Launch Date
Completion Date
RERA ID
25.541055
78.507803
THIS IS A PMAY – URBAN MULTISTOREY PROJECT SO THERE ARE NO PLOTS FOR SALE
THERE IS NO PROVISION FOR BOUNDARY WALL IN THIS PROJECT
Bitumen road will be constructed in this site.
THERE IS NO REQUIREMENT OF FOOTPATHS AS PER DEVELOPMENT AUTHORITY RULES
THIS SHELL BE PROVIDED BY THE PROMOTER ITSELF
Centralized Sewerage system shall be Provided. All Sewerage water shall go to STP.
Storm water system shall be Provided. Storm water from Roads and other landscape area shall connect to the Storm water drain channel and go to the Rain water harvesting Pit for recharging the Ground water.
There are 5 parks (green area) Including small and Big in this site.
There are 3 type of trees provided in site which are kachnar, gulmauhar and neem.
We have design the system as per local electricity Board and consider centralized Transformer,HT panel,LT Panel and DG backup for common service like External lighting,STP,Pump room etc
THERE IS NO PROVISION FOR COMMUNITY BUILDING IN THIS SITE
Centralized Sewerage system shall be Provided. All Sewerage water shall be go to the STP.
There are a proper garbage collection area provided for the solid waste management.
- A well designed rain water harvesting system shall be provided for the whole site to conserve water.
We will use LED lights fitting in external area . In STP and Pump room all the equipment shall have energy efficient motor.
NOT REQUIRED AS PER NORMS
NOT APPLICABLE
NOT REQUIRED AS PER NORMS
NOT APPLICABLE
Showing 6 blocks with 24 units
Total Carpet Area
69698.97 m²
750232.74 ft²
Total Units
1180
1 different types
Blocks & Floors
6
4 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
19630.00 m²
211295.36 ft²