ONGOINGActive

RAHEJA TRINITY

GURUGRAM, GURGAON
10-02-2020
Launch Date
ONGOING
Type
2022-07-25
Completion Date

Overview

Launch Date

10-02-2020

Completion Date

2022-07-25

RERA ID

RERA-GRG-387-2019

Basic Details

Project NameRAHEJA TRINITY
Project IDRERA-GRG-387-2019
Project TypeONGOING
Applicant TypeCompany
Submission Date10-02-2020 11:25:39 AM
Builder NameRAHEJA DEVELOPERS LTD.
CINU45400DL1990PLC042200
PANXXXX468E
Emailcompliances@raheja.com
Websitehttp://raheja.com
Phone (Mobile)9971091937
Phone (Landline)Not specified
Registered AddressRAHEJA DEVELOPERS LTD. W4D,2O4/5, KESHAV KUNJ, WESTERN AVENUE, CARIAPPA MARG, SAINIK FARMS, NEW DETHI- 110062
Project AddressSECTOR-84, GURUGRAM
DistrictGURUGRAM
TehsilGURGAON

Bank Details

Bank NamePUNJAB NATIONAL BANK, KHANPUR, NEW DELHI
Account Number4447002100000095
IFSC CodePUNB0151400
MICR Code110024056
Branch Code151400

Account Related Information

Annex copy of the balance sheet of last 3 yearsYes
In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.Yes
Name and address of the person/persons who would ordinarily be operating the account (Change at any time must be intimated to the Authority)Navin M. Raheja
Attach certificate issued by a Chartered Accountant that the applicant has not defaulted in its debt liabilities in the past five years in folder D. (In case of default, give details)Not specified

Development Details

Land Area2.281 (Acre)
Proposed FAR3.98
Permissible FAR3.99
Total Licensed Land2.281 (Acre)

Land Usage

PLOTS TO BE SOLD0
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
CONSTRUCTION OF ROADS2839
PAVEMENTS479.355
PARKS AND PLAYGROUNDS0
GREEN BELTS443.51
VEHICLE PARKINGS625
ELECTRICITY SUB-STATION198
CLUB HOUSE0
SEWAGE AND SOLID WASTE TREATMENT FACILITY277
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
ANY OTHER0
SHOPS4844
Total9705.865

Cost Details

Land Cost11725 Lakhs
Other Cost5547 Lakhs
Estimated Project Cost24100 Lakhs
Estimated Infrastructure Cost1858 Lakhs
Estimated Apartment Construction Cost4970 Lakhs

Documents

DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.

Uploaded on: 18-01-2020

A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS

Uploaded on: 18-01-2020

COPY OF LICENSE ALONG WITH SCHEDULE OF LAND

Uploaded on: 18-01-2020

CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT

Uploaded on: 18-01-2020

IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN

Uploaded on: 18-01-2020

DEMARCATION PLAN

Uploaded on: 18-01-2020

DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD

Uploaded on: 18-01-2020

ZONING PLAN

Uploaded on: 18-01-2020

IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN

Uploaded on: 18-01-2020

NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT

Uploaded on: 18-01-2020

Statutory Approvals

LICENSE NO. 26 OF 2013Date: 17-05-2013Status: ALREADY BEEN OBTAINED
AAI PERMISSIONDate: 30-05-2016Status: ALREADY BEEN OBTAINED
CTE EXTENSIONDate: 24-06-2017Status: ALREADY BEEN OBTAINED
ENVIRONMENT CLEARANCEDate: 17-10-2014Status: ALREADY BEEN OBTAINED
FOREST NOCDate: 28-02-2014Status: ALREADY BEEN OBTAINED
WATER SUPPLYDate: 03-10-2013Status: ALREADY BEEN OBTAINED
Lay out PlanApproved: No
Demarcation PlanApproved: Yes
Zoning PlanApproved: Yes
Building PlanApproved: Yes
Site PlanApproved: Yes
Floor PlanApproved: Yes
Apartment PlansApproved: No
Elevation SectionApproved: Yes
Detail of Permissible FARApproved: No
Detail of covered area achieved FARApproved: No
ROADS AND PAVEMENT PLANApproved: No
ELECTRICITY SUPPLY PLANApproved: No
WATER SUPPLY PLANApproved: No
SEWERAGE AND GARBAGE DISPOSAL PLANApproved: No
STROM WATER DRAINAGEApproved: No
10% LAND TO BE TRANSFERRED TO THE GOVT. FOR COMMUNITY FACILITYApproved: No
STREET LIGHTING PLANApproved: No
PARKING PLANApproved: No

Facilities

INTERNAL ROADS AND PAVEMENTSAS PER PROJECT REPORT
WATER SUPPLY SYSTEMAS PER PROJECT REPORT
STORM WATER DRAINAGEAS PER PROJECT REPORT
ELECTRICITY SUPPLY SYSTEMAS PER PROJECT REPORT
SEWAGE TREATMENT & GARBAGE DISPOSALAS PER PROJECT REPORT
STREET LIGHTINGAS PER PROJECT REPORT
SECURITY AND FIRE FIGHTINGAS PER PROJECT REPORT
PLAYGROUNDS AND PARKSAS PER PROJECT REPORT
CLUB HOUSE/COMMUNITY CENTREYET TO BE PREPARED
SHOPPING AREAYET TO BE PREPARED
RENEWABLE ENERGY SYSTEMYET TO BE PREPARED
SCHOOLYET TO BE PREPARED
HOSPITAL/DISPENSARYYET TO BE PREPARED
ANY OTHERYET TO BE PREPARED
SEWERAGE SYSTEMAS PER PROJECT REPORT
PARKINGAS PER PROJECT REPORT

NOC

ROADSProvider: HUDA/GMDAApproval Status: Pending
WATER SUPPLYProvider: GMDAApproval Status: Approved
ELECTRICITYProvider: DHBVNApproval Status: Pending
SEWAGE DISPOSALProvider: GMDAApproval Status: Pending
STORM WATER DRAINAGEProvider: GMDAApproval Status: Pending

Project Team

Authorized Representative

SHREYA GOEL
Name
SHREYA GOEL
PAN
XXXX270R
Email
N/A
Mobile
9971091932
Landline
N/A
Address
I-843 A Palam Vihar Gurugram Haryana- 122017

Managing Director/CEO

NAVIN M RAHEJA
Name
NAVIN M RAHEJA
PAN
XXXX209H
Email
N/A
Mobile
9971091904
Landline
N/A
Address
150A Central Avenue Sainik Farms Khanpur South Delhi- 110062

Directors

SANGEETA KUMAR
Name
SANGEETA KUMAR
PAN
XXXX953N
Email
N/A
Mobile
9999666926
Landline
N/A
Address
D-163A FF Enclave Neb Sarai Delhi- 110068
SANJANA RANA
Name
SANJANA RANA
PAN
XXXX291K
Email
N/A
Mobile
9810009540
Landline
N/A
Address
H.No. 111 Khasra no. 364 Mandir Wali Lal Kothi Neb Sarai Delhi- 110068

Contact Details

Project ContactEmail: compliances@raheja.comMobile: 9971091904Landline: N/A
Project Contact PersonName: AJAY MOHANTYEmail: compliances@raheja.comMobile: 9971091904Landline: N/A

Land Details

Land Area2.281 (Acre)
Proposed FAR3.98
Permissible FAR3.99
Total Licensed Land2.281 (Acre)

Land Usage

Land Cost11725 Lakhs
Other Cost5547 Lakhs
Estimated Project Cost24100 Lakhs
Estimated Infrastructure Cost1858 Lakhs
Estimated Apartment Construction Cost4970 Lakhs

Total Infrastructure Expenditure

ParticularsExpenditure (in Lakhs)
Other0
Shopping area0
Roads & Pavements0
Water Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Electricity Supply System0
Clubhouse/community centres0
Sewerage treatment & garbage disposal0

Other Details

Construction Specifications

FLOORING DETAILS OF VARIOUS PARTS OF HOUSEGRANITE/MARBLE/VITRIFIED TILES IN COMMON AREAS
WALL FINISHING DETAILSN.A.
KITCHEN DETAILSN.A.
BATHROOM FITTINGSVITRIFIED/CERAMIC TILE FLOORING/WALLS, HIGH QUALITY CP FITTING AND ACEESSORIES
WOOD WORK ETCN.A.
DOORS AND WINDOS FRAMESN.A.
GLASS WORKN.A.
ELECTRIC FITTINGSN.A.
CONDUCTING AND WIRING DETAILSN.A.
CUPBOARD DETAILSN.A.
WATER STORAGEN.A.
LIFT DETAILSMODERN HIGH CLASS LIFTS
EXTERNAL GLAZINGSN.A.
WINDOWS/GLAZINGSN.A.
DOORSN.A.
MAIN DOORSN.A.
INTERNAL DOORSN.A.
AIR CONDITIONINGN.A.
ELECTRICAL FITTINGSINTERNATIONAL STANDARDS ELECTRICAL WIRING AND OUTLETS, SEPARATE METERING FOR EACH SHOP. POWER BACKUP.
CNG PIPE LINEN.A.
PROVISION OF WIFI AND BROADBAND FACILITYN.A.
EXTERNAL FINISHING/COLOUR SCHEMESTONE CLADDING, ACP AND GLASS FACADE/GRIT FINISH/TEXTURE PAINTS
INTERNAL FINISHINGN.A.

Unit-wise Specifications

TOILET
FLOORN.A.
WALLSN.A.
CEILINGN.A.
COUNTERSN.A.
SANITARY WARE/CP FITTINGSN.A.
FIXTURESN.A.
KITCHEN
FLOORN.A.
WALLSN.A.
CEILINGN.A.
COUNTERSN.A.
FIXTURESN.A.
KITCHEN APPLIANCESN.A.
SIT-OUTS
FLOORN.A.
WALLS & CEILINGN.A.
RAILINGSN.A.
FIXTURESN.A.
BED ROOMS
FLOORN.A.
WALLSN.A.
CEILINGN.A.
WARDROBESN.A.
MASTER TOILET
FLOORN.A.
WALLSN.A.
CEILINGN.A.
COUNTERSN.A.
SANITARY WARE/CP FITTINGSN.A.
FITTING/FIXTURESN.A.
MASTER BEDROOM/DRESSROOM
FLOORN.A.
WALLSN.A.
CEILINGN.A.
MODULAR WARDROBESN.A.
LIVING/DINING/FOYER/FAMILY LOUNGE
FLOORN.A.
WALLSN.A.
CEILINGN.A.
UTILITY ROOMS/UTILITY BALCONY/TOILET
FLOORN.A.
WALLS & CEILINGN.A.
TOILETN.A.
BALCONYN.A.

Fee Details

Payment 1
amount:486000
cheque no:513468
draft date:27-06-2017
payable to:HRERA Gurugram
payee bank:ICICI BANK