NEWActive

RANGOLI HILLS

PANCHKULA, PANCHKULA
14-05-2024
RERA Received Date
NEW
Type
2030-10-01
Completion Date

Overview

RERA Received Date

14-05-2024

Completion Date

2030-10-01

RERA ID

RERA-PKL-1467-2024

Basic Details

Project NameRANGOLI HILLS
Project IDRERA-PKL-1467-2024
Project TypeNEW
Applicant TypeCompany
Submission Date14-05-2024 04:12:48 PM
Builder NameRANGOLI BUILDTECH PVT. LTD.
CINU70101DL2004PTC129243
PANXXXX695P
WebsiteNot specified
Phone (Mobile)8800400785
Phone (Landline)01145783300
Registered AddressFLAT NO. 1010, 10TH FLOOR, MERCANTILE HOUSE, 15 KASTURBA GANDHI MARG, NEW DELHI-110001
Project AddressSECTOR 14 VILLAGE KOT
DistrictPANCHKULA
TehsilPANCHKULA

Bank Details

Bank NameIDBI BANK LIMITED, SURYA KIRAN BUILDING, 19, KG MARG DELHI
Account Number0011102000087975
IFSC CodeIBKL0000011
MICR Code110259001
Branch Code00011

Account Related Information

Annex copy of the balance sheet of last 3 yearsYes
In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.No
Name and address of the person/persons who would ordinarily be operating the account (Change at any time must be intimated to the Authority)SH. RAM MEHAR DAHIYA R/O 432, SECTOR 17A, Gurgaon-122001
Attach certificate issued by a Chartered Accountant that the applicant has not defaulted in its debt liabilities in the past five years in folder D. (In case of default, give details)UPLOADED IN UPLOAD SECTION

Development Details

Land Area7.66875 (Acre)
Proposed FAR1.00
Permissible FAR1.00 FOR PLOTTED AND 1.5 FOR COMMERCIAL
Total Licensed Land7.66875 (Acre)

Land Usage

PLOTS TO BE SOLD4.04050
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
CONSTRUCTION OF ROADS1.97289
PAVEMENTS0
PARKS AND PLAYGROUNDS0.5814
GREEN BELTS0
VEHICLE PARKINGS0
ELECTRICITY SUB-STATION0
CLUB HOUSE0
SEWAGE AND SOLID WASTE TREATMENT FACILITY0
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0.76726
ANY OTHER0
COMMERCIAL0.30670
Total7.66875

Cost Details

Land Cost560.7 Lakhs
Other Cost229.9 Lakhs
Estimated Project Cost1782.83 Lakhs
Estimated Infrastructure Cost992.230 Lakhs
Estimated Apartment Construction Cost0 Lakhs

Documents

DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.

Uploaded on: 30-04-2024

COPY OF LICENSE ALONG WITH SCHEDULE OF LAND

Uploaded on: 30-04-2024

IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN

Uploaded on: 30-04-2024

IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN

Uploaded on: 30-04-2024

NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT

Uploaded on: 30-04-2024

Statutory Approvals

LICENSE NO. 200 OF 2023Date: 04-10-2023Status: ALREADY BEEN OBTAINED
DEMARCATION-CUM-ZONING PLANDate: 26-04-2024Status: ALREADY BEEN OBTAINED
Lay out PlanApproved: Yes
Demarcation PlanApproved: Yes
Zoning PlanApproved: Yes
Building PlanApproved: No
Site PlanApproved: No
Floor PlanApproved: No
Apartment PlansApproved: No
Elevation SectionApproved: No
Detail of Permissible FARApproved: No
Detail of covered area achieved FARApproved: No

Facilities

INTERNAL ROADS AND PAVEMENTSAS PER PROJECT REPORT
WATER SUPPLY SYSTEMAS PER PROJECT REPORT
STORM WATER DRAINAGEAS PER PROJECT REPORT
ELECTRICITY SUPPLY SYSTEMAS PER PROJECT REPORT
SEWAGE TREATMENT & GARBAGE DISPOSALAS PER PROJECT REPORT
STREET LIGHTINGAS PER PROJECT REPORT
SECURITY AND FIRE FIGHTINGYET TO BE PREPARED
PLAYGROUNDS AND PARKSAS PER PROJECT REPORT
CLUB HOUSE/COMMUNITY CENTREYET TO BE PREPARED
SHOPPING AREAYET TO BE PREPARED
RENEWABLE ENERGY SYSTEMYET TO BE PREPARED
SCHOOLYET TO BE PREPARED
HOSPITAL/DISPENSARYYET TO BE PREPARED
ANY OTHERAS PER PROJECT REPORT

NOC

ROADSProvider: HSVPApproval Status: Pending
WATER SUPPLYProvider: HSVPApproval Status: Pending
ELECTRICITYProvider: UHBVNLApproval Status: Pending
SEWAGE DISPOSALProvider: HSVPApproval Status: Pending
STORM WATER DRAINAGEProvider: HSVPApproval Status: Pending

Project Team

Authorized Representative

ANIL KUMAR KARHANA
Name
ANIL KUMAR KARHANA
PAN
XXXX308J
Mobile
8800400785
Landline
01145783300
Address
Vill Firozpur Kalan Ballabgarh Faridabad

Managing Director/CEO

RAM MEHAR DAHIYA
Name
RAM MEHAR DAHIYA
PAN
XXXX128L
Mobile
8800400785
Landline
01145783300
Address
H. NO. 432 SECTOR 17A GURGAON

Directors

MANISH KUMAR
Name
MANISH KUMAR
PAN
XXXX021A
Mobile
8800400785
Landline
01145783300
Address
4783 Near Bhola Chowk Billu Colony Panipat Haryana

Contact Details

Project ContactEmail: [email protected]Mobile: 8800400785Landline: 01145783300
Project Contact PersonName: PANKAJ SHARMAEmail: [email protected]Mobile: 8800400785Landline: 01145783300

Land Details

Land Area7.66875 (Acre)
Proposed FAR1.00
Permissible FAR1.00 FOR PLOTTED AND 1.5 FOR COMMERCIAL
Total Licensed Land7.66875 (Acre)

Land Usage

Land Cost560.7 Lakhs
Other Cost229.9 Lakhs
Estimated Project Cost1782.83 Lakhs
Estimated Infrastructure Cost992.230 Lakhs
Estimated Apartment Construction Cost0 Lakhs

Total Infrastructure Expenditure

Infrastructure Total Expenditure

No total expenditure data is currently available for this project.

Quarterly Infrastructure Expenditure

2024 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres-000
Electricity Supply System-7.697.697.69
Other-8.898.898.89
Parks and Playgrounds-0.260.260.26
Roads & Pavements-6.786.786.78
Sewerage treatment & garbage disposal-4.394.394.39
Shopping area-000
Storm Water Drainage-2.742.742.74
Water Supply System-7.427.427.42
2025 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres0000
Electricity Supply System7.697.697.697.69
Other8.898.898.898.89
Parks and Playgrounds0.260.260.260.26
Roads & Pavements6.786.786.786.78
Sewerage treatment & garbage disposal4.394.394.394.39
Shopping area0000
Storm Water Drainage2.742.742.742.74
Water Supply System7.427.427.427.42
2026 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres0000
Electricity Supply System7.697.697.697.69
Other8.898.898.898.89
Parks and Playgrounds0.260.260.260.26
Roads & Pavements6.786.786.786.78
Sewerage treatment & garbage disposal4.394.394.394.39
Shopping area0000
Storm Water Drainage2.742.742.742.74
Water Supply System7.427.427.427.42
2027 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres0000
Electricity Supply System7.697.697.697.69
Other8.898.898.898.89
Parks and Playgrounds0.260.260.260.26
Roads & Pavements6.786.786.786.78
Sewerage treatment & garbage disposal4.394.394.394.39
Shopping area0000
Storm Water Drainage2.742.742.742.74
Water Supply System7.427.427.427.42
2028 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres0000
Electricity Supply System7.694.697.697.69
Other8.898.898.898.89
Parks and Playgrounds0.260.260.260.26
Roads & Pavements6.786.786.786.78
Sewerage treatment & garbage disposal4.394.394.394.39
Shopping area0000
Storm Water Drainage2.742.742.742.74
Water Supply System7.427.427.747.42
2029 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres0000
Electricity Supply System7.697.697.697.69
Other8.898.898.898.89
Parks and Playgrounds0.260.260.260.26
Roads & Pavements6.786.786.786.78
Sewerage treatment & garbage disposal4.394.394.394.39
Shopping area0000
Storm Water Drainage2.742.742.742.74
Water Supply System7.427.427.427.42
2030 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres000-
Electricity Supply System7.697.697.69-
Other8.898.898.89-
Parks and Playgrounds0.260.260.26-
Roads & Pavements6.786.786.78-
Sewerage treatment & garbage disposal4.394.394.39-
Shopping area000-
Storm Water Drainage2.742.742.74-
Water Supply System7.427.427.42-

Other Details

Construction Specifications

FLOORING DETAILS OF VARIOUS PARTS OF HOUSENOT APPLICABLE BEING PLOTTED COLONY
WALL FINISHING DETAILSNOT APPLICABLE BEING PLOTTED COLONY
KITCHEN DETAILSNOT APPLICABLE BEING PLOTTED COLONY
BATHROOM FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
WOOD WORK ETCNOT APPLICABLE BEING PLOTTED COLONY
DOORS AND WINDOS FRAMESNOT APPLICABLE BEING PLOTTED COLONY
GLASS WORKNOT APPLICABLE BEING PLOTTED COLONY
ELECTRIC FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
CONDUCTING AND WIRING DETAILSNOT APPLICABLE BEING PLOTTED COLONY
CUPBOARD DETAILSNOT APPLICABLE BEING PLOTTED COLONY
WATER STORAGENOT APPLICABLE BEING PLOTTED COLONY
LIFT DETAILSNOT APPLICABLE BEING PLOTTED COLONY
EXTERNAL GLAZINGSNOT APPLICABLE BEING PLOTTED COLONY
WINDOWS/GLAZINGSNOT APPLICABLE BEING PLOTTED COLONY
DOORSNOT APPLICABLE BEING PLOTTED COLONY
MAIN DOORSNOT APPLICABLE BEING PLOTTED COLONY
INTERNAL DOORSNOT APPLICABLE BEING PLOTTED COLONY
AIR CONDITIONINGNOT APPLICABLE BEING PLOTTED COLONY
ELECTRICAL FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
CNG PIPE LINENOT APPLICABLE BEING PLOTTED COLONY
PROVISION OF WIFI AND BROADBAND FACILITYNOT APPLICABLE BEING PLOTTED COLONY
EXTERNAL FINISHING/COLOUR SCHEMENOT APPLICABLE BEING PLOTTED COLONY
INTERNAL FINISHINGNOT APPLICABLE BEING PLOTTED COLONY

Unit-wise Specifications

TOILET
FLOORNOT APPLICABLE BEING PLOTTED COLONY
WALLSNOT APPLICABLE BEING PLOTTED COLONY
CEILINGNOT APPLICABLE BEING PLOTTED COLONY
COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
SANITARY WARE/CP FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
KITCHEN
FLOORNOT APPLICABLE BEING PLOTTED COLONY
WALLSNOT APPLICABLE BEING PLOTTED COLONY
CEILINGNOT APPLICABLE BEING PLOTTED COLONY
COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
KITCHEN APPLIANCESNOT APPLICABLE BEING PLOTTED COLONY
SIT-OUTS
FLOORNOT APPLICABLE BEING PLOTTED COLONY
WALLS & CEILINGNOT APPLICABLE BEING PLOTTED COLONY
RAILINGSNOT APPLICABLE BEING PLOTTED COLONY
FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
BED ROOMS
FLOORNOT APPLICABLE BEING PLOTTED COLONY
WALLSNOT APPLICABLE BEING PLOTTED COLONY
CEILINGNOT APPLICABLE BEING PLOTTED COLONY
WARDROBESNOT APPLICABLE BEING PLOTTED COLONY
MASTER TOILET
FLOORNOT APPLICABLE BEING PLOTTED COLONY
WALLSNOT APPLICABLE BEING PLOTTED COLONY
CEILINGNOT APPLICABLE BEING PLOTTED COLONY
COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
SANITARY WARE/CP FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
FITTING/FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
MASTER BEDROOM/DRESSROOM
FLOORNOT APPLICABLE BEING PLOTTED COLONY
WALLSNOT APPLICABLE BEING PLOTTED COLONY
CEILINGNOT APPLICABLE BEING PLOTTED COLONY
MODULAR WARDROBESNOT APPLICABLE BEING PLOTTED COLONY
LIVING/DINING/FOYER/FAMILY LOUNGE
FLOORNOT APPLICABLE BEING PLOTTED COLONY
WALLSNOT APPLICABLE BEING PLOTTED COLONY
CEILINGNOT APPLICABLE BEING PLOTTED COLONY
UTILITY ROOMS/UTILITY BALCONY/TOILET
FLOORNOT APPLICABLE BEING PLOTTED COLONY
WALLS & CEILINGNOT APPLICABLE BEING PLOTTED COLONY
TOILETNOT APPLICABLE BEING PLOTTED COLONY
BALCONYNOT APPLICABLE BEING PLOTTED COLONY

Fee Details

Payment 1
amount:354000
cheque no:32502
draft date:29-04-2024
payable to:HRERA Panchkula
payee bank:DD NO. 32502 OF RS. 1,86,984/- & DD NO. 32797 DT 13.05.24- OF RS. 1,67,016/- (ENCLOSED)