Overview

Launch Date

25-11-2024

Completion Date

2030-04-30

RERA ID

RERA-GRG-1775-2024

Basic Details

Project NameROF PRAVASA
Project IDRERA-GRG-1775-2024
Project TypeNEW
Applicant TypeCompany
Submission Date25-11-2024 05:50:18 PM
Builder NameNANI RESORTS AND FLORICULTURE PRIVATE LIMITED
CINU55101DL1999PTC098037
PANXXXX603L
EmailCOMPLIANCE@ROF.CO.IN
Websitehttps://www.rof.co.in
Phone (Mobile)9717022441
Phone (Landline)01244399399
Registered AddressPLOT NO.80, SECTOR-44, GURUGRAM
Project AddressVILLAGE HARSARU, SEC-88A, GURUGRAM
DistrictGURUGRAM
TehsilHARSARU ST

Bank Details

Bank NameSTATE BANK OF INDIA, PLOT NO. 91, IDC,1ST FLOOR, MG ROAD, GURUGRAM-122001
Account Number43637057308
IFSC CodeSBIN0050933
MICR Code110002777
Branch Code50933

Account Related Information

Annex copy of the balance sheet of last 3 yearsYes
In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.No
Name and address of the person/persons who would ordinarily be operating the account (Change at any time must be intimated to the Authority)Mohit Mittal, B-62,South Extension-I, New Delhi-110049
Attach certificate issued by a Chartered Accountant that the applicant has not defaulted in its debt liabilities in the past five years in folder D. (In case of default, give details)Yes

Development Details

Land Area11.21 (Acre)
Proposed FAR2.64
Permissible FAR2.64
Total Licensed Land11.21 (Acre)

Land Usage

PLOTS TO BE SOLD0
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS6.958
CONSTRUCTION OF ROADS0
PAVEMENTS0
PARKS AND PLAYGROUNDS0
GREEN BELTS0
VEHICLE PARKINGS0
ELECTRICITY SUB-STATION0
CLUB HOUSE0
SEWAGE AND SOLID WASTE TREATMENT FACILITY0
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
ANY OTHER0
Total6.958

Cost Details

Land Cost14076.00 Lakhs
Other Cost8303.07 Lakhs
Estimated Project Cost59416.67 Lakhs
Estimated Infrastructure Cost0 Lakhs
Estimated Apartment Construction Cost37037.60 Lakhs

Documents

IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN

Uploaded on: 05-03-2025

ZONING PLAN

Uploaded on: 05-03-2025

CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT

Uploaded on: 05-03-2025

DEMARCATION PLAN

Uploaded on: 05-03-2025

COPY OF LICENSE ALONG WITH SCHEDULE OF LAND

Uploaded on: 05-03-2025

CASH FLOW STATEMENT OF THE PROPOSED PROJECT

Uploaded on: 05-03-2025

IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN

Uploaded on: 05-03-2025

DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.

Uploaded on: 05-03-2025

DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD

Uploaded on: 05-03-2025

NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT

Uploaded on: 05-03-2025

A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS

Uploaded on: 05-03-2025

SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN

Uploaded on: 05-03-2025

Statutory Approvals

LICENSE NO 70 OF 2023Date: 05-04-2023Status: ALREADY BEEN OBTAINED
BUILDING PLAN PLOT NO. 1-49Date: 18-10-2024Status: ALREADY BEEN OBTAINED
BUILDING PLAN PLOT NO. 50-152Date: 11-10-2024Status: ALREADY BEEN OBTAINED
BUILDING PLAN PLOT NO. 67-74Date: 18-10-2024Status: ALREADY BEEN OBTAINED
BUILDING PLAN PLOT NO. 144-149Date: 08-11-2024Status: ALREADY BEEN OBTAINED
BUILDING PLAN PLOT NO. 153-157Date: 18-10-2024Status: ALREADY BEEN OBTAINED
BUILDING PLAN PLOT NO. 158Date: 08-11-2024Status: ALREADY BEEN OBTAINED
BUILDING PLAN PLOT NO. 159-166Date: 08-11-2024Status: ALREADY BEEN OBTAINED
BUILDING PLAN PLOT NO. 167-179Date: 11-10-2024Status: ALREADY BEEN OBTAINED
BUILDING PLAN PLOT NO. 180Date: 08-11-2024Status: ALREADY BEEN OBTAINED
BUILDING PLAN PLOT NO. 181-203Date: 18-10-2024Status: ALREADY BEEN OBTAINED
BUILDING PLAN PLOT NO. 186Date: 12-11-2024Status: ALREADY BEEN OBTAINED
BUILDING PLAN PLOT NO. 193-196Date: 08-11-2024Status: ALREADY BEEN OBTAINED
BUILDING PLAN PLOT NO. 204Date: 08-11-2024Status: ALREADY BEEN OBTAINED
Lay out PlanApproved: Yes
Demarcation PlanApproved: Yes
Zoning PlanApproved: Yes
Building PlanApproved: Yes
Site PlanApproved: Yes
Floor PlanApproved: Yes
Apartment PlansApproved: Yes
Elevation SectionApproved: Yes
Detail of Permissible FARApproved: Yes
Detail of covered area achieved FARApproved: Yes

Facilities

INTERNAL ROADS AND PAVEMENTSSUBMITTED TO TOWN & COUNTRY PLANNING
WATER SUPPLY SYSTEMSUBMITTED TO TOWN & COUNTRY PLANNING
STORM WATER DRAINAGESUBMITTED TO TOWN & COUNTRY PLANNING
ELECTRICITY SUPPLY SYSTEMSUBMITTED TO TOWN & COUNTRY PLANNING
SEWAGE TREATMENT & GARBAGE DISPOSALSUBMITTED TO TOWN & COUNTRY PLANNING
STREET LIGHTINGSUBMITTED TO TOWN & COUNTRY PLANNING
SECURITY AND FIRE FIGHTINGSUBMITTED TO TOWN & COUNTRY PLANNING
PLAYGROUNDS AND PARKSSUBMITTED TO TOWN & COUNTRY PLANNING
CLUB HOUSE/COMMUNITY CENTRESUBMITTED TO TOWN & COUNTRY PLANNING
SHOPPING AREASUBMITTED TO TOWN & COUNTRY PLANNING
RENEWABLE ENERGY SYSTEMSUBMITTED TO TOWN & COUNTRY PLANNING
SCHOOLSUBMITTED TO TOWN & COUNTRY PLANNING
HOSPITAL/DISPENSARYSUBMITTED TO TOWN & COUNTRY PLANNING
ANY OTHERSUBMITTED TO TOWN & COUNTRY PLANNING

NOC

ROADSProvider: GMDA (APPLIED)Approval Status: Pending
WATER SUPPLYProvider: GMDAApproval Status: Approved
ELECTRICITYProvider: GMDAApproval Status: Approved
SEWAGE DISPOSALProvider: GMDAApproval Status: Approved
STORM WATER DRAINAGEProvider: GMDAApproval Status: Approved

Project Team

Authorized Representative

MANISH KUMAR
Name
MANISH KUMAR
PAN
XXXX773L
Email
compliance@rof.co.in
Mobile
9717022441
Landline
01244399399
Address
Manesar Gurugram Haryana

Managing Director/CEO

GOVIND
Name
GOVIND
PAN
XXXX504B
Email
compliance@rof.co.in
Mobile
9717022441
Landline
01244399399
Address
Madhubani Bihar

Directors

PRABODH MISHRA
Name
PRABODH MISHRA
PAN
XXXX999P
Email
compliance@rof.co.in
Mobile
9717022441
Landline
01244399399
Address
Mehrali Madhubani Bihar

Contact Details

Project ContactEmail: compliance@rof.co.inMobile: 9560890400Landline: 01244399399
Project Contact PersonName: MUKESH KUMAREmail: compliance@rof.co.inMobile: 9560890400Landline: 01244399399

Land Details

Land Area11.21 (Acre)
Proposed FAR2.64
Permissible FAR2.64
Total Licensed Land11.21 (Acre)

Land Usage

Land Cost14076.00 Lakhs
Other Cost8303.07 Lakhs
Estimated Project Cost59416.67 Lakhs
Estimated Infrastructure Cost0 Lakhs
Estimated Apartment Construction Cost37037.60 Lakhs

Total Infrastructure Expenditure

ParticularsExpenditure (in Lakhs)
MEP0
Other0
Finishing0
Shopping area0
Sub Structure0
Super Structure0
Roads & Pavements0
Water Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Electricity Supply System0
Clubhouse/community centres0
Sewerage treatment & garbage disposal0

Quarterly Infrastructure Expenditure

2024 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres---0
Electricity Supply System---0
Finishing----
MEP----
Other---0
Parks and Playgrounds---0
Roads & Pavements---0
Sewerage treatment & garbage disposal---0
Shopping area---0
Storm Water Drainage---0
Sub Structure----
Super Structure----
Water Supply System---0
2025 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres0000
Electricity Supply System0000
Finishing217.47217.47455.79455.79
MEP72.4972.49151.93151.93
Other0000
Parks and Playgrounds0000
Roads & Pavements0000
Sewerage treatment & garbage disposal0000
Shopping area0000
Storm Water Drainage0000
Sub Structure144.98144.98303.86303.86
Super Structure289.96289.96607.73607.73
Water Supply System0000
2026 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres0000
Electricity Supply System0000
Finishing1073.251073.251230.291230.29
MEP357.75357.75410.09410.09
Other0000
Parks and Playgrounds0000
Roads & Pavements0000
Sewerage treatment & garbage disposal0000
Shopping area0000
Storm Water Drainage0000
Sub Structure715.5715.5820.19820.19
Super Structure143114311640.381640.38
Water Supply System0000
2027 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres0000
Electricity Supply System0000
Finishing1256.741256.74847.79847.79
MEP418.91418.91282.59282.59
Other0000
Parks and Playgrounds0000
Roads & Pavements0000
Sewerage treatment & garbage disposal0000
Shopping area0000
Storm Water Drainage0000
Sub Structure837.83837.83565.19565.19
Super Structure1675.661675.661130.381130.38
Water Supply System0000
2028 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres0000
Electricity Supply System0000
Finishing400.97400.9773.373.3
MEP133.65133.6524.4324.43
Other0000
Parks and Playgrounds0000
Roads & Pavements0000
Sewerage treatment & garbage disposal0000
Shopping area0000
Storm Water Drainage0000
Sub Structure267.31267.3148.8748.87
Super Structure534.62534.6297.7497.74
Water Supply System0000

Other Details

Construction Specifications

FLOORING DETAILS OF VARIOUS PARTS OF HOUSETILE/ LAMINATED WOODEN FLOOR/ ANTI SKID CERAMIC TILES/ HEAVY DUTY ANTI SKID/ STONE FLOORING.
WALL FINISHING DETAILSPLASTIC EMULSION PAINT
KITCHEN DETAILSCERAMIC TILE ON FLOOR, PLASTIC EMULSION PAINT ON ALL WALLS, CERAMIC TILES UP TO 2 FEET HEIGHTFROM THE PLATFORM, CEILING AS PER THEDESIGN, TOUGHENED GLASS UPVC/ ALUMINUM WINDOWS, WIRING WITH PVC CONCEALED/ CONDUIT,PROVISION OF LIGHTS AND POWER POINTS WITH MODULAR SWITCHED WITH MCB'S.KITCHEN TOP GRANITE.
BATHROOM FITTINGSFITTING WITH LOCK, WALL MOUNTED WC, WASH BASIN, CP FITTING BRANDED
WOOD WORK ETCMODULAR WOOD WORK.
DOORS AND WINDOS FRAMESFLUSH DOOR & UPVC/ ALUMINIUM WINDOWS EXTERNAL
GLASS WORKSTRUCTURE GLASSING WITH OPENABLE PANEL ORUPVC/ ALUMINUM.
ELECTRIC FITTINGSWIRING WITH PVC CONCEALED/ CONDUIT,PROVISION OF LIGHTS AND POWER POINTS WITHMODULAR SWITCHES WITH PROTECTIVE MCB'S.
CONDUCTING AND WIRING DETAILSWIRING WITH PVC CONCEALED/ CONDUIT.
CUPBOARD DETAILSMODULAR CUPBOARDS.
WATER STORAGEOVERHEAD WATER TANK.
LIFT DETAILSISI BRANDED LIFTS
EXTERNAL GLAZINGSUPVC/ ALUMINUM WITH TOUGHENED GLASS
WINDOWS/GLAZINGSUPVC/ ALUMINUM WITH TOUGHENED GLASS
DOORSLAMINATED FLUSH DOOR WITH HARD WOODFRAME.
MAIN DOORSLAMINATED FLUSH DOOR WITH HARD WOODFRAME.
INTERNAL DOORSFLUSH DOOR WITH HARD WOOD FRAME.
AIR CONDITIONINGN/A
ELECTRICAL FITTINGSPOWERPOINT WITH MODULAR SWITCHES WITHPROTECTIVE MCB'S. FAN AND LIGHTS
CNG PIPE LINEAS PER THE GOVERNMENT AUTHORITY
PROVISION OF WIFI AND BROADBAND FACILITYAS PER ACTUAL CONDITION
EXTERNAL FINISHING/COLOUR SCHEMEWEATHER SHIELD PAINTING
INTERNAL FINISHINGPLASTIC EMULSION PAINT

Unit-wise Specifications

TOILET
FLOORANTI SKID CERAMIC TILES
WALLSCERAMIC TILES CLADDED UP TO WALL CEILINGHEIGHTS
CEILINGAS PER DESIGN
COUNTERSGRANITE/ STONE
SANITARY WARE/CP FITTINGSBRANDED WALL MOUNTED WC SEAT, COUNTERTOP WASH BASIN, SHOWER PANEL WITH OTHERCP FITTING.
FIXTURESBRANDED WALL MOUNTED WC SEAT, COUNTERTOP WASH BASIN, SHOWER PANEL WITH OTHERCP FITTING.
KITCHEN
FLOORTILES
WALLSPLASTIC EMULSION PAINT
CEILINGAS PER DESIGN
COUNTERSCERAMIC TILES UP TO 2 FEET HEIGHT FROM THEPLATFORM/ COUNTER. KITCHEN TOP GRANITE.
FIXTURESCP FITTING WITH DOUBLE BOWL STAINLESSSTEEL SINK AND TAP.
KITCHEN APPLIANCESNA
SIT-OUTS
FLOORHEAVY DUTY ANTI SKID
WALLS & CEILINGPAINT AS PER EXTERIOR
RAILINGSRAILING/ PARAPET
FIXTURESNA
BED ROOMS
FLOORTILES
WALLSPLASTIC EMULSION PAINT
CEILINGAS PER DESIGN
WARDROBESMODULAR CUPBOARDS.
MASTER TOILET
FLOORANTI SKID CERAMIC TILES
WALLSCERAMIC TILES CLADDED UP TO WALL CEILINGHEIGHTS
CEILINGAS PER DESIGN
COUNTERSGRANITE/ STONE
SANITARY WARE/CP FITTINGSBRANDED WALL MOUNTED WC SEAT, COUNTERTOP WASH BASIN, SHOWER PANEL WITH OTHERCP FITTING.
FITTING/FIXTURESBRANDED WALL MOUNTED WC SEAT, COUNTERTOP WASH BASIN, SHOWER PANEL WITH OTHERCP FITTING.
MASTER BEDROOM/DRESSROOM
FLOORTILES
WALLSPLASTIC EMULSION PAINT
CEILINGAS PER DESIGN
MODULAR WARDROBESMODULAR CUPBOARDS.
LIVING/DINING/FOYER/FAMILY LOUNGE
FLOORTILES
WALLSPLASTIC EMULSION PAINT
CEILINGAS PER DESIGN
UTILITY ROOMS/UTILITY BALCONY/TOILET
FLOORANTI SKID CERAMIC TILES
WALLS & CEILINGCERAMIC TILES CLADDED UP TO WALL CEILINGHEIGHTS
TOILETWC WASHBASIN AND TAPS, OTHER CP FITTINGS
BALCONYRAILING/ PARAPET

Fee Details

Payment 1
amount:743500
cheque no:739427
draft date:25-11-2024
payable to:HRERA Gurugram
payee bank:PNB
Payment 2
amount:1963000
cheque no:739428
draft date:25-11-2024
payable to:HRERA Gurugram
payee bank:PNB