NewActive

Valencia Towers- Phase 2

Lucknow, Uttar Pradesh
20-07-2029Completion
NewType
LucknowDistrict
52562 LCost

Basic Details

Project Type:New
Project Category:Residential
Total area in round figure (Sq.mt.):19793
Project Name:Valencia Towers- Phase 2
Registration Fee (in Rs.):104000
Address:Plot No. GH-17, Baghamau, Integrated Township Shalimar One World, Lucknow
Village/Locality/Sector etc.:Baghamau
State:Uttar Pradesh
Project Duration (In month):59
District:Lucknow
Original Start Date:-
Tehsil:Lucknow
Proposed Start Date:02-09-2024
Sanctioning Competent Authority:Lucknow Development Authority
Project Cost (in Lacs):52562
Proposed Completion Date:20-07-2029

Location

Latitude

26.826907

Longitude

81.022261

Bank Details

Account Details
Name of the Account:SLPL - COLL A/c- VALENCIA TOWERS - PHASE 2
Account Number:43191431289
Bank Name:STATE BANK OF INDIA
Branch Name:COMMERCIAL BRANCH, LUCKNOW
Branch Address:6A, Way Road, Gokhle Marg, Lucknow, UP-226001
IFSC Code:SBIN0004166
Branch District:Lucknow
Branch State:Select
Branch Email Address:sbi.04166@sbi.co.in
Separate Account Details
Name of the Account:SLPL - SEP A/c- VALENCIA TOWERS -PHASE 2
Account Number:43191432782
Bank Name:STATE BANK OF INDIA
Branch Name:COMMERCIAL BRANCH, LUCKNOW
Branch Address:6A, Way Road, Gokhle Marg, Lucknow, UP-226001
Branch State:Uttar Pradesh
Branch District:Lucknow
IFSC Code:SBIN0004166
Transaction Account Details
Name of the Account:SLPL - TRANS A/c- VALENCIA TOWERS -PHASE 2
Account Number:43191433548
Bank Name:STATE BANK OF INDIA
Branch Name:COMMERCIAL BRANCH, LUCKNOW
Branch Address:6A, Way Road, Gokhle Marg, Lucknow, UP-226001
Branch State:Uttar Pradesh
Branch District:Lucknow
IFSC Code:SBIN0004166

Development Works

Demarcation of Plots

This is one plot polygon shaped abutting 9 mtr. Internal road. Site has one entrance and one exit from 45 mtr road to south side. Site is surrounded by greens from East and West side and other plot from North side.

Boundary Wall

1.8 - 2.1m high and 200 mm thick Boundary wall designed. Brick Work of 9inches and rcc work in column and beam may be used as per design. Entrance and exit gates are developed with boundary.

Road Work

Trimix finish/ bitumen will be used as per design suggested by the Architect for internal road.

Footpaths

All internal roads will have narrow footpath with matt finish tiles pavers or equivalent finishes.

Water Supply Including Drinking Water Facilities

All apartments shall be provided with domestic water for household activities and STP treated water for flushing. Clear water may also be used and user can have their individual RO system as per their requirement. The STP treated water shall also be supplied for irrigation purposes. For the same water tanks are getting created in underground and on terrace. Separate tanks are provided for fire water.

Sewer System

Centralized Sewerage system shall be Provided. All Sewerage water shall be go to the STP for treatment. after treatment ,water shall be recycled and it will use in gardening, flush tanks and vehicle washing, overflow from the STP shall be connect with the Municipal sewerage system.

Drain

Storm water system shall be Provided. Storm water from Roads and other landscape area shall be connected to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connect with Municipal drain line.

Parks

There are significant green area including green parks,Tree Boulevard, Green Mounds, play areas for childrens and different recreational activities.

Tree Planting

The trees of category ornamental ,shady and native species shall be planted in the entire project as per the species recommended in the landscape in order to maintain greenery and natural view.

Design For Electric Supply Including Street Lighting

We have designed the system as per local electricity Board and consider centralized Transformer,HT panel,LT Panel,Feeder Pillar and DG back for common service like External lighting with timer control,STP,Pump room etc

Community Buildings

A common multipurpose hall connected through previous phase at ground floor with the amenities viz. Jacuzzi,gynasium,spa,beauty salon, indor games etc shall be provided.

Treatment and Disposal System of Sewage and Sullage water

A common Centralized Sewerage system for entire project and all towers shall be connected to STP . All Sewerage water shall go to the STP for treatment after treatment ,water shall be recycle and it will use in gardening, flush tanks and vehicle washing, overflow from the STP shall be connect with the Municipal sewerage system.

Solid Waste Management And Disposal System

Project shall have  waste segregation area. The solid waste shall be encouraged for segregation. Dustbins shall be provided for segregated waste in the common areas within the campus and other waste shall be handed over to the government vendors for further disposal.

Water Conservation System

A well designed rain water harvesting system shall be provided for the whole building complex to conserve water by ensuring adequate nos. of recharge pits

Energy Management System Including Use of Renewable Energy

We will use LED lights fitting in external area as well as solar lights. In STP and Pump room all the equipment shall have energy efficient motor. Also timer controlled panels shall be used for efficient energy management.

Fire Protection And Fire Safety System

All Fire norms shall be followed as per NBC Part 4 code and approval of fire department. fire sprinklers,FHC with pumps are provided as per norms.

Social Infrastructure And Other Public Amenities Including Public Health Services

NA

Emergency Evacuation Services

Fire Staircase is provided in the each building, basements have access and exit in case of emergency. Dedicated assembly areas defined in the campus. Adequate signage is also provided.

Other Miscellaneous Work

Other amenities viz. Swimming pool for Adults and kids,Change rooms, Meeting Rooms,Pergola With Seating,Lush Green,Kids play area,MuGA Court,Fountain,Private seating zone,Jogging track,Pet Park,Deck area with seating,Tree Boulevard,Tennis Court,Outdoor GYM,Green Mounds and many more also propvided for recreational activities.

New Documents

Lease Deed

No: 9652 | Date: 24-06-2015

Registry Document

No: 5396 | Date: 18-04-2015

Sale Deed

No: 15995 | Date: 23-10-2013

Sale Deed

No: 14340 | Date: 15-09-2018

Sale Deed

No: 4664 | Date: 06-05-2024

Extract of Khatauni

No: 1422-1427 | Date: -

Extract of Khatauni

No: 1422-1427 | Date: -

Extract of Khatauni

No: 1422-1427 | Date: -

Extract of Khatauni

No: 1422-1427 | Date: -

Extract of Khatauni

No: 1422-1427 | Date: -

Extract of Khatauni

No: 1422-1427 | Date: -

Extract of Khatauni

No: 1422-1427 | Date: -

Extract of Khatauni

No: 1422-1427 | Date: -

Extract of Khatauni

No: 1422-1427 | Date: -

Sale Deed

No: 9076 | Date: 01-08-2016

Extract of Khatauni

No: Land Area Chart | Date: -

Extract of Khatauni

No: Affidavit for GS Land | Date: -

Extract of Khatauni

No: Promoter Name Change- ANS Developers to Shalimar Lakecity_MCA | Date: -

Extract of Khatauni

No: Application for Promoter name change | Date: -

Extract of Khatauni

No: Request for CIN update | Date: -

Extract of Khatauni

No: Affidavit for Name Change | Date: -

Uploaded Documents

Other Plan(If Any)

Other Plan(If Any)

Proforma of Completion Certificate(Occupancy)

Affidavit

Details of Encumbrances

Uploaded: 31-07-2024

Commencement Certificate

Uploaded: 29-07-2024

Other Plan(If Any)

Uploaded: 31-07-2024

Proforma of Application Form

Uploaded: 31-07-2024

Proforma of Allotment Letter

Uploaded: 07-08-2024

Proforma of Conveyance Deed

Uploaded: 31-07-2024

Waste Disposal Plan

Uploaded: 29-07-2024

Water Supply Plan

Uploaded: 29-07-2024

Electricity Supply Plan

Uploaded: 29-07-2024

Development Work Plan

Uploaded: 31-07-2024

Affidavit

Uploaded: 07-08-2024

CA CERTIFICATE

Uploaded: 31-07-2024

ARCHITECT CERTIFICATE

Uploaded: 31-07-2024

ENGINEERS CERTIFICATE

Uploaded: 31-07-2024

Other

Uploaded: 05-09-2024

Proforma of Agreement for Sale

Uploaded: 31-07-2024

Permits

Orignal Permit NoGroup Housing/12543/LDA/BP/24-25/1065/02072024
Orignal Permit Date27-07-2024
Valid Upto26-07-2029
Permit Extendable Upto26-07-2032
End Date20-07-2029

Project Team

Contractor Name (if any)Mr. Sanjeev Saluja (Sawhney Buildwell LLP)
Contractor Address129-C, Gobind Nagar, Race Course, Dehradun, Uttarakhand, India – 248 001
Architect NameShivam Srivastava
Architect AddressVibhuti Khand Gomti Nagar, Lucknow
Architect Licence NumberCA/2010/50742
Structural Engineer NameMr. Pankish Goel (TPC Technical Projects Consultants Pvt. Ltd.)
Structural Engineer AddressB-74, Sector-57, Noida-201301
Mobile number(Project Co-ordinator)8005497688

Project Land Details

AFS

Showing 3 blocks with 209 units

Property Summary

Total Area

69827.16

751612.57 ft²

Total Units

396

3 different types

Blocks & Floors

3

34 floors across all blocks

Parking

0

0 garages, 0 open

Average unit size:176.33
Balconies:711
Parking ratio:0.00 per unit

Block Tower D

69 units

Block TOWER E

69 units

Block TOWER F

71 units

Khasra Details

Total Area

28220.00

303757.26 ft²

1 plot
Khasra
Type:Khasra
Khasra/Plot No:Part of Khasras 47, 70, 71, 72, 73, 74, 75, 76, 78, 87, 88, 89
Area(In Sq. Mt.):28220

Other Details

Contractor Name (if any):Mr. Sanjeev Saluja (Sawhney Buildwell LLP)
Contractor Address:129-C, Gobind Nagar, Race Course, Dehradun, Uttarakhand, India – 248 001
Architect Name:Shivam Srivastava
Architect Address:Vibhuti Khand Gomti Nagar, Lucknow
Architect Licence Number:CA/2010/50742
Structural Engineer Name:Mr. Pankish Goel (TPC Technical Projects Consultants Pvt. Ltd.)
Structural Engineer Address:B-74, Sector-57, Noida-201301
Mobile number(Project Co-ordinator):8005497688